# How to Make a School Work and Financial Plan (WFP)

To make a school work and financial plan (WFP), take PPAs from the SIP and AIP, fill each column, spread costs by month to equal the MOOE, align and review.

This is the Markdown copy of [How to Make a School Work and Financial Plan (WFP)](https://nash.com.ph/blog/make-school-work-financial-plan), an article on the NASH Reviewer Blog by Mark Anthony Llego, published Nov 26, 2026. Topics: School leadership, Aspiring school heads. NASH Reviewer is an independent practice platform not affiliated with DepEd, BHROD, or NEAP.

To make a school work and financial plan (WFP), take the programs, projects and activities (PPAs) of the school's approved School Improvement Plan (SIP) and Annual Implementation Plan (AIP), give each one an output, indicators, monthly targets and a cost on your division's template, and check that the months add up to the school's allocation before the school head signs. No DepEd order in force sets a WFP form for a school's Maintenance and Other Operating Expenses (MOOE): for a school, the AIP does the work of the WFP, since school MOOE funds the activities "specifically determined in the Annual Implementation Plan (AIP) which shall follow the calendar year format (Annex 1) of the school" ([DepEd Order No. 008, s. 2019](https://www.deped.gov.ph/2019/05/02/may-2-2019-do-008-s-2019-revised-implementing-guidelines-on-the-direct-release-use-monitoring-and-reporting-of-maintenance-and-other-operating-expenses-allocation-of-schools-including-other-fu/), Sec. V.D.1).

Many Schools Division Offices (SDOs) still ask every school for a WFP each year, on a template of their own, between September and December for the next fiscal year. That is division practice, so the division's memorandum decides the form, the deadline, the attachments and who signs. What a WFP is, where the term comes from and which schools must prepare one are covered in [the WFP's meaning and rules in DepEd](https://nash.com.ph/blog/work-financial-plan-deped).

The worked example throughout is Project Basa-Galing, a reading remediation project of Liwayway Elementary School, an invented Kindergarten to Grade 6 school of about 600 learners. Its fiscal year 2027 MOOE is taken as ₱1,262,000, the median FY 2026 allocation of the 913 public elementary schools that are not implementing units and had 550 to 650 learners in SY 2025-2026; a real school plans on the figure its division sends. The rules below are stated as of November 26, 2026.

## Key findings

- **The AIP comes first.** School MOOE pays for "activities as identified in the approved School Improvement Plan (SIP) for implementation in the current year and as specifically determined in the Annual Implementation Plan (AIP)", "subject to availability of funds and prioritization of mandatory expense items" (DO 008, s. 2019, Sec. V.D and V.D.1). A WFP row that traces to no AIP line has nothing to stand on.
- **Divisions use two families of templates.** Planning sheets ask for the BEDP pillar or priority improvement area, the program or activity, its output, indicators and physical targets, the schedule and the resources needed (Imus City, DM 768, s. 2025, Encl. 1; Abra's and Tayabas City's program-fund templates; Pasay City South High School's FY 2021 WFP); budget sheets ask for the object of expenditure (with its UACS code in some), a target, the total, tax withheld, the net and each month's amount (Bulacan's FY 2027 workbook; Nueva Vizcaya's FY 2027 request-for-subsidy sheet). Where a division asks for both, make them agree.
- **The fiscal year crosses two school years.** FY 2027 runs January 1 to December 31, 2027 (DO 008, s. 2019, Sec. I.3). Term 3 of SY 2026-2027 runs January 4 to April 8, 2027, and DepEd had not issued the SY 2027-2028 calendar as of November 26, 2026 ([DO 009, s. 2026](https://www.deped.gov.ph/2026/04/16/april-16-2026-do-009-s-2026-guidelines-on-the-implementation-of-the-three-term-school-calendar-in-basic-education/), item 4 and Annex B).
- **The months become cash.** A school's MOOE cash "will be determined by the expenditures needed based on its MDP", its monthly disbursement program ([DO 029, s. 2019](https://www.deped.gov.ph/2019/10/17/october-17-2019-do-029-s-2019-procedural-guidelines-on-the-management-of-cash-advances-for-school-maintenance-and-other-operating-expenses-and-program-funds-of-non-implementing-units-pursuant-to/), item 18). Each amount goes in the month it will be paid.
- **Division sheets check the totals.** Divisions plan on the school MOOE in the National Expenditure Program (NEP) and check that the WFP total equals it (Region VIII, RM 1047, s. 2026, item 4; Imus City, DM 768, s. 2025, Encl. 3, item 3); Bulacan's sheet also checks it against the School Operating Budget, and Imus City's tool against the Project Procurement Management Plan (PPMP) and the Annual Procurement Plan (APP) (item 13). Nueva Vizcaya's request-for-subsidy sheet refuses any "difference until the last centavo" (SDO Nueva Vizcaya, DM 460, s. 2026).
- **Review every quarter.** The school head conducts a "quarterly Program Implementation Review (PIR) in the school to track physical and financial accomplishments" ([DO 029, s. 2022](https://www.deped.gov.ph/2022/06/22/june-20-2022-do-029-s-2022-adoption-of-the-basic-education-monitoring-and-evaluation-framework/), Sec. VIII, item f). The ten working days to revise a WFP after a PIR bind only the offices that plan in DepEd's Program Management Information System (PMIS); no national text sets a school's deadline.

## What you need before making the WFP

A school WFP is assembled from documents the school and the division already hold. Gather these before the planning team meets.

| Input | Where it comes from | What the WFP takes from it |
| --- | --- | --- |
| Approved SIP | The school's three-year plan ([DepEd Order No. 44, s. 2015](https://www.deped.gov.ph/2015/09/29/do-44-s-2015-guidelines-on-the-enhanced-school-improvement-planning-sip-process-and-the-school-report-card-src/)) | The Priority Improvement Areas (PIAs), general objectives and projects every row must trace to |
| AIP for the fiscal year | Prepared by the School-Community Planning Team "from the general objectives set in the SIP" (SIP Guidebook, Step 8) | The year's activities, outputs, persons responsible, schedule and budget by source |
| The school's MOOE figure | The division's list of school allocations under the NEP, sent to schools from August to November | The ceiling; adjusted once the General Appropriations Act (GAA) is enacted |
| Special Education Fund (SEF) items | The Local School Board's approved SEF budget; schools request by August 31 and the municipal or city school board approves by October 31, the circular's indicative timelines ([Joint Circular No. 01, s. 2025](https://www.deped.gov.ph/2026/03/03/deped-dbm-dilg-joint-memorandum-circular-no-01-s-2025-omnibus-guidelines-on-the-use-of-the-special-education-fund-sef/), §6.8) | Rows the SEF pays for, by month |
| Canteen budget | The annual budget the school head prepares from expected canteen income, approved by the Schools Division Superintendent (SDS) "at the start of every school year" ([DepEd Order No. 8, s. 2007](https://www.deped.gov.ph/2007/02/06/do-8-s-2007-revised-implementing-guidelines-on-the-operation-and-management-of-school-canteens-in-public-elementary-and-secondary-schools/), item 6.7) | Rows paid from canteen net income |
| Other funds | Donations, PTA support, local government support and program funds the school must declare (DO 008, s. 2019, Sec. VI.A.1) | Rows by fund source, where the template has a fund column |
| Last year's results | The quarterly PIRs and the M&E records the school head keeps "in the preparation of SIP/AIP" (DO 029, s. 2022, Sec. VIII, item g) | What to continue, change or stop |
| Division priorities and template | The Division Education Development Plan (DEDP) and the division's memorandum and template | The pillar or priority column, the columns, the deadline and signatories |

The 2026 bills for electricity, water and internet belong on the table too: they show what the mandatory expenses will take before any project is planned. The SIP's steps and the AIP in DO 008's calendar-year format are set out in [DepEd School Improvement Plan (SIP): Steps, AIP and SRC](https://nash.com.ph/blog/deped-school-improvement-plan) and [School Improvement Plan Sample: SIP and AIP Templates](https://nash.com.ph/blog/school-improvement-plan-sample-sip-aip-template).

Program support funds that reach a school on their own release (the School Innovation and Improvement Fund, Special Needs Education support, computerization packages) usually come with their own forms. The SIIF for FY 2026 needs no proposal at all: recipient schools "shall ensure that planned activities are reflected in their approved School Improvement Plan (SIP) and Annual Implementation Plan (AIP)" ([DepEd Memorandum No. 048, s. 2026](https://www.deped.gov.ph/2026/08/03/august-3-2026-dm-048-s-2026-allocation-and-release-of-the-school-innovation-and-improvement-fund-to-non-implementing-unit-public-schools-to-strengthen-decentralization-practices-in-the-de/), Encl., Sec. III.1). Plan those funds on whatever form their release asks for, and keep them out of the MOOE total.

## Who prepares the school WFP

The school head prepares the WFP with the School-Community Planning Team (SPT), the team that prepares the SIP and the AIP. The SIP Guidebook asks for at least seven members: the school head as team leader and a student, teacher, parent, barangay or LGU representative, a member of the Barangay DRRM Committee and a member of the school's Child Protection Committee, with at least one member of the school governance council (DO 44, s. 2015, SIP Guidebook, Activity 1.2). [DepEd Order No. 026, s. 2022](https://www.deped.gov.ph/2022/06/17/june-17-2022-do-026-s-2022-implementing-guidelines-on-the-establishment-of-school-governance-council/) keeps the SPT and has the School Governance Council work with it on the SIP and the AIP.

Division templates put the school head on "Prepared by" (Bulacan's FY 2027 MOOE sheet, Abra's SIIF template, Tayabas City's Special Needs Education template), and Misamis Oriental's FY 2026 allocation memorandum had the WFP and the School Operating Budget "crafted by the School Planning Team" (DM 569, s. 2025). Divide the work: the administrative officer or bookkeeper fills the budget sheet, the teachers who run each project fill its planning row, and the school head checks and signs the whole. Keep the minutes of the meeting where the team settles the PPAs; they show that the team, not one person, made the plan.

## How to make a school WFP, step by step

A school WFP takes ten steps, from the division's memorandum to the plan the division approves.

1. **Read the division's memorandum and template.** Note the deadline, the columns, whether the total must equal the NEP figure, the tax rule, the attachments and the signatories. A division template, where one is prescribed, comes first.
2. **Set the ceiling.** Write the school's NEP-level MOOE figure at the top of the work sheet, and list the other funds the school will plan with.
3. **Budget the mandatory expenses first.** Mandatory expenses come before projects (DO 008, s. 2019, Sec. V.D): put in the year's electricity, water and internet from the 2026 bills.
4. **Take the PPAs from the AIP.** Each WFP row is an AIP line; drop anything that traces to no PIA or objective in the SIP.
5. **Write each row's output, indicators and targets.** Make each one countable, and split the targets by month or quarter.
6. **Schedule the row across the fiscal year.** Place activities on the school calendar of two school years, January to December.
7. **Cost each row and assign its object of expenditure and fund.** Price each item, choose a fund the rules allow (see [how to cost a WFP row and choose its fund](https://nash.com.ph/blog/wfp-budget-breakdown)), and flag the rows that need a purchase so they reach the PPMP.
8. **Spread each amount by month and check the totals.** Every row's months must add to its total, and the plan's total must equal the allocation.
9. **Trace each row.** Trace every row to its SIP objective, AIP line and the division's priority (Imus City's presentation template asks for the same trace by BEDP pillar).
10. **Assemble, sign and submit.** Attach what the division asks for, have the school head sign, submit by the deadline, present at the division's appraisal where it holds one, and revise where the reviewers comment.

## Choosing PPAs: only what traces to the SIP and AIP

A PPA belongs in the WFP when it is in the AIP and the AIP line traces to a PIA in the SIP. Division memoranda say the same in their own words: "It is expected that the 2027 Work and Financial Plan of each school is reflective of the programs, projects, and activities indicated in its School Improvement Plan" (SDO Kabankalan City, DM 321, s. 2026). Imus City's evaluation tool checks whether the WFP "indicated activities included in the AIP relative to the school improvement projects that address the Priority Improvement Areas (PIAs)" (DM 768, s. 2025, Encl. 3, item 2).

Several national orders tell schools to carry a program into the SIP and AIP, which is how it earns a WFP row:

| Program | What the order says | Order |
| --- | --- | --- |
| Learning Action Cells | The LAC Plan "should be integrated or linked with the School Improvement Plan (SIP) or Annual Implementation Plan"; funds "may be sourced from the school's Maintenance and Other Operating Expenses (MOOE)" | [DO 35, s. 2016](https://www.deped.gov.ph/2016/06/07/do-35-s-2016-the-learning-action-cell-as-a-k-to-12-basic-education-program-school-based-continuing-professional-development-strategy-for-the-improvement-of-teaching-and-learning/), items 11 and 17.10 |
| ARAL Program | "The ARAL Program and its activities shall be included in the School Improvement Plan and Annual Implementation Plan." | [DO 018, s. 2025](https://www.deped.gov.ph/2025/06/13/june-13-2025-do-018-s-2025-implementing-guidelines-of-the-academic-recovery-and-accessible-learning-program/), item 80 |
| School Sports Club | MOOE may fund the club "provided that SSC activities are explicitly included in both the School Improvement Plan (SIP) and the Annual Improvement Plan [sic] (AIP)" | [DO 022, s. 2025](https://www.deped.gov.ph/2025/08/07/august-7-2025-do-022-s-2025-policy-guidelines-on-the-institutionalization-of-the-school-sports-club-in-public-schools/), Sec. V.E, item 3 |
| Tobacco control | Schools "incorporate it into the Work and Financial Plan (WFP) and Annual Implementation Plan (AIP)" after a self-assessment | [DO 48, s. 2016](https://www.deped.gov.ph/2016/06/28/do-48-s-2016-policy-and-guidelines-on-comprehensive-tobacco-control/), Sec. V.G, item 6 |
| School-Based Mental Health Program | Each level includes the program's PPAs "in their respective strategic plans, Work and Financial Plans, and in the schools' School Improvement Plan and Annual Implementation Plan" | [DO 024, s. 2026](https://www.deped.gov.ph/2026/11/26/november-26-2026-do-024-s-2026-guidelines-on-the-implementation-of-the-school-based-mental-health-program/), Sec. V.f |

Three money rules then decide which rows MOOE can carry. Mandatory expenses come first, since the other uses of MOOE are "subject to availability of funds and prioritization of mandatory expense items" (DO 008, s. 2019, Sec. V.D). DO 008 does not list those items; DepEd's PMIS order, written for its offices, names "electricity, water, cable, telecommunication, and other mandatory expenses" (DO 011, s. 2021, Part V.C.1.d). MOOE never buys school seats or teachers' tables and chairs (except furniture the higher offices do not provide), textbooks, or other supplementary learning resources such as review materials (Sec. V.D.6). And an item of ₱50,000 or more a unit is property, plant and equipment under [COA Circular No. 2022-004](https://coa.gov.ph/wpfd_file/coa-circular-no-2022-004-may-31-2022/), not a supplies expense, although DO 008 still prints ₱15,000 for semi-expendable items (Sec. V.D.5). The [fund rules for each WFP row](https://nash.com.ph/blog/wfp-budget-breakdown), SEF and canteen included, are set out with how to cost it.

## The WFP columns, one by one

Division templates come in two families. A planning sheet describes what the school will deliver; a budget sheet describes what it will spend, by object of expenditure and month. Some divisions ask for one kind; the PMIS sheet that implementing schools download where their region asks (Region X, RM 932, s. 2024) holds both in three parts. The entries below are Project Basa-Galing's, the row the [school WFP sample](https://nash.com.ph/blog/school-work-financial-plan-sample) sets out in full with the rest of Liwayway's plan.

### The planning columns

The rows below gather the columns of the public planning templates (Imus City's presentation template, Abra's and Tayabas City's program-fund templates, Pasay City South High School's FY 2021 WFP) and of the AIP itself; a division's sheet may ask for fewer.

| Column | What to write | Project Basa-Galing |
| --- | --- | --- |
| BEDP pillar or priority improvement area (Imus City; Abra) | The pillar of the Basic Education Development Plan (BEDP) 2030 (access, equity, quality, resiliency and well-being) or the enabling mechanism the row serves, or the SIP's priority improvement area, as the template asks | Quality (BEDP 2030 Pillar 3): foundational literacy |
| Program, project or activity | The PPA's title as the AIP names it | Project Basa-Galing: reading remediation for struggling readers in Grades 2 to 4 |
| Output | The thing delivered by the end of the year, stated as done | Struggling readers in Grades 2 to 4 given a term of reading remediation and reassessed |
| Activities | The steps that produce the output, in order | Group the learners by reading level; reproduce leveled passages and set up reading folders; hold 40-minute after-class sessions three times a week; reassess at the end of each term and report to parents; review attendance and levels at each quarterly PIR |
| Performance indicators | What will be counted to show that the output was delivered and the activities happened | Output: number of identified struggling readers given a full term of after-class reading sessions and reassessed at the end of the term. Activity: number of after-class reading sessions held |
| Physical targets | The number each indicator must reach, split by period | 60 learners: 30 in Term 3 of SY 2026-2027, 30 in Term 1 of SY 2027-2028; Term 2 continues with Term 1's learners still below grade level, who are counted once. 72 sessions: 24 in each of three terms |
| Schedule or time frame | The months the row runs | January to March 2027 and June to November 2027 |
| Persons responsible | Who carries the row out, by position | The school head, the school reading coordinator and the Grades 2 to 4 teachers who tutor |
| Resources needed | What the row needs to run: people, materials and places, and money | The tutors and the learners' parents; CRLA and Phil-IRI materials, leveled passages, a reading folder for each learner and a classroom after classes; five common-use supplies |
| Budget and fund source | The row's amount and where it comes from, where the template asks | ₱6,244.56, school MOOE |

On the team's working copy, mark the rows whose items must be bought or done by administration, so they go into the PPMP, which asks the same question: "Whether the implementation of the PAPs will require procurement or undertaken by administration" ([IRR of Republic Act No. 12009](https://www.gppb.gov.ph/ngpa-implementing-rules-and-regulations/), Sec. 7.7.1(a)). Project Basa-Galing's five supplies are bought from PS-DBM, so its row is marked. How a school plans and buys those items is in [School Procurement Under RA 12009](https://nash.com.ph/blog/deped-school-procurement-ra-12009) and, for PS-DBM supplies, [APP-CSE in DepEd](https://nash.com.ph/blog/app-cse-deped-ps-dbm).

### The budget columns

| Column | What to write | Project Basa-Galing |
| --- | --- | --- |
| Program, output or activity | The row's title, the same words as the planning sheet | Project Basa-Galing |
| Object of expenditure | The expense account, chosen from the template's list | Two lines: Office Supplies Expenses for the paper, cartolina, markers and folders; ICT Office Supplies Expenses for the ink cartridges |
| UACS code | The account's code in the Unified Accounts Code Structure, where the template asks | 5020301002 and 5020301001; Nueva Vizcaya's FY 2027 request sheet prints the account as 5020301000 |
| Target | The number of participants or beneficiaries | 60 learners, on both lines |
| Total amount | The row's cost for the year | ₱4,832.28 and ₱1,412.28: ₱6,244.56 for the row |
| Tax withheld | The taxes the school or division will withhold from payees, if the template asks per line | As the division's sheet sets it |
| Net of tax | The total less the tax withheld | As the sheet computes it |
| January to December | Each month's amount, often with quarter subtotals | Office supplies: January ₱1,724.65, June ₱1,724.65, September ₱1,382.98. ICT office supplies: ₱470.76 in each of those months. The row: ₱2,195.41, ₱2,195.41 and ₱1,853.74 |
| Checking | The total less the months, which must be zero | ₱0.00 on each line |

A row that spends from two objects takes one budget line per object, and Project Basa-Galing is one: its ink cartridges are ICT office supplies, the rest office supplies. Bulacan's FY 2027 sheet offers 56 objects in a dropdown and asks schools to "Enter your target number of participants or beneficiaries" and to "Distribute the budget across the months when the activity or expense will occur".

UACS object codes are ten digits: the account code of the Commission on Audit's Revised Chart of Accounts (eight digits) and two digits for a sub-object. Office Supplies Expenses is account 50203010; the UACS list splits it into 5020301001, ICT Office Supplies Expenses, and 5020301002, Office Supplies Expenses, while Nueva Vizcaya's FY 2027 request sheet prints the account as 5020301000. Booking the ink as ICT office supplies is the sample's reading: COA's Government Accounting Manual describes the Office Supplies Expenses account as covering office supplies "such as bond paper, ink" ([GAM, Vol. III, Ch. 3](https://www.coa.gov.ph/wp-content/uploads/abc-help/gam_3/3main.htm)), and the division's budget officer decides the code. Use the code the division's sheet gives, and ask the budget officer where its list and the UACS list differ.

The tax columns follow the division. A disbursement includes "the issuance of Tax Remittance Advice (TRA) for the remittance to BIR of taxes withheld from employees and suppliers" (DO 008, s. 2019, Sec. IV.3), so the tax withheld from a payment needs no cash in the school's account. Divisions handle it in two ways. Bulacan's FY 2027 sheet for non-implementing units, elementary and secondary, locks the tax column at zero, while its sheet for implementing units says "you can input your estimated tax for the year". Nueva Vizcaya's request sheet for FY 2027 and Misamis Oriental's FY 2026 allocation matrix take 5% off the NEP figure first and spread only the net. The division's accountant decides which applies.

### Where a division asks for both sheets

The two sheets describe one plan, so they meet at four points. The program or project title is the same on both. A planning row's budget equals the sum of its budget lines. The months in the planning row's schedule hold its physical targets, and the budget months hold its money; they need not be the same months, as the next section shows. And the planning sheet's target count and the budget sheet's "target" describe the same people.

### The three-part sheet

The WFP that DepEd's offices prepare in the PMIS "consists of the Physical Plan, Monthly Obligation Program, and Monthly Disbursement Program as prescribed by the Department of Budget and Management (DBM)" ([DO 011, s. 2021](https://www.deped.gov.ph/2021/02/24/february-24-2021-do-011-s-2021-guidelines-on-the-operationalization-of-the-program-management-information-system/), Part III, item r). Some schools use that shape: a public high school's FY 2021 WFP, published on the school's website, sets physical targets, obligations and disbursements by month for each PPA. On such a sheet, Project Basa-Galing's physical plan holds its sessions and learners by month, its obligation program the month each purchase is committed, and its disbursement program the month each is paid.

## How to write a measurable output, indicator and target

An output is a delivered thing, an indicator is what will be counted, and a target is the number it must reach by a date. The SIP Guidebook defines an output as "The concrete, tangible products that results from undertaking an activity" and asks that project objectives be "specific, measurable, attainable, realistic, time-bound" (DO 44, s. 2015, SIP Guidebook, Step 6). DBM describes a performance indicator as one that "can measure the quantity, quality or timeliness of outputs and outcomes" (DBM Circular Letter No. 2022-14, BED No. 2 instructions): a quantity indicator says "How much did we do?", a quality indicator "How well did we do it?", and a timeliness indicator whether the output came "as and when required" ([DBM National Budget Memorandum No. 156](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Memorandum/NATIONAL-BUDGET-MEMORANDUM-NO-156.pdf), BP Form B instructions).

| Column | Weak entry | Why it fails | Strong entry |
| --- | --- | --- | --- |
| Output | Reading program conducted | Names an activity, not a delivered thing | Struggling readers in Grades 2 to 4 given a term of reading remediation and reassessed |
| Output | Improved reading skills of learners | An outcome the row cannot promise alone, and nothing to count | (Keep for the SIP objective; the WFP output is the one above) |
| Output indicator | Reading program | Not a count | Number of identified struggling readers given a full term of sessions and reassessed |
| Activity indicator | Sessions conducted regularly | "Regularly" cannot be checked | Number of after-class reading sessions held |
| Physical target | 100% of learners | No base: 100% of which learners, by when? | 60 learners: 30 by March 2027, 30 by September 2027 |
| Physical target | Year-round | A time frame, not a number | 72 sessions: 24 in each of three terms |

Three habits make targets hold up. Base the count on the school's own data: the learners below grade level in the latest Comprehensive Rapid Literacy Assessment (CRLA) and Phil-IRI results, not a round number. Compute the activity target from the schedule, so that a reviewer can check it: eight weeks of three sessions is 24 a term, and DO 009, s. 2026 allows after-class remediation sessions "two (2) to four (4) times per week" (Encl., item 13). And split every target by the months or quarters the template has, since the quarterly review compares each quarter's accomplishment with its target.

## The fiscal year versus the school year

A WFP runs by fiscal year, January to December, and a school runs by school year, June to April. School MOOE is "valid for release and obligation for one fiscal year: that is from January 1 to December 31" (DO 008, s. 2019, Sec. I.3), although the FY 2026 GAA kept FY 2026 MOOE valid until December 31, 2027 ([DBM National Budget Circular No. 599](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Circular/NATIONAL-BUDGET-CIRCULAR-NO-599.pdf), item 3.3). Whether FY 2027 money gets the same extra year depends on the FY 2027 GAA, which had not been enacted as of November 26, 2026.

So an FY 2027 WFP holds two school years. Its January to April 8 is Term 3 of SY 2026-2027; April 9 to May 9 is the teachers' break; June 7 to 11 is Brigada Eskwela and enrollment (DO 009, s. 2026, item 4 and Annex B). From the day SY 2027-2028 opens, the row belongs to that school year, whose calendar DepEd issues by memorandum before it starts (item 4). Until it is issued, plan its months on SY 2026-2027's pattern and say so: Republic Act No. 11480 lets a school year open no earlier than the first Monday of June (June 7, 2027) and no later than the last day of August (DO 009, s. 2026, Encl., item 10). The sample assumes SY 2027-2028 opens in June, after Brigada week, as SY 2026-2027 opened on June 8, 2026 (item 4), and marks every month from June 2027 as assumed.

The money follows a different calendar from the work. Project Basa-Galing's sessions run from January to March and from July to November, but its money is spent in January, June and September, the months each term's supplies are bought. Put each amount in the month it will be paid: the school's cash is released on the monthly disbursement program "within the first week of every month or quarter" (DO 029, s. 2019, item 18), and DBM's Notice of Cash Allocation covers what non-implementing units need "corresponding to the amounts indicated in the approved Monthly Disbursement Program" (COA-DBM-DepEd Joint Circular No. 2019-1, item 6.2.1, enclosed in DO 029, s. 2019). A December purchase that slips into January lands in the next fiscal year's months.

**Project Basa-Galing across fiscal year 2027.** On the page, the reader picks the sessions a week (two to four, as DO 009, s. 2026 allows) and the month each term's supplies are bought, and the figure redraws the row's months, its quarter totals and its timing check. The sample opens at three sessions a week:

| Month | Where it falls | Sessions held (activity target) | Learners reassessed (output target) | Amount |
| --- | --- | --- | --- | --- |
| January 2027 | SY 2026-2027: Term 3 opens January 4 | 9 | 0 | ₱2,195.41 |
| February 2027 | SY 2026-2027: Term 3 | 12 | 0 | — |
| March 2027 | SY 2026-2027: Term 3; its Instructional Block ends March 23 | 3 | 30 | — |
| April 2027 | SY 2026-2027: Term 3 ends April 8; break from April 9 | 0 | 0 | — |
| May 2027 | Between school years: Teachers' break to May 9; intervention and training from May 10 | 0 | 0 | — |
| June 2027 | Between school years, then SY 2027-2028: Brigada Eskwela and enrollment, June 7 to 11; the school year opens after them (opening day not yet set) (assumed) | 0 | 0 | ₱2,195.41 |
| July 2027 | SY 2027-2028: Term 1; grouping from the beginning-of-year results, sessions from mid-July (assumed) | 9 | 0 | — |
| August 2027 | SY 2027-2028: Term 1 (assumed) | 12 | 0 | — |
| September 2027 | SY 2027-2028: Term 1's last sessions in the first week; Term 1 ends and Term 2 opens (assumed) | 3 | 30 | ₱1,853.74 |
| October 2027 | SY 2027-2028: Term 2 (assumed) | 12 | 0 | — |
| November 2027 | SY 2027-2028: Term 2 (assumed) | 12 | 0 | — |
| December 2027 | SY 2027-2028: Term 2 ends; year-end break (assumed) | 0 | 0 | — |

- Year: 72 sessions, 60 learners, ₱6,244.56; Q1 ₱2,195.41, Q2 ₱2,195.41, Q3 ₱1,853.74, Q4 ₱0.00.
- The months add to the row's total: ₱6,244.56 minus ₱6,244.56 is ₱0.00.
- Supplies for Term 3 of SY 2026-2027: bought in January, the month its sessions start.
- Supplies for Term 1 of SY 2027-2028: bought in June, before its sessions start in July.
- Supplies for Term 2 of SY 2027-2028: bought in September, before its sessions start in October.

Term 2 continues with Term 1's learners still below grade level, who are counted once. DepEd had not issued the SY 2027-2028 calendar as of November 26, 2026; the months marked assumed follow SY 2026-2027's pattern.

Try moving the Term 1 supplies to August: the year's total does not change, the quarters do, and the sessions that start in July would run without their supplies. A division that releases cash by quarter sees Q3 grow and Q2 shrink.

## Checking the totals

A school WFP's totals are checked in four ways.

1. **Each row adds up.** A row's months must equal its total. Bulacan's sheet computes a "CHECKING" column for every row and flags a mismatch in yellow.
2. **The plan equals the allocation.** The WFP's total for school MOOE must equal the NEP-level figure the division sent: Imus City's tool asks whether it "was in accordance with the FY 2026 National Expenditure Program (NEP)" (DM 768, s. 2025, Encl. 3, item 3), and Nueva Vizcaya's FY 2027 request-for-subsidy sheet, which spreads the NEP figure less 5% tax by month and object of expenditure, answers any gap with "Sorry but the variance should be exactly zero (0), no difference until the last centavo". For Liwayway, every school-MOOE row together must come to ₱1,262,000.00.
3. **The other documents agree.** Bulacan, which collects the School Operating Budget, the cash program and BED No. 3 (the monthly disbursement program) with the WFP, fills all three from the WFP sheet and notes that "The total amount in the WFP should be equal to the amounts in NEP and SOB", and Imus checks that "The same total amount were reflected in the PPMP, APP, and WFP" (item 13). For what each of those documents holds, see [how the WFP, AIP and PPMP fit together](https://nash.com.ph/blog/wfp-aip-ppmp-difference).
4. **Mandatory expenses are in full.** The year's utilities are budgeted before projects take the rest (DO 008, s. 2019, Sec. V.D).

The NEP figure is a proposal. Region VIII told its offices to use the FY 2027 NEP level "subject to any subsequent adjustments arising from the enacted FY 2027 General Appropriations Act (GAA) and/or succeeding budget issuances" (RM 1047, s. 2026, item 4), and Tangub City reminded its schools that the allocations "remain subject to final budget authorization" (DM 363, s. 2026). When the final allocation differs, adjust the rows to the new total.

## Tracing each row

Tracing a row means showing where it comes from in the school's plans and which division and DepEd priorities it serves. No national form prescribes a table for it, but each link rests on a rule: the AIP comes from the SIP's objectives (SIP Guidebook, Step 8), the SIP "must contribute to the attainment of the goals of the Division Education Development Plan (DEDP)" (DO 44, s. 2015, Encl., Sec. V.A), and "All DepEd offices and units in all governance levels shall align their policies, plans, and programs with the BEDP 2030" ([DO 024, s. 2022](https://www.deped.gov.ph/2022/05/30/may-30-2022-do-024-s-2022-adoption-of-the-basic-education-development-plan-2030/), item 4). Imus City's presentation template asks for the trace in short form: BEDP pillar, priority improvement area, project, activities, resources needed, amount and source of fund (DM 768, s. 2025, Encl. 1). In those columns:

| BEDP pillar | Priority improvement area | Project | Activities | Resources needed | Amount | Source of fund |
| --- | --- | --- | --- | --- | --- | --- |
| Pillar 3, Quality; the DEDP's literacy priority, in the division's own words | Learners in Grades 2 to 4 reading below grade level in the latest CRLA and Phil-IRI | Project Basa-Galing | Grouping by reading level; after-class sessions three times a week; reassessment each term | Tutors, leveled passages, reading folders, five supply items | ₱6,244.56 | School MOOE |
| None | None in the SIP | A laptop for the school office | None | A laptop | ₱55,000 | Not school MOOE supplies: at ₱50,000 or more a unit it is property |

The second row shows why the trace matters. An item that traces to nothing is a request the plan cannot carry; it waits for the SIP's adjustment or another fund, and it never enters the WFP as a supplies line.

## Supporting documents, signatures and submission

Divisions differ on attachments. Those their memoranda ask for include:

- the approved SIP, the AIP for the fiscal year, or both (Imus City, Bulacan, Tangub City);
- the WFP in the division's template, as an editable file or a signed copy;
- the PPMP and the APP (Imus City, Lipa City, Ligao City, Tangub City; Kabankalan City asks for the APP with a monthly expenditure matrix), and the APP-CSE, which Misamis Oriental lists among the documents its schools prepare (DM 569, s. 2025);
- the School Operating Budget, the cash program and the monthly disbursement program (all three in Bulacan; the SOB and the MDP in Tangub City; the MDP in Ligao City);
- a presentation tracing each project to its BEDP pillar and priority improvement area, where the division holds an appraisal (Imus City).

Keep three more papers ready even where none is asked for: the budget breakdown behind each row's amount, the baseline data behind its targets, and the planning team's minutes. They answer what a reviewer asks first: where an amount came from, why a target is that number, and who decided.

DO 017, s. 2024, which sets who signs DepEd's financial documents, has WFP tables for the Central Office, regional offices and division offices only ([DO 017, s. 2024](https://www.deped.gov.ph/2024/12/04/december-4-2024-do-017-s-2024-amendment-to-the-provisions-of-deped-order-no-001-s-2023-on-signing-authorities-for-financial-matters-in-the-department-of-education/), Annex A, item A). For a school's WFP, the division's template names the signatories. Examples from 2025 and 2026 templates:

| Division and fund | Prepared by | Reviewed by | Approved by |
| --- | --- | --- | --- |
| Bulacan, school MOOE, FY 2027 | School head | Accountant III | Assistant Schools Division Superintendent |
| Abra, School Innovation and Improvement Fund, FY 2026 | School head | District supervisor, the SMME section, the budget officer, and the SGOD and CID chiefs | SDS, on the ASDS's recommendation |
| Tayabas City, Special Needs Education fund, FY 2025 | School head | CID chief; budget officer and accountant certify the allotment and funds | SDS |

Deadlines in division memoranda for FY 2026 and FY 2027 run from October 8 to December 12, and many divisions then hold an appraisal: a panel that reviews the plans, often with the school head presenting, and returns comments. Name the file the way the memorandum says, sign every page that asks for a signature, and keep the version the division approved.

## Why divisions return a WFP

A division returns a WFP when its reviewers cannot trace, check or total it. The reasons below come from the criteria divisions publish and from the money rules.

| Reason | What the reviewer checks | Fix |
| --- | --- | --- |
| A row is not in the AIP | Imus's item 2: activities "included in the AIP" for the school's PIAs | Trace each row to an AIP line, or drop it |
| The total is not the NEP figure | Imus's item 3; Nueva Vizcaya's zero variance | Recompute; budget mandatory expenses first; spread the remainder |
| Months do not add to the row total | The sheet's checking column | Correct the months, not the total |
| No measurable target | An output indicator with a number and a period | Rewrite as in the table above |
| A disallowed MOOE item | Seats, textbooks, review materials; items of ₱50,000 or more | Move to another fund, or drop |
| Wrong template or missing columns | Imus's item 4: "adhered to the prescribed format" | Use the division's file as sent |
| Missing signatures | Imus's item 5: "duly authorized signatories" | Sign as the template's blocks say |
| Purchases missing from the PPMP | Imus's item 13: same totals in the PPMP, APP and WFP | Enter every purchased item in the PPMP |
| Costs with no basis | A budget breakdown for each amount | Attach the breakdown and price sources |

In Region X's FY 2025 cycle, the division chiefs of curriculum and of school governance checked that the activities of implementing schools' WFPs were aligned with the division's and DepEd's priorities, and plans with comments went back to the schools for revision and resubmission (RM 932, s. 2024, as attached to SDO Misamis Oriental DM 791, s. 2024).

## After approval: the quarterly review and plan adjustment

After approval, the WFP becomes the yardstick of the school's quarterly review. The school head conducts a "quarterly Program Implementation Review (PIR) in the school to track physical and financial accomplishments and assess the progress of implementation of plans, programs, projects, and major activities" (DO 029, s. 2022, Sec. VIII, item f), with the planning team and the school governance council taking part (item e). The [quarterly school review](https://nash.com.ph/blog/deped-smea-school-monitoring-evaluation-adjustment) covers how the review runs and what it records.

Each review compares the quarter's targets and amounts with what happened, and the team decides what to change. For the offices that plan in the PMIS, "After the conduct of the PIR, program proponents are given ten (10) working days to revise their Work and Financial Plan through Plan Adjustment" (DO 011, s. 2021, Part III, item m), but that order covers "the Central Office, Regional Offices, and Schools Division Offices only" (Part VIII.1). No national text sets a school's deadline, so follow the division's.

An adjustment is easiest to approve when it sets the approved targets and amount beside the adjusted ones, with the reason the review found. Two rules hold whatever the form. A change to an approved plan needs the approval the rules require; DepEd's 2026 memorandum on the Super El Niño, for one, says "Any modification to the approved fund utilization, work and financial plan, or expenditure classification shall be subject to existing regulations and the approval of the authorized official" ([DM 064, s. 2026](https://www.deped.gov.ph/2026/10/26/october-26-2026-dm-064-s-2026-anticipatory-action-preparedness-and-protective-measures-for-the-2026-2027-super-el-nino/), Sec. VIII). And what the year does not finish goes into the next year's AIP: "any item not accomplished for the year shall be included in the AIP of the following year" (Financial Management Operations Manual, p. 45, adopted by [DO 60, s. 2016](https://www.deped.gov.ph/2016/09/02/do-60-s-2016-implementation-of-the-financial-management-operations-manual-and-orientation-of-deped-financial-management-staff-at-the-regional-division-and-school-levels/)).

**The review of Project Basa-Galing after the third quarter.** On the page, the reader enters what Q3 (July to September 2027, Term 1 of SY 2027-2028) saw (sessions held, learners reassessed, amount spent) and picks a decision; the figure works out Q3's accomplishment and sets the approved targets and amount beside the adjusted ones. Q1 and Q2 are taken as planned. The sample: 21 of 24 sessions held (88%), 26 of 30 learners reassessed (87%), ₱1,651.87 of ₱1,853.74 spent (89%). Decision: adjust the rest of the year.

| Adjusted row | Q1 | Q2 | Q3 (actual) | Q4 | Year |
| --- | --- | --- | --- | --- | --- |
| Sessions held | 24 | 0 | 21 (planned 24) | 24 | 69 |
| Learners reassessed | 30 | 0 | 26 (planned 30) | 4 (planned 0) | 60 |
| Amount | ₱2,195.41 | ₱2,195.41 | ₱1,651.87 (planned ₱1,853.74) | ₱201.87 (planned ₱0.00) | ₱6,244.56 |

- Change from the approved row: sessions −3 (72 to 69), learners 0, amount ₱0.00.
- Reason: 3 of Term 1's 24 sessions were not held; 4 of the 30 learners were not reassessed; ₱201.87 of Q3's ₱1,853.74 was not spent. The learners not reassessed join the Term 2 group, and the money difference moves into a Q4 purchase.
- The money: ₱201.87 unspent in Q3 moves into a Q4 purchase for the Term 2 group.

How each decision changes the rest of the year is the figure's own example, not a DepEd rule: keeping the plan holds the approved months; adjusting the rest of the year carries the learners not reassessed into the Term 2 group and moves Q3's savings into a Q4 purchase; ending the project releases what is unspent for another use in the plan, with the approval the division requires.

In the sample, Liwayway's review after the third quarter, held as Term 2 of SY 2027-2028 opens, finds 21 of Term 1's 24 sessions held, 26 of 30 learners reassessed and ₱1,651.87 of the quarter's ₱1,853.74 spent. Keeping the plan would leave ₱201.87 with nothing planned against it, and the row would come to ₱6,042.69, ₱201.87 short of its ₱6,244.56. Adjusting the rest of the year moves the four learners into the Term 2 group, in the same school year and grade, and the ₱201.87 into a fourth-quarter purchase for them, so the row keeps its 60 learners and its ₱6,244.56. The quarter's sources and uses of funds also go on the school's Transparency Board, which "must be updated every three (3) months" (DO 008, s. 2019, Sec. VI.A.4).

## What this means for school heads

- **Start from the AIP, not the template.** A WFP made from the template's columns first ends up with rows the SIP never asked for. An AIP written in DO 008's calendar-year format already holds most of what the WFP asks.
- **Budget the bills before the projects.** List the year's electricity, water and internet from the 2026 bills, then plan projects in what remains of the NEP-level figure.
- **Make every target countable from a record.** If the PIR cannot count it from attendance sheets, assessment results or receipts, rewrite it.
- **Put money in the month it is paid.** Purchases for a term's activities belong in or before the month those activities start, and nothing belongs after December.
- **Keep the planning team's minutes, the budget breakdown and the price sources.** They answer most of what an appraisal panel asks.
- **Do not spend on a change before it is approved.** After each PIR, set the approved targets and amount beside the adjusted ones, get the approval the division requires, and carry what the year did not finish into the next AIP.
- **Do not buy what MOOE cannot pay for** (seats, textbooks, review materials, property of ₱50,000 or more), whatever the template's dropdown allows.

Planning with the team serves PPSSH indicator 1.2.2, "Develop and implement with the planning team school plans aligned with institutional goals and policies", and costing and spending by the rules serves strand 2.2 on financial management. The domains are explained in [PPSSH Domain 1: Leading Strategically](https://nash.com.ph/blog/ppssh-domain-1-leading-strategically) and [PPSSH Domain 2: Managing School Operations and Resources](https://nash.com.ph/blog/ppssh-domain-2-managing-school-operations).

## How the NASH may test this

The items below are original practice items, scored 3 (Relational), 2 (Multistructural), 1 (Unistructural) or 0 (Prestructural). An option that breaks a rule scores 0.

### Question 1

*Indicator 2.2.2, Financial management. Career Stage 2, Situational, Moderate.*

You are the school head of a non-implementing elementary school in a coastal town. The division has sent the school's MOOE figure under the National Expenditure Program and asks for a work and financial plan whose total equals it. The planning team's draft, built from the approved AIP, exceeds the figure by Php 48,000. Electricity and water, which took about a fifth of last year's MOOE, are not yet in the draft, and a teacher proposes adding review books for the national test. What is the most appropriate action?

- **A.** Submit the draft as the team prepared it with a letter asking the division to raise the figure, since every activity in it comes from the approved AIP.
- **B.** Budget electricity and water first from last year's bills, then defer the lower-priority AIP activities until the plan equals the figure, leaving out the review books.
- **C.** Defer the lower-priority AIP activities with the team until the draft equals the figure, then add electricity and water once the division releases the final allocation.
- **D.** Add the review books to the draft with the other AIP activities and submit it as it stands, since the division adjusts every plan once the budget is enacted.

**Answer and explanation**

**Best answer: B.** Points: A = 1, B = 3, C = 2, D = 0.

- **A (1 point, Unistructural).** Drawing every activity from the approved AIP is right, but the division asked for a plan that equals its figure, and the draft still leaves out the bills the school must pay first.
- **B (3 points, Relational).** It puts the mandatory expenses in first, fits the AIP's activities to the allocation by priority, and keeps out an item MOOE may never buy, so the plan both totals correctly and can be carried out.
- **C (2 points, Multistructural).** Fitting the draft to the figure by priority is right, but leaving electricity and water for later reverses the order the rules set: mandatory expenses come first, and a plan that already equals the figure has no room left for them.
- **D (0 points, Prestructural).** School MOOE may never buy supplementary learning resources, "which include publications, periodicals and review materials" (DO 008, s. 2019, Sec. V.D.6), and a draft over the figure fails the division's check whatever happens after the budget is enacted.

**Why.** This aligns with Career Stage 2 expectations because indicator 2.2.2 has the school head manage allocation in line with the issuances and the school plan. DO 008, s. 2019 lets school MOOE fund the AIP's activities "subject to availability of funds and prioritization of mandatory expense items" (Sec. V.D and item 1), and bars review materials in every case (Sec. V.D.6). The 2-point option fits the plan to the figure but leaves the mandatory expenses for last.

*Indicator 2.2.2: Manage finances adhering to policies, guidelines and issuances in allocation, procurement, disbursement and liquidation aligned with the school plan.*

*Sources: DepEd Order No. 008, s. 2019, Sec. V.D, items 1 and 6.*

### Question 2

*Indicator 1.7.2, Monitoring and evaluation processes and tools. Career Stage 2, Situational, Moderate.*

You are the school head of a multigrade elementary school in an upland barangay. At the quarterly review held as Term 2 opens, the reading project in your approved work and financial plan shows 18 of 24 planned after-class sessions held in Term 1, because floods closed the school for two weeks, and 22 of 30 learners reassessed. Php 1,500 of Term 1's supply budget was not spent. The division approved the plan and approves any change to it. What is the most appropriate action?

- **A.** Record the shortfall and its cause in the review report, and keep the rest of the year as approved so that the targets match what the division signed.
- **B.** Mark the quarter's targets as met in the review report, since the floods were beyond the school's control, and keep the unspent amount for urgent needs.
- **C.** Record the variance and its cause, and propose carrying the learners not reassessed and the unspent amount into Term 2, for the division's approval.
- **D.** Ask the division to approve carrying the learners not reassessed and the unspent amount into Term 2, and record the variance in the year-end report.

**Answer and explanation**

**Best answer: C.** Points: A = 1, B = 0, C = 3, D = 2.

- **A (1 point, Unistructural).** Recording the shortfall and its cause is the review's first use, but keeping the year unchanged leaves eight learners without a reassessment and Php 1,500 with nothing planned against it.
- **B (0 points, Prestructural).** Reporting targets as met when they were not makes the review's record false, though the review exists "to track physical and financial accomplishments" (DO 029, s. 2022, Sec. VIII, item f), and money kept for unnamed needs is outside the approved plan.
- **C (3 points, Relational).** It uses the review as the tool it is meant to be: it records the variance, turns it into an adjustment for the learners left behind, and seeks the division's approval, which the plan requires, before acting on it.
- **D (2 points, Multistructural).** The adjustment for the learners and the money is the right one, and it waits for the division's approval, but the variance and its cause belong in this quarter's review: the review exists to track accomplishment each quarter, and its record is what the division reads when it decides on the change.

**Why.** This aligns with Career Stage 2 expectations because indicator 1.7.2 has the school head use monitoring and evaluation processes to promote learner achievement. DO 029, s. 2022 has the school head conduct the quarterly review "to track physical and financial accomplishments and assess the progress of implementation of plans" and integrate its results into the school's plans (Sec. VIII, items f and g), and it says monitoring "determines any adjustment of plans and activities needed to achieve the committed targets" (Sec. VI, item 1). Here the division approves every change to the plan, as DepEd's 2026 El Niño memorandum also requires for the funds it covers (DM 064, s. 2026, Sec. VIII). The 2-point option seeks the right change but leaves the quarter's record of the variance for the year's end.

*Indicator 1.7.2: Utilize available monitoring and evaluation processes and tools to promote learner achievement.*

*Sources: DepEd Order No. 029, s. 2022, Sec. VI, item 1, and Sec. VIII, School M&E System, items f and g; DepEd Memorandum No. 064, s. 2026, Sec. VIII.*

Nothing in this guide reproduces or predicts examination content.

## Frequently asked questions

### Is a school required to make a work and financial plan?

No DepEd order in force sets a WFP form for a school's MOOE; for a school, the AIP in DO 008, s. 2019's calendar-year format does that work (Sec. V.D.1). Many divisions still require one each year on their own template, and their memorandum binds the school. Program funds may also ask for one, such as ALS program support funds downloaded to a school ([DO 028, s. 2022](https://www.deped.gov.ph/2022/06/20/june-20-2022-do-028-s-2022-implementing-guidelines-on-the-release-receipt-utilization-monitoring-and-reporting-of-program-support-funds-for-alternative-learning-system-for-calendar-yea/), item 38).

### What is the format of a school WFP?

The division's template sets it. Planning templates ask for the BEDP pillar or priority improvement area, the program or activity, its output, indicators and physical targets, the schedule and the resources needed; budget templates ask for the object of expenditure (with its UACS code in some), target, total, tax withheld, net and monthly amounts. DepEd's own AIP format (DO 008, s. 2019, Annex 1) already carries each line's indicators, budget source and monthly targets and amounts.

### How do I compute the total of the WFP?

Add every row's total by fund. The school-MOOE rows must equal the NEP-level allocation the division sent, to the centavo where the division's sheet checks it, with mandatory expenses budgeted first (DO 008, s. 2019, Sec. V.D). After the GAA is enacted, adjust the rows to the final allocation.

### Can the school change its WFP after the division approves it?

Yes, through the quarterly review and an adjustment approved as the division requires. The school head reviews physical and financial accomplishment every quarter (DO 029, s. 2022, Sec. VIII, item f). DepEd's 2026 El Niño memorandum, for the funds it covers, puts any modification to an approved work and financial plan under "the approval of the authorized official" (DM 064, s. 2026, Sec. VIII), and divisions set the route for the rest. Items not finished in the year go into the next year's AIP (FMOM, p. 45).

### Where do I get a WFP template?

From the division's memorandum, which links its template. Where the division prescribes none, the AIP format of DO 008, s. 2019, Annex 1 holds the same facts, and there is a [filled school WFP sample with a downloadable template](https://nash.com.ph/blog/school-work-financial-plan-sample).

## Sources

**DepEd issuances**

- DepEd Order No. 8, s. 2007, Revised Implementing Guidelines on the Operation and Management of School Canteens in Public Elementary and Secondary Schools, February 6, 2007: item 6.7. [deped.gov.ph](https://www.deped.gov.ph/2007/02/06/do-8-s-2007-revised-implementing-guidelines-on-the-operation-and-management-of-school-canteens-in-public-elementary-and-secondary-schools/)
- DepEd Order No. 44, s. 2015, Guidelines on the Enhanced School Improvement Planning (SIP) Process and the School Report Card (SRC), September 29, 2015, and its SIP Guidebook: Introduction; Activity 1.2; Steps 6 and 8. [deped.gov.ph](https://www.deped.gov.ph/2015/09/29/do-44-s-2015-guidelines-on-the-enhanced-school-improvement-planning-sip-process-and-the-school-report-card-src/)
- DepEd Order No. 35, s. 2016, The Learning Action Cell as a K to 12 Basic Education Program School-Based Continuing Professional Development Strategy for the Improvement of Teaching and Learning, June 7, 2016: items 11 and 17.10. [deped.gov.ph](https://www.deped.gov.ph/2016/06/07/do-35-s-2016-the-learning-action-cell-as-a-k-to-12-basic-education-program-school-based-continuing-professional-development-strategy-for-the-improvement-of-teaching-and-learning/)
- DepEd Order No. 48, s. 2016, Policy and Guidelines on Comprehensive Tobacco Control, June 28, 2016: Sec. V.G, item 6. [deped.gov.ph](https://www.deped.gov.ph/2016/06/28/do-48-s-2016-policy-and-guidelines-on-comprehensive-tobacco-control/)
- DepEd Order No. 60, s. 2016, Implementation of the Financial Management Operations Manual, September 2, 2016, and the manual (FMOM): p. 45. [deped.gov.ph](https://www.deped.gov.ph/2016/09/02/do-60-s-2016-implementation-of-the-financial-management-operations-manual-and-orientation-of-deped-financial-management-staff-at-the-regional-division-and-school-levels/)
- DepEd Order No. 008, s. 2019, Revised Implementing Guidelines on the Direct Release, Use, Monitoring and Reporting of Maintenance and Other Operating Expenses (MOOE) Allocation of Schools, Including Other Funds Managed by Schools, May 2, 2019: Secs. I.3, IV.3, V.D, V.D.1, V.D.5, V.D.6, VI.A.1 and VI.A.4; Annex 1. [deped.gov.ph](https://www.deped.gov.ph/2019/05/02/may-2-2019-do-008-s-2019-revised-implementing-guidelines-on-the-direct-release-use-monitoring-and-reporting-of-maintenance-and-other-operating-expenses-allocation-of-schools-including-other-fu/)
- DepEd Order No. 029, s. 2019, Procedural Guidelines on the Management of Cash Advances for School MOOE and Program Funds of Non-Implementing Units, October 17, 2019: item 18, and the enclosed COA-DBM-DepEd Joint Circular No. 2019-1, item 6.2.1. [deped.gov.ph](https://www.deped.gov.ph/2019/10/17/october-17-2019-do-029-s-2019-procedural-guidelines-on-the-management-of-cash-advances-for-school-maintenance-and-other-operating-expenses-and-program-funds-of-non-implementing-units-pursuant-to/)
- DepEd Order No. 011, s. 2021, Guidelines on the Operationalization of the Program Management Information System, February 24, 2021: Part III, items m and r; Part VIII.1. [deped.gov.ph](https://www.deped.gov.ph/2021/02/24/february-24-2021-do-011-s-2021-guidelines-on-the-operationalization-of-the-program-management-information-system/)
- DepEd Order No. 024, s. 2022, Adoption of the Basic Education Development Plan 2030, May 30, 2022: item 4. [deped.gov.ph](https://www.deped.gov.ph/2022/05/30/may-30-2022-do-024-s-2022-adoption-of-the-basic-education-development-plan-2030/)
- DepEd Order No. 026, s. 2022, Implementing Guidelines on the Establishment of School Governance Council, June 17, 2022. [deped.gov.ph](https://www.deped.gov.ph/2022/06/17/june-17-2022-do-026-s-2022-implementing-guidelines-on-the-establishment-of-school-governance-council/)
- DepEd Order No. 028, s. 2022, Implementing Guidelines on the Release, Receipt, Utilization, Monitoring and Reporting of Program Support Funds for Alternative Learning System, June 20, 2022: item 38. [deped.gov.ph](https://www.deped.gov.ph/2022/06/20/june-20-2022-do-028-s-2022-implementing-guidelines-on-the-release-receipt-utilization-monitoring-and-reporting-of-program-support-funds-for-alternative-learning-system-for-calendar-yea/)
- DepEd Order No. 029, s. 2022, Adoption of the Basic Education Monitoring and Evaluation Framework, June 22, 2022: Sec. VIII, School M&E System, items e, f and g. [deped.gov.ph](https://www.deped.gov.ph/2022/06/22/june-20-2022-do-029-s-2022-adoption-of-the-basic-education-monitoring-and-evaluation-framework/)
- DepEd Order No. 017, s. 2024, Amendment to the Provisions of DepEd Order No. 001, s. 2023 on Signing Authorities for Financial Matters, December 4, 2024: Annex A, item A. [deped.gov.ph](https://www.deped.gov.ph/2024/12/04/december-4-2024-do-017-s-2024-amendment-to-the-provisions-of-deped-order-no-001-s-2023-on-signing-authorities-for-financial-matters-in-the-department-of-education/)
- DepEd Order No. 018, s. 2025, Implementing Guidelines of the Academic Recovery and Accessible Learning Program, June 13, 2025: item 80. [deped.gov.ph](https://www.deped.gov.ph/2025/06/13/june-13-2025-do-018-s-2025-implementing-guidelines-of-the-academic-recovery-and-accessible-learning-program/)
- DepEd Order No. 022, s. 2025, Policy Guidelines on the Institutionalization of the School Sports Club in Public Schools, August 7, 2025: Sec. V.E, item 3. [deped.gov.ph](https://www.deped.gov.ph/2025/08/07/august-7-2025-do-022-s-2025-policy-guidelines-on-the-institutionalization-of-the-school-sports-club-in-public-schools/)
- DepEd Order No. 009, s. 2026, Guidelines on the Implementation of the Three-Term School Calendar in Basic Education, April 16, 2026: item 4; Encl., items 10 and 13; Annex B. [deped.gov.ph](https://www.deped.gov.ph/2026/04/16/april-16-2026-do-009-s-2026-guidelines-on-the-implementation-of-the-three-term-school-calendar-in-basic-education/)
- DepEd Order No. 024, s. 2026, Guidelines on the Implementation of the School-Based Mental Health Program, November 26, 2026: Sec. V.f. [deped.gov.ph](https://www.deped.gov.ph/2026/11/26/november-26-2026-do-024-s-2026-guidelines-on-the-implementation-of-the-school-based-mental-health-program/)
- DepEd Memorandum No. 048, s. 2026, Allocation and Release of the School Innovation and Improvement Fund to Non-Implementing Unit Public Schools to Strengthen Decentralization Practices in the Department of Education for Fiscal Year 2026, August 3, 2026: Encl., Sec. III.1. [deped.gov.ph](https://www.deped.gov.ph/2026/08/03/august-3-2026-dm-048-s-2026-allocation-and-release-of-the-school-innovation-and-improvement-fund-to-non-implementing-unit-public-schools-to-strengthen-decentralization-practices-in-the-de/)
- DepEd Memorandum No. 064, s. 2026, Anticipatory Action, Preparedness, and Protective Measures for the 2026-2027 Super El Niño, October 26, 2026: Sec. VIII. [deped.gov.ph](https://www.deped.gov.ph/2026/10/26/october-26-2026-dm-064-s-2026-anticipatory-action-preparedness-and-protective-measures-for-the-2026-2027-super-el-nino/)

**Joint circulars and other agencies**

- DepEd-DBM-DILG-DOF Joint Circular No. 01, s. 2025, Omnibus Guidelines on the Use of the Special Education Fund (SEF): §6.8. [deped.gov.ph](https://www.deped.gov.ph/2026/03/03/deped-dbm-dilg-joint-memorandum-circular-no-01-s-2025-omnibus-guidelines-on-the-use-of-the-special-education-fund-sef/)
- COA Circular No. 2022-004, May 31, 2022, on the capitalization threshold of ₱50,000. [coa.gov.ph](https://coa.gov.ph/wpfd_file/coa-circular-no-2022-004-may-31-2022/)
- Commission on Audit, Government Accounting Manual, Vol. III, Ch. 3, Description of Accounts: Office Supplies Expenses (50203010), read November 26, 2026. [coa.gov.ph](https://www.coa.gov.ph/wp-content/uploads/abc-help/gam_3/3main.htm)
- DBM Circular Letter No. 2022-14, October 28, 2022, Prescribing Guidelines for the Preparation and Submission of the Annual Budget Execution Plans Covering the FY 2023 Budget and Thereafter: BED No. 2 instructions.
- DBM National Budget Circular No. 599, January 5, 2026, Guidelines on the Release of Funds for FY 2026: item 3.3. [dbm.gov.ph](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Circular/NATIONAL-BUDGET-CIRCULAR-NO-599.pdf)
- DBM National Budget Memorandum No. 156, January 5, 2026, National Budget Call for FY 2027: BP Form B instructions. [dbm.gov.ph](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Memorandum/NATIONAL-BUDGET-MEMORANDUM-NO-156.pdf)
- Implementing Rules and Regulations of Republic Act No. 12009 (New Government Procurement Act), 2025: Sec. 7.7.1(a). [gppb.gov.ph](https://www.gppb.gov.ph/ngpa-implementing-rules-and-regulations/)
- Unified Accounts Code Structure, object codes (sub-object list), read November 26, 2026. [uacs.gov.ph](https://uacs.gov.ph/resources/uacs/object-code/sub-object)

**Division memoranda and templates (practice, not national rules)**

- SDO Bulacan, Division Memorandum No. 468, s. 2026 (October 14, 2026), and its FY 2027 SOB-WFP-CP-BED 3 workbooks. [bulacandeped.com.ph](https://bulacandeped.com.ph/division-memorandum-no-468-s-2026-submission-of-annual-implementation-plan-work-and-financial-plan-and-other-financial-documents-for-fy-2027/)
- SDO Imus City, Division Memorandum No. 768, s. 2025 (December 11, 2025): Enclosures 1 and 3. [depedimuscity.com](https://www.depedimuscity.com/portal/uploads/DM_768_S_2025v1.pdf)
- SDO Kabankalan City, Division Memorandum No. 321, s. 2026 (September 1, 2026). [depedkabankalancity.com](https://www.depedkabankalancity.com/uploads/7/4/2/6/74269293/division_memorandum_no._321_s._2026_submission_of_the_fy_2027_school_monthly_expenditure_matrix_work_and_financial_plan_and_annual_procurement_plan.pdf)
- SDO Nueva Vizcaya, Division Memorandum No. 460, s. 2026 (November 12, 2026), and its FY 2027 request-for-subsidy sheet. [sdonuevavizcaya.com](https://sdonuevavizcaya.com/wp-content/uploads/2026/11/DM-No.-460-S.-2026-PREPARATION-AND-SUBMISSION-OF-SCHOOLS-ANNUAL-IMPLEMENTATION-PLAN-AIP-WORK-AND-FINANCIAL-PLAN-WFP-AND-REQUEST-FOR-SUBSIDY-RFS-FOR-FY-2027.pdf)
- SDO Misamis Oriental, Division Memorandum No. 569, s. 2025 (August 18, 2025), and No. 791, s. 2024 (December 9, 2024), with Region X RM 932, s. 2024. [depedmisor.com](https://www.depedmisor.com/uploads/1/3/2/5/13258713/dm791s.2024.pdf)
- SDO Abra, Division Memorandum No. 575, s. 2026 (October 26, 2026), and its SIIF WFP template. [depedabra.com](https://depedabra.com/wp-content/uploads/2026/10/DM_NO_575_S_2026-UTILIZATION-OF-THE-NEW-WORK-AND-FINANCIAL-PLAN-WFP-TEMPLATE-FOR-THE-BUDGET-UTILIZATION-OF-THE-SCHOOL-INNOVATION-AND-IMPROVEMENT-FUND-SIIF-FOR-FISCAL-YEAR.pdf)
- SDO Tayabas City, Division Memorandum No. 570, s. 2025 (August 22, 2025). [sdotayabascity.ph](https://www.sdotayabascity.ph/data_files/uploaded_memo/DM%20NO.%20570,%20S.%202025-5wwox3JEE59PhzFyBlbD.pdf)
- SDO Tangub City, Division Memorandum No. 363, s. 2026 (September 24, 2026). [tangub.deped.gov.ph](https://tangub.deped.gov.ph/wp-content/uploads/2026/10/divmemo363_2026.pdf)
- SDO Lipa City, Division Memorandum No. 375, s. 2026 (November 5, 2026). [depedlipacity.com.ph](https://depedlipacity.com.ph/assets/resources/issuances/DM_No_375_s_2026.pdf)
- SDO Ligao City, Division Memorandum No. 0509, s. 2026 (October 22, 2026). [sdoligaocity.ph](https://sdoligaocity.ph/storage/uploads/issuances/wz0aYKEhIHyKuWBP9zbcPzD074Oboy1iQyJmT6P1.pdf)
- DepEd Region VIII, Regional Memorandum No. 1047, s. 2026 (August 17, 2026): item 4. [region8.deped.gov.ph](https://region8.deped.gov.ph/wp-content/uploads/2026/08/RM-No.-1047-s.-2026-FD-BS-GJNC-81926.pdf)

**The sample**

- Liwayway Elementary School and Project Basa-Galing are the series' invented sample. The MOOE figure is the median FY 2026 allocation of the 913 non-implementing, purely elementary public schools with 550 to 650 learners in SY 2025-2026 (DepEd's FY 2026 school MOOE allocation list and SY 2025-2026 enrollment); the supply prices are PS-DBM's APP-CSE 2027 Form prices as of April 27, 2026.

## The school WFP series

- [Work and Financial Plan (WFP) in DepEd: Meaning and Rules](https://nash.com.ph/blog/work-financial-plan-deped)
- How to Make a School Work and Financial Plan (WFP) (this post)
- [School Work and Financial Plan Sample: Excel WFP Template](https://nash.com.ph/blog/school-work-financial-plan-sample)
- [WFP Budget Breakdown: How to Cost and Fund School PPAs](https://nash.com.ph/blog/wfp-budget-breakdown)
- [WFP and PPMP, AIP and APP in DepEd Schools: What Must Match](https://nash.com.ph/blog/wfp-aip-ppmp-difference)

*Written by Mark Anthony Llego for NASH Reviewer. Sources: DepEd Orders No. 008, s. 2019; No. 44, s. 2015; No. 009, s. 2026; No. 029, s. 2019; No. 029, s. 2022; No. 011, s. 2021; DBM issuances; division memoranda and templates.*

---

© 2026 Mark Anthony Llego, NASH Reviewer. You may quote up to 100 words from this article with the author's name, its title and a link. In research and teaching, such as a thesis, action research, a journal article, or a class or LAC session, you may also quote it at the length your point needs, reproduce up to three of its charts or figures unchanged, and analyze its data and publish your results. Cite it as: Llego, M. A. (2026, November 26). *How to make a school Work and Financial Plan (WFP)*. NASH Reviewer. https://nash.com.ph/blog/make-school-work-financial-plan. Put the reference under each chart you reproduce. Any other reuse, such as reposting the article, its charts or its data files, needs written permission: ask through our [contact form](https://nash.com.ph/contact). Our [Copyright](https://nash.com.ph/copyright) page explains these rules with examples, and the [Terms of Service](https://nash.com.ph/terms#website-content-and-data) set them out.