# Work and Financial Plan (WFP) in DepEd: Meaning and Rules

A Work and Financial Plan (WFP) in DepEd is an annual plan of activities, targets and monthly costs. Who must prepare one, its parts, signatories and deadlines.

This is the Markdown copy of [Work and Financial Plan (WFP) in DepEd: Meaning and Rules](https://nash.com.ph/blog/work-financial-plan-deped), an article on the NASH Reviewer Blog by Mark Anthony Llego, published Nov 26, 2026. Topics: School leadership, Aspiring school heads. NASH Reviewer is an independent practice platform not affiliated with DepEd, BHROD, or NEAP.

A Work and Financial Plan (WFP) in DepEd is an office's annual operational plan: the programs, outputs and activities it will carry out in one fiscal year, with their timelines and budget, laid out as monthly physical, obligation and disbursement plans ([DepEd Order No. 017, s. 2024](https://www.deped.gov.ph/2024/12/04/december-4-2024-do-017-s-2024-amendment-to-the-provisions-of-deped-order-no-001-s-2023-on-signing-authorities-for-financial-matters-in-the-department-of-education/), Annex A, item A). DepEd's orders define it for the Central Office, the Regional Offices and the Schools Division Offices (SDOs), which prepare it in the Program Management Information System (PMIS) under [DepEd Order No. 011, s. 2021](https://www.deped.gov.ph/2021/02/24/february-24-2021-do-011-s-2021-guidelines-on-the-operationalization-of-the-program-management-information-system/).

For a public school's Maintenance and Other Operating Expenses (MOOE), no DepEd order in force sets a WFP form. The school's Annual Implementation Plan (AIP), drawn from its School Improvement Plan (SIP) and written in calendar-year form with monthly targets and amounts, does the work of the WFP ([DepEd Order No. 008, s. 2019](https://www.deped.gov.ph/2019/05/02/may-2-2019-do-008-s-2019-revised-implementing-guidelines-on-the-direct-release-use-monitoring-and-reporting-of-maintenance-and-other-operating-expenses-allocation-of-schools-including-other-fu/), Sec. V.D.1 and Annex 1). Many SDOs still ask every school for a WFP each year on a template of their own, and in September to December 2026 several asked for the plan for fiscal year (FY) 2027. A school follows its division's memorandum.

The rules below are those in force on November 26, 2026. On that date the FY 2027 General Appropriations Act (GAA) had not yet been enacted.

## Key findings

- **A WFP is an office's yearly plan in three parts.** DepEd defines it as "an annual operational plan that details the office's planned programs, outputs, and activities including the timelines and budgetary requirements", which "guides budget execution by outlining the monthly physical, obligation, and disbursement plans" (DO 017, s. 2024, Annex A, item A). In the PMIS it "consists of the Physical Plan, Monthly Obligation Program, and Monthly Disbursement Program as prescribed by the Department of Budget and Management (DBM)" (DO 011, s. 2021, Part III, item r).
- **DBM's current forms carry other names.** Agencies submit three budget execution documents (BEDs): BED No. 1, the Financial Plan; BED No. 2, the Physical Plan; and BED No. 3, the Monthly Disbursement Program (DBM Circular Letter No. 2022-14, item 4.1).
- **No DepEd order in force gives schools a WFP form for their MOOE.** The PMIS order applies to the Central, Regional and Schools Division Offices "only" and promised a separate policy for schools (DO 011, s. 2021, Part VIII.1), which had not been issued as of November 26, 2026. School MOOE pays for the activities of the SIP "as specifically determined in the Annual Implementation Plan (AIP)" (DO 008, s. 2019, Sec. V.D.1).
- **Two orders in force still name a school WFP.** A school head prepares "the updated WFP, AIP" when part of the Alternative Learning System (ALS) program support fund is downloaded to the school (DO 028, s. 2022, item 38), and every school puts its tobacco-control self-assessment into "the Work and Financial Plan (WFP) and Annual Implementation Plan (AIP)" (DO 48, s. 2016, Sec. V.G, item 6).
- **Divisions set the school WFP.** Division memoranda of 2026 asked schools for FY 2027 WFPs with deadlines from October 8 to December 4, 2026. Most set the school's MOOE in the National Expenditure Program (NEP) as the ceiling, and several required the WFP's total to equal the NEP figure and the budget documents (one division's FY 2026 tool also checks it against the PPMP and APP).
- **The plan is reviewed every quarter.** The school head conducts a quarterly Program Implementation Review (PIR) "to track physical and financial accomplishments" (DO 029, s. 2022, Sec. VIII, item f). Offices revise their WFPs within ten working days after the PIR (DO 011, s. 2021, Part III, item m); no national text sets a deadline for a school.

## What a Work and Financial Plan means in DepEd

A Work and Financial Plan is the document an office spends its budget by: what it will do in the fiscal year, what each activity should produce and when, and how much each costs, month by month. DepEd's texts describe it in five places, each for a different reader.

| Source | What it says | Whom it covers |
|---|---|---|
| DO 017, s. 2024, Annex A, item A (signing authorities) | "an annual operational plan that details the office's planned programs, outputs, and activities including the timelines and budgetary requirements based on an uploaded Expenditure Matrix (EM) in the Program Management Information System (PMIS). It guides budget execution by outlining the monthly physical, obligation, and disbursement plans." | The Central Office, the Regional Offices and the SDOs: its signing tables have no row for a school |
| DO 011, s. 2021, Part III, item r (the PMIS) | "an operational planning document generated from the uploaded Expenditure Matrix (EM) that outlines the complete course of action (activities) to be undertaken, indicators, major deliverables and milestones, schedule and duration, and the budgetary requirements" | The Central, Regional and Schools Division Offices "only" (Part VIII.1) |
| [DepEd Order No. 45, s. 2015](https://www.deped.gov.ph/2015/09/29/do-45-s-2015-guidelines-on-school-based-management-sbm-grants-for-fiscal-year-fy-2014/), item 3.16 (School-Based Management grants for FY 2014) | "Overall physical (targeted outputs) and financial (estimated obligations/expenditures) plan of the agency or unit consistent with their approved budget level for the year, broken down by quarter" | The schools that received the grant; the order's footnote cites DBM's Budget Execution Document form of September 2012 |
| Quality Basic Education Development Plan (Q-BEDP) 2025-2035, Annex 2, item 5.i | "The operational plan consists of the Physical Plan, Monthly Obligation Program, and Monthly Disbursement Program, collectively called the Work and Financial Plan …" (the same item adds the PPMP and the APP for common-use supplies to the operational plan) | DepEd's offices; school plans "shall be appraised by the SDO" (item 3.vii) |
| Financial Management Operations Manual (FMOM), p. 46 | "A Work and Financial Plan covering the Budget year is also prepared by each SU." | Every Spending Unit (SU), which the manual defines as "an operating/implementing or non-implementing unit that is authorized to disburse funds for its operations" (Glossary) |

The [Q-BEDP 2025-2035](https://www.deped.gov.ph/wp-content/uploads/Quality-Basic-Education-Development-Plan-QBEDP-2025-to-2035-29-July-2025.pdf) is a DepEd publication of July 29, 2025, not adopted by a DepEd order. The FMOM is the manual that [DepEd Order No. 60, s. 2016](https://www.deped.gov.ph/2016/09/02/do-60-s-2016-implementation-of-the-financial-management-operations-manual-and-orientation-of-deped-financial-management-staff-at-the-regional-division-and-school-levels/) put in place, five years before the PMIS order.

### The three plans inside a WFP

Each WFP holds three plans over the same activities, all spread across the twelve months of the fiscal year.

- **The physical plan** sets the targets: the outputs each activity should produce, the indicator that measures each, and how much of it should be done in each month or quarter. The WFP in the PMIS "contains the performance indicators for every output and activity" (DO 011, s. 2021, Part V.B.3(d)).
- **The monthly obligation program** sets when the office will commit its money. DBM's glossary defines it: "Obligation. A commitment by a government agency arising from an act of a duly authorized official which binds the government to the eventual payment of a sum of money" (Budget of Expenditures and Sources of Financing FY 2027, Glossary of Terms). A purchase order or a contract is such an act.
- **The monthly disbursement program** sets when the cash goes out. The same glossary defines a disbursement as "Settlement, liquidation, or payment of an obligation incurred". The WFP's obligation and disbursement programs are the "basis for requesting the issuance of Notice of Cash Allocation (NCA) by the DBM" (DO 011, s. 2021, Part V.B.3(d)).

Take one activity of the sample school used across this series, Liwayway Elementary School, an invented non-implementing-unit elementary school of about 600 learners. Its reading remediation project, Project Basa-Galing, aims to give 60 struggling readers in Grades 2 to 4 reading remediation, using ₱6,244.56 of paper, ink, cartolina, markers and folders bought from the Procurement Service of DBM (PS-DBM). The physical plan holds the 60 learners and the months the sessions run. The obligation program holds the ₱6,244.56 in the month the school commits to the purchase, and the disbursement program in the month it pays. The [sample WFP](https://nash.com.ph/blog/school-work-financial-plan-sample) gives the project's full row.

## What "work and financial plan" means in DBM's budget system

"Work and financial plan" is an old name in government budgeting. [Executive Order No. 359, s. 1989](https://www.gppb.gov.ph/wp-content/uploads/2023/06/Executive-Order-No.-359.pdf), on the government's procurement service, provides that "The appropriations for the Annual Procurement Programs of Agencies shall be identified in their annual Work and Financial Plan. Said Work and Financial Plan shall serve as the basis of the Department of Budget and Management in the release of the Agency's quarterly allotments and monthly funding warrants" (Sec. 4(b)). [DBM Circular Letter No. 2013-14](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2013/Circular%20Letter/CL2013-14.pdf) applies that rule to common-use supplies: "The APP-CSE shall serve as both the work and financial plan, to be used by DBM as basis in the release of funds" (item 4.4.1).

DBM's current budget execution system uses other names. Since FY 2023, every agency covered submits three BEDs based on the NEP "without waiting for the approval of the corresponding General Appropriations Act" ([DBM Circular Letter No. 2022-14](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2022/Circular-Letter/CIRCULAR-LETTER-NO-2022-14-DATED-OCTOBER-28-2022.pdf), item 4.1), and DBM releases funds "in accordance with the targets set forth under the DBM-evaluated BEDs" ([National Budget Circular No. 599](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Circular/NATIONAL-BUDGET-CIRCULAR-NO-599.pdf), item 3.9). DepEd's WFP is built from the same three parts.

| Part of DepEd's WFP (DO 011, s. 2021) | DBM's budget execution document | What DBM uses it for |
|---|---|---|
| Physical Plan | BED No. 2, Physical Plan: physical targets "broken down by quarter" | "the overall physical plan of the department/agency/OUs" (NBC No. 599, item 3.9.2) |
| Monthly Obligation Program | BED No. 1, Financial Plan: the "Estimated quarterly obligation program for the budget year" | "the basis for determining the obligation program of the agency" (NBC No. 599, item 3.9.1) |
| Monthly Disbursement Program | BED No. 3, Monthly Disbursement Program (MDP) | "the basis for the DBM's release of disbursement authorities including the comprehensive NCA" (NBC No. 599, item 3.9.3) |

DBM still gives the name to a form for government-owned or -controlled corporations: APYS Form 1, which supports a corporation's request to use its prior years' subsidies (DBM Corporate Budget Circular No. 27, April 28, 2025, item 4.4). DBM prescribes no WFP form for a school.

## Where the WFP sits among DepEd's plans

The WFP comes late in a chain of plans that runs from the national plan to the month's purchases. Each plan draws on the one before it.

1. **The Basic Education Development Plan (BEDP) 2030**: "All DepEd offices and units in all governance levels shall align their policies, plans, and programs with the BEDP 2030" ([DepEd Order No. 024, s. 2022](https://www.deped.gov.ph/2022/05/30/may-30-2022-do-024-s-2022-adoption-of-the-basic-education-development-plan-2030/), item 4), and the Q-BEDP 2025-2035, a DepEd publication that does not amend it.
2. **The Regional and Division Education Development Plans** (REDP and DEDP), six-year plans of the region and the division (DO 024, s. 2022, Sec. 7.1).
3. **The School Improvement Plan**, the school's three-year plan ([DepEd Order No. 44, s. 2015](https://www.deped.gov.ph/2015/09/29/do-44-s-2015-guidelines-on-the-enhanced-school-improvement-planning-sip-process-and-the-school-report-card-src/)).
4. **The Annual Implementation Plan**, one fiscal year of the SIP in calendar-year format (DO 008, s. 2019, Sec. V.D.1 and Annex 1).
5. **The WFP**, where the division asks for one.
6. **The Project Procurement Management Plan (PPMP) and the Annual Procurement Plan (APP)**, for everything bought (Implementing Rules and Regulations of Republic Act No. 12009, Sec. 7), and the APP for Common-Use Supplies and Equipment (APP-CSE), for what is bought from PS-DBM.
7. **The monthly disbursement program**, which sets the cash a non-implementing school receives each month or quarter ([DepEd Order No. 029, s. 2019](https://www.deped.gov.ph/2019/10/17/october-17-2019-do-029-s-2019-procedural-guidelines-on-the-management-of-cash-advances-for-school-maintenance-and-other-operating-expenses-and-program-funds-of-non-implementing-units-pursuant-to/), item 18).
8. **Purchase, payment and liquidation.**

A guide to [how the WFP, AIP and PPMP differ](https://nash.com.ph/blog/wfp-aip-ppmp-difference) sets the documents side by side, with what must match across them.

## Does a public school need a Work and Financial Plan?

Not as a form of its own for its MOOE: no DepEd order in force sets a school WFP form, and the school's AIP does the work of the WFP. Many divisions ask for a WFP each year on their own template. Five texts settle the national side.

- **The PMIS stops at the division office.** "The use of the PMIS shall be implemented at the Central Office, Regional Offices, and Schools Division Offices only. The guidelines on the use of the system by the schools will be issued in a separate policy" (DO 011, s. 2021, Part VIII.1). As of November 26, 2026, no such policy has been issued.
- **The signing rules have no school row.** DO 017, s. 2024 sets who prepares, reviews and approves the WFP of Central Office units, Regional Offices and SDOs (Annex A, item A), and none for a school.
- **For purchases, the WFP and the AIP are paired.** A purchase must follow "the approved WFP and the approved APP", or "in the case of the field offices or schools, in accordance with the approved WFP/Annual Implementation Plan and the APP for the current year of the office/school concerned" (DO 017, s. 2024, Annex A, item B). The same item speaks of "the approved WFP, or Annual Implementation Plan (AIP) where applicable".
- **The AIP is the school's annual plan and budget.** School MOOE funds the activities of the SIP "as specifically determined in the Annual Implementation Plan (AIP) which shall follow the calendar year format (Annex 1) of the school" (DO 008, s. 2019, Sec. V.D.1). Annex 1 lays out, for each program, project or activity, a target and an amount for each month, with totals by quarter and by fund (MOOE, Special Education Fund, others). The FMOM adds that "The AIP is also referred to as the school operating budget (SOB)" (p. 127).
- **DepEd's newest orders name WFPs for offices and the SIP and AIP for schools.** The School-Based Mental Health Program is to be included "in their respective strategic plans, Work and Financial Plans, and in the schools' School Improvement Plan and Annual Implementation Plan" ([DepEd Order No. 024, s. 2026](https://www.deped.gov.ph/2026/11/26/november-26-2026-do-024-s-2026-guidelines-on-the-implementation-of-the-school-based-mental-health-program/), Sec. V.f).

The FMOM's line that each Spending Unit prepares a WFP (p. 46) dates from 2016 and reads wider. A non-implementing school that receives cash advances may fall within its definition of a Spending Unit, but no later order gives schools a WFP form, and the PMIS order, the later text, keeps its WFPs to the offices.

### When a national text does name a school WFP

Two orders in force name a school WFP.

- **The ALS program support fund.** "In the event that part of the PSF under STO component is downloaded to the schools, the School Head (IU/Non-IU school) shall … Prepare and submit the updated WFP, AIP and other related documents to the SDO, including the physical and financial accomplishment reports and liquidation reports" ([DepEd Order No. 028, s. 2022](https://www.deped.gov.ph/2022/06/20/june-20-2022-do-028-s-2022-implementing-guidelines-on-the-release-receipt-utilization-monitoring-and-reporting-of-program-support-funds-for-alternative-learning-system-for-calendar-yea/), item 38(a)). The order governs ALS program support funds for 2022 and the years after.
- **Tobacco control.** Every school shall "Conduct self-assessment of the degree of implementation of this policy in the school and incorporate it into the Work and Financial Plan (WFP) and Annual Implementation Plan (AIP) efforts to improve implementation of comprehensive tobacco control in school" ([DepEd Order No. 48, s. 2016](https://www.deped.gov.ph/2016/06/28/do-48-s-2016-policy-and-guidelines-on-comprehensive-tobacco-control/), Sec. V.G, item 6). The order names the WFP beside the AIP and prescribes no WFP form.

### From school WFPs to division WFPs for program funds

DepEd once had schools prepare WFPs for program funds, drawn from their AIPs. Under the FY 2014 guidelines for schools with special curricular programs, "Using the template in Enclosure No. 2.a, the schools shall prepare the Work and Financial Plan specific to the fund support and shall submit to the SDO for appraisal. Projects and activities which are chargeable to the fund may be culled out from the approved Annual Implementation Plan (AIP) of the schools" ([DepEd Order No. 15, s. 2014](https://www.deped.gov.ph/wp-content/uploads/2014/03/DO_s2014_015.pdf), item 3.1.2). The 2015 support funds for the Special Education (SPED) program worked the same way, through an Excel template from the PMIS ([DepEd Order No. 38, s. 2015](https://www.deped.gov.ph/2015/08/19/do-38-s-2015-guidelines-on-the-utilization-of-support-funds-for-the-special-education-sped-program/), item 5.1.6), and so did the School-Based Management grants for FY 2014 (DO 45, s. 2015, item 7.1.2). Senior high schools reflected the proposed uses of their MOOE "in the school's Work and Financial Plan, format hereto attached" ([DepEd Order No. 9, s. 2018](https://www.deped.gov.ph/wp-content/uploads/DO_s2018_009.pdf), item 26) until DO 008, s. 2019 revoked that order (item 2).

Since the PMIS order of 2021, program orders have the division office prepare the program's WFP from the schools' approved AIPs. For Special Needs Education (SNEd), the former SPED, the recipient schools submit their AIPs to the Schools Division Superintendent (SDS) for approval, and the SDO prepares "the Work and Financial Plan (WFP) through the Program Management Information System (PMIS) based on the approved AIP of the recipient schools" ([DepEd Order No. 042, s. 2021](https://www.deped.gov.ph/2021/10/04/october-4-2021-do-042-s-2021-guidelines-on-the-utilization-of-program-support-funds-for-special-education-program/), items 5.3 and 5.4). For the School-Based Feeding Program run by DepEd, "SDO prepares the Work and Financial Plan (WFP) and identifies funding allocation per school" ([DepEd Order No. 013, s. 2026](https://www.deped.gov.ph/2026/06/04/june-4-2026-do-013-s-2026-institutional-guidelines-on-the-implementation-of-the-school-based-feeding-program/), Annex E, stage 1). For the School Innovation and Improvement Fund, "Recipient schools are not required to submit funding proposals; instead, they shall ensure that planned activities are reflected in their approved School Improvement Plan (SIP) and Annual Implementation Plan (AIP)" ([DepEd Memorandum No. 048, s. 2026](https://www.deped.gov.ph/2026/08/03/august-3-2026-dm-048-s-2026-allocation-and-release-of-the-school-innovation-and-improvement-fund-to-non-implementing-unit-public-schools-to-strengthen-decentralization-practices-in-the-de/), Encl., Sec. III.1). A 2026 pilot for learners and teacher-coaches in competitions, GAS-TUKLAS, requires that "A Work and Financial Plan (WFP) shall be prepared and submitted" for funds downloaded to schools, without naming who prepares it ([DepEd Memorandum No. 046, s. 2026](https://www.deped.gov.ph/wp-content/uploads/DM_s2026_046r.pdf), Sec. VII.b).

**Who writes the WFP, fund by fund.** For each fund: what the national text has the school prepare, what it gives the division office and the regional and central offices, and the clause, quoted.

*In force on November 26, 2026*

- **School MOOE.** The school: SIP and AIP; the AIP in calendar-year form, by month and fund source; A WFP on the division's own template, where its memo asks (division practice). The division office: Releases a non-IU school's cash on its monthly disbursement program; Calls for, appraises and approves school WFPs (division practice). Regional and Central Offices: Sets no school WFP form; WFPs in the PMIS are for the offices only. "in the case of the field offices or schools, in accordance with the approved WFP/Annual Implementation Plan and the APP for the current year of the office/school concerned" (DO 017, s. 2024, Annex A, item B (the authority to procure)). In force. DO 008, s. 2019 ties MOOE to the SIP and the AIP (Sec. V.D.1). DO 011, s. 2021 promised a separate policy on schools' use of the PMIS (Part VIII.1), not issued as of November 26, 2026. Bulacan, Dasmariñas City, Kabankalan City, Ligao City, Nueva Vizcaya and Tangub City, among others, in 2026.
- **ALS program support fund, part downloaded to the school.** The school: The updated WFP and AIP, sent to the SDO; Physical and financial accomplishment reports and liquidation reports. The division office: Its Expenditure Matrix, uploaded in the PMIS. Regional and Central Offices: Regional Office: its Expenditure Matrix in the PMIS; Central Office: Sub-AROs. "Prepare and submit the updated WFP, AIP and other related documents to the SDO, including the physical and financial accomplishment reports and liquidation reports" (DO 028, s. 2022, item 38(a)). In force: the guidelines cover Calendar Year 2022 and the years after it.
- **SNEd (SPED) program support fund.** The school: An AIP with the program's activities, for the SDS's approval. The division office: The WFP in the PMIS, built from the schools' approved AIPs. Regional and Central Offices: Regional planning division endorses the SDO-approved plan for release. "prepare the Work and Financial Plan (WFP) through the Program Management Information System (PMIS) based on the approved AIP of the recipient schools" (DO 042, s. 2021, item 5.4). In force since FY 2021 (item 4).
- **School-Based Feeding Program.** The school: Orientations for parents and teachers; kitchens and facilities ready. The division office: The WFP and the funding allocation per school; The 20-day cycle menu, with the LGU. Regional and Central Offices: Nothing named. "SDO prepares the Work and Financial Plan (WFP) and identifies funding allocation per school" (DO 013, s. 2026, Annex E, stage 1 (DepEd-led)). In force since June 4, 2026. The chips are the order's column for the program where DepEd runs it; where the LGU runs it, the SDO provides the master list of beneficiaries.
- **School Innovation and Improvement Fund (FY 2026).** The school: The planned activities in the approved SIP and AIP; no funding proposal; A SIIF WFP on the division's template, where asked (division practice). The division office: Asks for a SIIF WFP in some divisions (division practice). Regional and Central Offices: Sets each school's allocation, 'predetermined and final'. "Recipient schools are not required to submit funding proposals; instead, they shall ensure that planned activities are reflected in their approved School Improvement Plan (SIP) and Annual Implementation Plan (AIP)" (DM 048, s. 2026, Encl., Sec. III.1). The FY 2026 release. Abra and Cebu Province asked their recipient schools for a SIIF WFP in 2026.

*Lapsed or revoked: what DepEd once asked*

- **SPED support fund, 2015.** The school: A WFP on the PMIS Excel template, culled from the approved AIP. The division office: Calls for, appraises and approves the schools' WFPs. Regional and Central Offices: Regional planning division endorses the approved plans for release. "the recipient schools shall prepare and submit WFP, which shall be subject to the SDO's appraisal. Projects and activities chargeable to the fund may be culled out from the approved AIP of the schools." (DO 38, s. 2015, item 5.1.6). Followed in 2021 by DO 042, s. 2021, under which the division office prepares the WFP.
- **Special curricular programs, FY 2014.** The school: A WFP for the fund on Enclosure No. 2.a, culled from the approved AIP. The division office: Calls for and appraises the schools' WFPs. Regional and Central Offices: Nothing named. "Using the template in Enclosure No. 2.a, the schools shall prepare the Work and Financial Plan specific to the fund support and shall submit to the SDO for appraisal." (DO 15, s. 2014, item 3.1.2). Lapsed: it governed the FY 2014 funds.
- **SBM grants for FY 2014.** The school: A WFP with the eligible activities, posted for the public. The division office: SGOD approves a WFP that holds eligible activities. Regional and Central Offices: Nothing named. "If a recipient school submits a WFP with the eligible activities set in these guidelines, the WFP shall be approved." (DO 45, s. 2015, item 7.1.2). Lapsed: the grant was valid until December 31, 2015 (item 1.2).
- **Senior high school MOOE, 2018.** The school: The proposed uses of SHS MOOE in the school's WFP, on the attached format. The division office: Nothing named. Regional and Central Offices: Nothing named. "The uses of SHS MOOE being proposed by the school head must be reflected in the school's Work and Financial Plan, format hereto attached." (DO 9, s. 2018, item 26). Revoked by DO 008, s. 2019 (item 2).

No DepEd order in force sets a WFP form for a school's MOOE; for a school, the AIP does the work of the WFP. Many divisions require a WFP of every school, and a school head files it because the division's memorandum says so.

## What a school WFP contains

A WFP holds the same activities as the AIP, with their targets and costs spread across the months. What the columns are depends on the template, since the only national formats are the PMIS's for offices and DO 008's Annex 1 for the AIP.

The AIP format of DO 008, s. 2019 (Annex 1) already has a WFP's shape. For each program, project or activity it sets the objective, the output or performance indicator and the budget source, then a target and an amount for every month from January to December, with quarter totals, the full year, and the first quarter of the next year. Its footer totals the MOOE, the Special Education Fund (SEF) and other funds, such as PTA funds, canteen funds and donations. [The sample SIP and AIP](https://nash.com.ph/blog/school-improvement-plan-sample-sip-aip-template) sets a reading project on this format.

Division WFP templates fall into two families.

| Family | Its columns | Examples |
|---|---|---|
| Planning-type | The BEDP pillar or priority improvement area, the program or activity, its output, indicators and physical targets, the schedule and the resources needed | Imus City's FY 2026 presentation template; Abra's SIIF WFP; Tayabas City's SNEd WFP; Pasay City South High School's FY 2021 WFP |
| Budget-type | The program, project or activity; the object of expenditure, with its Unified Accounts Code Structure (UACS) code in some sheets; a target; the total; tax withheld; the net of tax; amounts by month and quarter | Bulacan's FY 2027 WFP sheet, which names the objects without codes and sits in a workbook with a School Operating Budget, a cash program and a BED No. 3; Nueva Vizcaya's request sheet, with UACS codes |

A few templates join the two, as the PMIS does: a physical plan, an obligation program and a disbursement program, month by month. The guide to [making a school WFP](https://nash.com.ph/blog/make-school-work-financial-plan) explains each column of both families, how to write outputs, indicators and targets, and how to trace each PPA to its SIP objective, AIP line, BEDP pillar and the division's priorities.

## What Schools Division Offices ask schools for

Division memoranda of 2024 to 2026 share most of their demands and differ mostly in the form. These are division practice, not national rules, and a school follows its own division's memorandum.

| What divisions ask | How it runs | Examples |
|---|---|---|
| A WFP from every school, each year | Called between September and December for the next fiscal year | Bulacan, Dasmariñas City, Kabankalan City, Ligao City, Nueva Vizcaya and Tangub City for FY 2027 |
| The NEP figure as the ceiling | The division sends each school its MOOE in the NEP; the plan is adjusted once the GAA is enacted | Dasmariñas City sent the FY 2027 list on August 25, 2026 and told schools they "may also start the post-planning process" |
| The SIP and the AIP as the basis | The WFP's activities come from the SIP's improvement areas and the AIP | Kabankalan City's appraisal asked school heads to bring the approved SIP |
| Procurement and budget documents with it | The PPMP and APP; where the Budget Office leads, the School Operating Budget, a cash program and BED No. 3 | Bulacan asked for the WFP, cash program, School Operating Budget, AIP and BED 3 by October 26, 2026 |
| Totals that agree | The WFP total equals the NEP figure, the School Operating Budget and the PPMP and APP | Imus City's evaluation tool checks that "The same total amount were [sic] reflected in the PPMP, APP, and WFP"; Nueva Vizcaya's sheet wants the variance "exactly zero" |
| Amounts by month or quarter | So the division can program the school's cash | Bulacan's sheet by month; Misamis Oriental's FY 2026 matrix in quarterly shares |
| A division review | A panel appraises each plan and returns it with comments | Kabankalan City's appraisal committee, with its Accountant III, Administrative Officer V for budget, Senior Education Program Specialist and Planning Officer III, met school heads from October 20 to November 11, 2026 |

What varies is the template itself: its columns, its signatories, whether it asks for physical targets, and whether it goes through the PMIS. For FY 2025, Region X had its secondary schools that are implementing units prepare their WFPs in the PMIS, as the offices do. Program funds come with WFPs of their own, on their own forms: some divisions asked SIIF recipients for a SIIF WFP in 2026, and others asked for WFPs for the SNEd fund (in 2025) or for the DepEd Computerization Program's downloads (in 2026).

## Who prepares, reviews and approves a WFP

At the offices, DO 017, s. 2024 names every signatory (Annex A, item A).

| Office | Prepared by | In coordination with | Recommending approval | Approved by |
|---|---|---|---|---|
| Schools Division Office: Office of the SDS and of the ASDS | The second highest-ranking personnel in each office | The Planning Officer of the SGOD Planning and Research Section and the Budget Officer (OSDS-Finance) | Assistant Schools Division Superintendent | Schools Division Superintendent |
| Schools Division Office: Curriculum Implementation Division, School Governance and Operations Division | The functional division chief | The same | Assistant Schools Division Superintendent | Schools Division Superintendent |
| Regional Office: Office of the RD, Office of the ARD, functional divisions | The next highest-ranking personnel, or the functional division chief | The Chief of the Policy, Planning and Research Division and the Finance Division | Assistant Regional Director | Regional Director |

The Central Office's units have their own rows, ending with the Secretary or the Undersecretaries in charge of planning and of finance. Before approval, an office's planning unit reviews the WFP with finance and procurement in a "triangulation" that checks alignment with the "Regional Basic Education Plan (RBEP)/Division Education Development Plan (DEDP)", and the reviewer is given three working days (DO 011, s. 2021, Part V.B.3(g)).

At the school, no national text names a WFP's signatories. The School Planning Team prepares the SIP and the AIP. It has at least seven members: the school head as team leader, a student, a teacher, a parent, a barangay or local government representative, a member of the Barangay Disaster Risk Reduction and Management Council and a member of the school's Child Protection Committee (DO 44, s. 2015, SIP Guidebook, Activity 1.2). DO 44 sets no SDS approval of the AIP; program orders such as DO 042, s. 2021 (item 5.3) do. The school head approves each Authority to Procure, which must follow the approved WFP or AIP and the APP (DO 017, s. 2024, Annex A, item B). The Q-BEDP adds that "School plans shall be appraised by the SDO" (Annex 2, item 3.vii).

Divisions fill the gap in their templates. The school head prepares the WFP. Reviewers vary: an Accountant III in Bulacan, the district supervisor and several division sections for Abra's SIIF WFP, the Curriculum Implementation Division chief for Tayabas City's SNEd WFP. The approver is the ASDS on Bulacan's FY 2027 MOOE WFP and the SDS on the program-fund WFPs of Abra, Cebu Province and Tayabas City.

## When a WFP is prepared: the planning calendar

A WFP is planned in one year and spent in the next. The fiscal year is the calendar year: school MOOE is "valid for release and obligation for one fiscal year: that is from January 1 to December 31" (DO 008, s. 2019, Sec. I.3). The GAA can extend that; the FY 2026 GAA keeps FY 2026 MOOE valid until December 31, 2027 (NBC No. 599, item 3.3). A school year does not match the fiscal year. School Year 2026-2027 runs from June 8, 2026 to April 8, 2027 ([DepEd Order No. 009, s. 2026](https://www.deped.gov.ph/2026/04/16/april-16-2026-do-009-s-2026-guidelines-on-the-implementation-of-the-three-term-school-calendar-in-basic-education/), item 4), so the FY 2027 plan covers the last term of one school year and the first months of the next.

**The planning year and the budget year: the FY 2027 calendar.** Each entry is marked as a national rule, a division practice (what a Schools Division Office asked of its schools in a 2026 memo, an example, not a rule) or a date.

*2026, the planning year*

- **January 2026** (DBM, national rule): DBM issues the National Budget Call for FY 2027 on January 5, 2026, which starts every agency's budget proposal. (DBM National Budget Memorandum No. 156)
- **January 2026** (DepEd offices, national rule): Central, regional and division offices prepare their FY 2027 WFP, PPMP and common-use supplies list in the PMIS from January to March. (DO 011, s. 2021, Annex 1, A.I.1)
- **March 2026** (DepEd offices, national rule): The offices submit the WFP, PPMP and common-use supplies list for the next fiscal year on or before the end of March. (DO 011, s. 2021, Annex 1, A.I.1)
- **June 2026** (School, date): School Year 2026-2027 opens on June 8, 2026 and ends on April 8, 2027. (DO 009, s. 2026, item 4)
- **July 2026** (Congress and the President, national rule): Congress convenes on the fourth Monday of July (July 27, 2026), and the President submits the budget within 30 days. (1987 Constitution, Art. VI, Sec. 15; Art. VII, Sec. 22)
- **August 2026** (DBM, date): DBM's page for the FY 2027 National Expenditure Program (NEP), the President's proposed budget, is dated August 11, 2026. (DBM, National Expenditure Program FY 2027)
- **August 2026** (DepEd offices, national rule): Offices adjust their WFP, PPMP and common-use supplies list to the NEP within three working days after it is issued. (DO 011, s. 2021, Annex 1, A.I.2)
- **August 2026** (Procuring entity, national rule): Once the NEP is submitted to Congress, end-users revise their PPMPs to the budget it proposes. (IRR of RA 12009, Sec. 7.7.3)
- **August 2026** (Division office, division practice): Divisions send schools their FY 2027 MOOE at the NEP level, the ceiling of the school's plan, from August to November 2026: Dasmariñas City on August 25, Nueva Vizcaya with its memo of November 12. (Dasmariñas City DM 646, s. 2026; Nueva Vizcaya DM 460, s. 2026)
- **August 2026** (School, national rule): Schools send their funding requests for the 2027 Special Education Fund to the district supervisor (municipal school board) or the SDS (city school board) not later than August 31, in the Joint Circular's indicative timeline. (Joint Circular No. 01, s. 2025, §6.8)
- **August 2026** (School, national rule): The standing deadline for uploading next year's APP-CSE on mPhilGEPS is August 31. (GPPB Resolution No. 20-2018, Annex A, item 5.2)
- **September 2026** (School, date): PS-DBM extended the FY 2027 APP-CSE deadline to September 15, 2026. (PS-DBM Advisory No. 2026-22)
- **September 2026** (Division office, division practice): Division memos asking every school for its FY 2027 plans go out. Tangub City, on September 24, 2026, asked for the AIP, the APP for non-CSE items, the PPMP, the WFP, the School Operating Budget and the Monthly Disbursement Plan. (Tangub City DM 363, s. 2026)
- **October 2026** (Division office, division practice): Bulacan asked its elementary and non-IU secondary schools for the WFP, cash program, School Operating Budget, AIP and BED 3 by October 26, 2026. (Bulacan DM 468, s. 2026)
- **October 2026** (Division office, division practice): Kabankalan City appraised its schools' FY 2027 WFPs from October 20 to November 11, 2026, with each school head bringing the approved SIP. (Kabankalan City DM 348, s. 2026)
- **October 2026** (Local School Board, national rule): The municipal or city Local School Board approves the SEF budget for the coming year by resolution not later than October 31, in the same indicative timeline. (Joint Circular No. 01, s. 2025, §6.8)
- **November 2026** (Division office, division practice): Ligao City set November 4, 2026 for the WFP, PPMP, APP and Monthly Disbursement Program; Nueva Vizcaya set November 30 for the AIP, WFP and its Request for Subsidy. (Ligao City DM 0509, s. 2026; Nueva Vizcaya DM 460, s. 2026)
- **November 2026** (DBM, national rule): Agencies submit their budget execution documents (BEDs) based on the NEP by November 15 (non-regionalized) or November 30 (regionalized). (DBM Circular Letter No. 2022-14, item 4.5.1)
- **December 2026** (Division office, division practice): Dasmariñas City asked for each school's AIP and WFP for FY 2027 by December 4, 2026. (Dasmariñas City DM 859, s. 2026)
- **December 2026** (Congress and the President, national rule): The FY 2027 GAA was not yet enacted on November 26, 2026. Once it is, offices adjust their WFP within three working days if Congress changed the NEP, and agencies send GAA-consistent BEDs within 15 working days. (DO 011, s. 2021, Annex 1, A.I.2; DBM Circular Letter No. 2022-14, item 4.5.3.2)

*2027, the budget year*

- **January 2027** (School, national rule): School MOOE is valid for release and obligation from January 1 to December 31, and the AIP follows the calendar year. (DO 008, s. 2019, Secs. I.3 and V.D.1)
- **January 2027** (Procuring entity, national rule): Once the GAA is final, PPMPs are finalized into the final APP, which is posted and submitted to the GPPB on or before the end of January. (IRR of RA 12009, Sec. 7.7.5)
- **January 2027** (Division office, national rule): For a non-IU school, the cash for MOOE is set by its monthly disbursement program (MDP) and released by the SDO in the first week of each month or quarter. (DO 029, s. 2019, item 18)
- **March 2027** (School, national rule): The school head conducts the quarterly Program Implementation Review (PIR) of physical and financial accomplishments, and the transparency board is updated every three months. (DO 029, s. 2022, Sec. VIII, item f; DO 008, s. 2019, Sec. VI.A.4)
- **March 2027** (DepEd offices, national rule): After each quarterly PIR, offices have ten working days to revise their WFP through plan adjustment. (DO 011, s. 2021, Part III, item m)
- **April 2027** (School, date): School Year 2026-2027 ends on April 8, 2027, in the middle of the fiscal year. (DO 009, s. 2026, item 4)
- **June 2027** (School, national rule): The second quarterly PIR, with the transparency board updated again. (DO 029, s. 2022, Sec. VIII, item f)
- **June 2027** (School, date): DepEd's calendar sets Brigada Eskwela and enrollment for the next school year on June 7 to 11, 2027. (DO 009, s. 2026, Annex B)
- **August 2027** (School, national rule): The FY 2028 APP-CSE is due on mPhilGEPS by August 31, 2027, unless PS-DBM sets another date. (GPPB Resolution No. 20-2018, Annex A, item 5.2)
- **August 2027** (School, national rule): Funding requests for the 2028 SEF are due by August 31, 2027, in the Joint Circular's indicative timeline. (Joint Circular No. 01, s. 2025, §6.8)
- **September 2027** (School, national rule): The third quarterly PIR. (DO 029, s. 2022, Sec. VIII, item f)
- **September 2027** (Division office, division practice): The cycle repeats: divisions called for the FY 2025, FY 2026 and FY 2027 school plans between August and December of the year before. (Region X RM 932, s. 2024; Imus City DM 768, s. 2025; and the 2026 memos)
- **December 2027** (School, national rule): The year's last quarterly PIR; activities not done go into the next year's AIP. (DO 029, s. 2022, Sec. VIII, item f; FMOM, p. 45)
- **December 2027** (School, national rule): DO 008 makes school MOOE valid to December 31 of its year; the year's GAA sets the actual period, and the FY 2026 GAA kept FY 2026 MOOE valid to December 31, 2027. (DO 008, s. 2019, Sec. I.3; NBC No. 599, item 3.3)

The quarterly reviews are placed in each quarter's last month: DO 029, s. 2022 sets the review quarterly and names no month.

| When | What happens | Rule or practice |
|---|---|---|
| January 5, 2026 | DBM issues the National Budget Call for FY 2027 | DBM National Budget Memorandum No. 156 |
| January to March 2026 | DepEd offices prepare their FY 2027 WFP, PPMP and common-use supplies list in the PMIS, and submit them by the end of March | DO 011, s. 2021, Annex 1, A.I.1 |
| August 2026 | The NEP is submitted to Congress, within 30 days of the session's opening on July 27, 2026; offices adjust their WFPs within three working days; end-users revise their PPMPs to the NEP | DO 011, s. 2021, Annex 1, A.I.2; IRR of RA 12009, Sec. 7.7.3 |
| August to November 2026 | Divisions send schools their MOOE at the NEP level | Division practice |
| August 31 | Schools' funding requests for the next year's SEF (in the Joint Circular's indicative timeline); the next year's APP-CSE (PS-DBM moved the FY 2027 deadline to September 15, 2026) | Joint Circular No. 01, s. 2025, §6.8; GPPB Resolution No. 20-2018, Annex A, item 5.2 |
| September to December 2026 | Divisions call for, appraise and return school WFPs | Division practice |
| October 31 | The Local School Board approves the next year's SEF budget (in the same indicative timeline) | Joint Circular No. 01, s. 2025, §6.8 |
| November 15 or 30 | Agencies submit BEDs based on the NEP to DBM | DBM CL No. 2022-14, item 4.5.1 |
| After the GAA is signed | Offices adjust their WFPs within three working days if Congress changed the NEP; agencies submit GAA-consistent BEDs within 15 working days | DO 011, s. 2021, Annex 1, A.I.2; DBM CL No. 2022-14, item 4.5.3.2 |
| End of January 2027 | The final APP is posted and submitted to the GPPB | IRR of RA 12009, Sec. 7.7.5 |
| January to December 2027 | Cash released each month or quarter on a non-implementing school's monthly disbursement program; a PIR every quarter | DO 029, s. 2019, item 18; DO 029, s. 2022, Sec. VIII, item f |

## How a WFP is reviewed and adjusted during the year

A WFP is checked against what was done every quarter and changed where the work fell behind. The national duty at school level is the PIR: the school head shall "Conduct quarterly Program Implementation Review (PIR) in the school to track physical and financial accomplishments and assess the progress of implementation of plans, programs, projects, and major activities" ([DepEd Order No. 029, s. 2022](https://www.deped.gov.ph/2022/06/22/june-20-2022-do-029-s-2022-adoption-of-the-basic-education-monitoring-and-evaluation-framework/), Sec. VIII, item f). The [guide to school monitoring, evaluation and adjustment](https://nash.com.ph/blog/deped-smea-school-monitoring-evaluation-adjustment) covers how schools hold it.

For offices, the PMIS order sets the clock. "After the conduct of the PIR, program proponents are given ten (10) working days to revise their Work and Financial Plan through Plan Adjustment" (DO 011, s. 2021, Part III, item m). The revised plan is reviewed within three working days and approved within five working days after the review (Annex 1, A.IV). The adjustments "will work on the remaining approved budget lodged to their office" (Part V.D.2): an adjustment moves money and targets within what is left, and adds no money.

No national text sets a deadline for a school's adjustment. Three rules still shape it. The school posts the sources and uses of its funds on its transparency board, "updated every three (3) months" (DO 008, s. 2019, Sec. VI.A.4). Its cash follows its monthly disbursement program: the cash for a non-implementing school's MOOE "will be determined by the expenditures needed based on its MDP" (DO 029, s. 2019, item 18). And activities left undone carry forward: "any item not accomplished for the year shall be included in the AIP of the following year" (FMOM, p. 45). The guide to [making a school WFP](https://nash.com.ph/blog/make-school-work-financial-plan) shows a plan adjustment and its variance analysis.

## What auditors found in DepEd's plans

The Commission on Audit (COA) has linked reverted funds and unplanned purchases in DepEd to plans that were not followed or not made.

- **Plans not carried out on schedule.** In Benguet, in the Cordillera Administrative Region, "Several non-IUs have encountered difficulties in executing their Work and Financial Plan (WFP) according to their schedule which resulted to reversion of unutilized fund to the National Treasury amounting to P111,717.25 while P1,133,179.59 remained unreleased at year-end" ([COA, 2023 Consolidated Annual Audit Report on DepEd](https://www.coa.gov.ph/wpfd_file/department-of-education-consolidated-annual-audit-report-2023/), Part II, Obs. 3, pp. 154-155). COA recommended that the division offices of Benguet and Baguio City "diligently monitor the utilization of allotted funds, using the WFP as a guide" (p. 160).
- **Purchases outside the plan.** In Naga City, "Procurements of Non-IUs are not in accordance with their approved Monthly Disbursement Program which was based on their APP" (2023 report, Table No. 99, p. 320). COA recommended that the school heads "ensure that school's procurements are included in their approved Monthly Disbursement Program and hence are aligned with their approved APP" (par. 12.15(b), p. 321).
- **Procurement plans missing.** In 2025, COA found "Non-submission/ Deficiencies in the preparation of Annual Procurement Plan (APP) and PPMP" in the Cordillera, the National Capital Region and Regions I to VI and VIII: "Failure to prepare/submit APPs", "Outdated/incomplete forms" and "Missing technical specifications". Management agreed to "instruct the concerned schools and offices to prepare and approve consolidated APP and PPMP" and to "adopt supplemental APPs and PPMPs for newly identified projects and align APPs with approved budgets" ([COA, 2025 Consolidated Annual Audit Report on DepEd](https://www.coa.gov.ph/wpfd_file/department-of-education-consolidated-annual-audit-report-2025/), Part II, Obs. 20, Table No. 84, p. 221).

## What this means for school heads

- **Read the division memorandum first.** It decides whether the school files a WFP, on which template, with which documents, by when and to whom. Keep a copy with the plan.
- **Write the AIP first, then the WFP from it.** Both carry the same activities, and the WFP's amounts match the AIP's MOOE amounts, spread by month. A WFP activity that is not in the SIP and AIP has no basis under DO 008, s. 2019 (Sec. V.D.1).
- **Plan to the NEP figure, and expect to adjust.** The division's NEP-level figure is a proposal until the GAA is enacted. Keep the planning team's working file so the plan can be changed quickly once the GAA amount arrives.
- **Put the mandatory expenses first.** School MOOE is used "subject to availability of funds and prioritization of mandatory expense items" (DO 008, s. 2019, Sec. V.D). The order does not list those items. Plan the bills the school must pay every month, such as electricity and water, before new projects.
- **Mark what will be bought.** Every item bought needs a line in the PPMP and the APP, and common-use supplies from PS-DBM need the APP-CSE by August 31 of the year before, unless PS-DBM sets another date. The guide to [the APP-CSE](https://nash.com.ph/blog/app-cse-deped-ps-dbm) has the form and the deadlines, and the guide to [school procurement under RA 12009](https://nash.com.ph/blog/deped-school-procurement-ra-12009) has the rest.
- **Spread the amounts as the money will be spent.** The monthly amounts become the monthly disbursement program on which the division releases a non-implementing school's cash. A plan that bunches its amounts in the last months leaves too little cash for the months before them.
- **Review every quarter and record the changes.** Hold the PIR, compare what was done with the plan, and adjust the months and amounts still ahead. Keep the PIR minutes, the adjusted plan and the transparency board postings together.
- **Spend only what the plan holds.** COA's findings above came from plans not followed: money reverted, and purchases outside the disbursement program and the APP.

The planning duties serve two strands of the Philippine Professional Standards for School Heads (PPSSH): school planning and implementation, in [Domain 1](https://nash.com.ph/blog/ppssh-domain-1-leading-strategically), and financial management, in [Domain 2](https://nash.com.ph/blog/ppssh-domain-2-managing-school-operations).

## How the NASH may test this

The items below are original practice items, scored 3 (Relational), 2 (Multistructural), 1 (Unistructural) or 0 (Prestructural). An option that breaks a rule scores 0.

### Question 1

*Indicator 1.2.1, School planning and implementation. Career Stage 1, Conceptual, Moderate.*

A head teacher preparing to lead a school asks how the Work and Financial Plan (WFP) that the division asks of every school relates to the school's School Improvement Plan (SIP) and Annual Implementation Plan (AIP). Which statement best explains the relationship?

- **A.** The WFP restates the AIP's MOOE activities as monthly targets and payments, so its activities come from the SIP and its total matches the MOOE allocation.
- **B.** The WFP lists the year's activities, targets and monthly costs, and the AIP lists the school's projects, objectives and budget sources for that same fiscal year.
- **C.** The WFP is the school's financial document for the fiscal year, since it shows how much of the school's MOOE it expects to spend in each month.
- **D.** The WFP replaces the AIP once the division approves it, so the school may then fund activities that its SIP and AIP do not contain.

**Answer and explanation**

**Best answer: A.** Points: A = 3, B = 2, C = 1, D = 0.

- **A (3 points, Relational).** It places the WFP in the chain of plans: the SIP sets the three-year priorities, the AIP the year's activities and budget, and the WFP restates them as monthly targets and payments, so the three agree.
- **B (2 points, Multistructural).** It describes what each document holds but never relates them, missing that the WFP's activities and amounts come from the AIP and, through it, the SIP.
- **C (1 point, Unistructural).** It sees one element, the money by month, and leaves out the physical targets and the plan the activities come from.
- **D (0 points, Prestructural).** School MOOE pays only for activities in the approved SIP "as specifically determined in the Annual Implementation Plan (AIP)" (DO 008, s. 2019, Sec. V.D.1); no approval of a WFP lets a school fund activities outside them.

**Why.** This aligns with Career Stage 1 expectations because the indicator asks for an understanding of how school plans are developed and implemented in line with institutional policies. DO 008, s. 2019 ties school MOOE to the SIP and the AIP, whose calendar-year format already sets monthly targets and amounts (Sec. V.D.1, Annex 1), and DepEd defines the WFP as the plan of "monthly physical, obligation, and disbursement plans" (DO 017, s. 2024, Annex A, item A). The 2-point option knows what each document holds but not that one is drawn from the other.

*Indicator 1.2.1: Demonstrate knowledge and understanding of the phases of development and implementation of school plans aligned with institutional goals and policies.*

*Sources: DepEd Order No. 008, s. 2019, Sec. V.D.1 and Annex 1; DepEd Order No. 017, s. 2024, Annex A, items A and B.*

### Question 2

*Indicator 2.2.2, Financial management. Career Stage 2, Situational, Moderate.*

You are the school head of a non-implementing-unit elementary school in an upland district. At the first quarterly review of the fiscal year, your planning team finds that the reading remediation supplies scheduled for February were not bought because the supplier ran out of stock, while the electricity bills have been higher than the monthly amounts in the school's approved WFP. A teacher suggests holding the unspent amount until November and then buying tablets for the faculty room so that no money goes back to the Treasury. What is the most appropriate action?

- **A.** Reschedule the reading supplies to the next quarter and pay the higher electricity bills, keeping the approved WFP and APP as they are since the year's MOOE total stays the same.
- **B.** Hold the unspent amount and buy tablets for the faculty room in November, so that the money is used up before the fiscal year ends.
- **C.** Pay the higher electricity bills within the year's MOOE and submit a revised WFP, APP and disbursement program, buying the reading supplies once these are approved.
- **D.** Record the delayed purchase and the higher bills in the review's minutes, then wait for the division to issue instructions on a supplemental APP before acting.

**Answer and explanation**

**Best answer: C.** Points: A = 2, B = 0, C = 3, D = 1.

- **A (2 points, Multistructural).** It makes the right two moves but leaves the WFP, the APP and the monthly disbursement program out of step with what the school will now buy and pay, the gap COA found in non-IU schools whose purchases did not follow their approved disbursement programs.
- **B (0 points, Prestructural).** A purchase must be "in accordance with the approved WFP/Annual Implementation Plan and the APP" (DO 017, s. 2024, Annex A, item B), and no procurement may be undertaken outside the approved APP (IRR of RA 12009, Sec. 7.8). Buying unplanned tablets to use up the money breaks both rules.
- **C (3 points, Relational).** It meets the bills from the year's MOOE, keeps the reading project for the learners, and has the WFP, the APP and the monthly disbursement program revised and approved before the supplies are bought, so cash and purchases follow an approved plan.
- **D (1 point, Unistructural).** It records the problem, which the quarterly review is for, but waits instead of adjusting the plan, so the project stays stalled and the bills stay unplanned.

**Why.** This aligns with Career Stage 2 expectations because the school head manages allocation, procurement and disbursement in line with the school plan. The quarterly review exists "to track physical and financial accomplishments" (DO 029, s. 2022, Sec. VIII, item f); MOOE is used "subject to availability of funds and prioritization of mandatory expense items" (DO 008, s. 2019, Sec. V.D); cash follows the school's monthly disbursement program (DO 029, s. 2019, item 18); and changed procurement plans may be made "as often as necessary" (IRR of RA 12009, Sec. 7.9). COA recommended that school heads, "whenever there are changes thereto, to seek approval of revised or supplementary APP, as the case maybe [sic], before proceeding with any procurement" (2023 Annual Audit Report, par. 12.15(b)). The 2-point option adjusts the work but not the plans that cash and purchases must follow.

*Indicator 2.2.2: Manage finances adhering to policies, guidelines and issuances in allocation, procurement, disbursement and liquidation aligned with the school plan.*

*Sources: DepEd Order No. 029, s. 2022, Sec. VIII; DepEd Order No. 008, s. 2019, Sec. V.D; DepEd Order No. 029, s. 2019, item 18; DepEd Order No. 017, s. 2024, Annex A, item B; Implementing Rules and Regulations of Republic Act No. 12009, Secs. 7.8 and 7.9; Commission on Audit, 2023 Annual Audit Report on DepEd, par. 12.15.*

Nothing in this guide reproduces or predicts examination content.

## Frequently asked questions

### What is the meaning of WFP in DepEd?

WFP means Work and Financial Plan: an office's annual operational plan of programs, outputs and activities, with their timelines and budget, set out as monthly physical, obligation and disbursement plans (DO 017, s. 2024, Annex A, item A). In the PMIS it is made of the Physical Plan, the Monthly Obligation Program and the Monthly Disbursement Program (DO 011, s. 2021, Part III, item r).

### Is the WFP the same as the AIP?

No, though for a school's MOOE they carry the same activities and amounts. The AIP is the school's annual plan under DO 008, s. 2019 (Sec. V.D.1), and its Annex 1 already sets a target and an amount for each month. A WFP is the office's budget execution plan under DO 011, s. 2021, and the plan a division asks of its schools on its own template.

### Are there DepEd guidelines and a template for a school WFP?

Not for a school's MOOE: on November 26, 2026, no DepEd order in force set a WFP form or template for it. DepEd's WFP guidelines, DO 011, s. 2021, cover the offices and promise a separate policy for schools (Part VIII.1), and each division that asks for a school WFP provides its own template. The [sample school WFP](https://nash.com.ph/blog/school-work-financial-plan-sample) offers a template of NASH Reviewer's own, which a division's template replaces wherever one is prescribed.

### Who approves a school's WFP?

The division that asks for it, through the officials its memorandum names. On Bulacan's FY 2027 MOOE WFP the school head prepares, an Accountant III reviews and the ASDS approves; on several divisions' program-fund WFPs the SDS approves. No national text names a school WFP's approver; DO 017, s. 2024 names approvers only for the offices (Annex A, item A).

### Is the WFP based on the NEP or the GAA?

Both, in turn. Divisions have schools plan on their MOOE in the NEP, because the GAA is not yet enacted when they call for the plans, and then adjust to the GAA. For offices, the adjustment comes within three working days after the GAA is issued, when Congress changed the NEP (DO 011, s. 2021, Annex 1, A.I.2).

## Sources

**DepEd issuances**

- [DepEd Order No. 011, s. 2021](https://www.deped.gov.ph/2021/02/24/february-24-2021-do-011-s-2021-guidelines-on-the-operationalization-of-the-program-management-information-system/), Guidelines on the Operationalization of the Program Management Information System, February 24, 2021: Parts II, III (items m and r), V.B.3, V.D.2, VIII.1; Annex 1.
- [DepEd Order No. 017, s. 2024](https://www.deped.gov.ph/2024/12/04/december-4-2024-do-017-s-2024-amendment-to-the-provisions-of-deped-order-no-001-s-2023-on-signing-authorities-for-financial-matters-in-the-department-of-education/), Amendment to the Provisions of DepEd Order No. 001, s. 2023 on Signing Authorities for Financial Matters, December 4, 2024: Annex A, items A and B.
- [DepEd Order No. 008, s. 2019](https://www.deped.gov.ph/2019/05/02/may-2-2019-do-008-s-2019-revised-implementing-guidelines-on-the-direct-release-use-monitoring-and-reporting-of-maintenance-and-other-operating-expenses-allocation-of-schools-including-other-fu/), Revised Implementing Guidelines on the Direct Release, Use, Monitoring and Reporting of MOOE Allocation of Schools, May 2, 2019: item 2; Secs. I.3, V.D, VI.A.4; Annex 1.
- [DepEd Order No. 029, s. 2019](https://www.deped.gov.ph/2019/10/17/october-17-2019-do-029-s-2019-procedural-guidelines-on-the-management-of-cash-advances-for-school-maintenance-and-other-operating-expenses-and-program-funds-of-non-implementing-units-pursuant-to/), Procedural Guidelines on the Management of Cash Advances for School MOOE and Program Funds of Non-Implementing Units, October 17, 2019: item 18.
- [DepEd Order No. 029, s. 2022](https://www.deped.gov.ph/2022/06/22/june-20-2022-do-029-s-2022-adoption-of-the-basic-education-monitoring-and-evaluation-framework/), Adoption of the Basic Education Monitoring and Evaluation Framework, June 2022: Sec. VIII.
- [DepEd Order No. 024, s. 2022](https://www.deped.gov.ph/2022/05/30/may-30-2022-do-024-s-2022-adoption-of-the-basic-education-development-plan-2030/), Adoption of the Basic Education Development Plan 2030, May 30, 2022: item 4; Sec. 7.1.
- [DepEd Order No. 44, s. 2015](https://www.deped.gov.ph/2015/09/29/do-44-s-2015-guidelines-on-the-enhanced-school-improvement-planning-sip-process-and-the-school-report-card-src/), Guidelines on the Enhanced School Improvement Planning Process and the School Report Card, September 29, 2015: SIP Guidebook, Activity 1.2.
- [DepEd Order No. 60, s. 2016](https://www.deped.gov.ph/2016/09/02/do-60-s-2016-implementation-of-the-financial-management-operations-manual-and-orientation-of-deped-financial-management-staff-at-the-regional-division-and-school-levels/), Implementation of the Financial Management Operations Manual, September 2, 2016: the FMOM, pp. 45, 46, 127 and Glossary.
- [DepEd Order No. 028, s. 2022](https://www.deped.gov.ph/2022/06/20/june-20-2022-do-028-s-2022-implementing-guidelines-on-the-release-receipt-utilization-monitoring-and-reporting-of-program-support-funds-for-alternative-learning-system-for-calendar-yea/), Implementing Guidelines on the Release, Receipt, Utilization, Monitoring and Reporting of Program Support Funds for ALS for Calendar Year 2022 and Years Thereafter, June 20, 2022: item 38.
- [DepEd Order No. 48, s. 2016](https://www.deped.gov.ph/2016/06/28/do-48-s-2016-policy-and-guidelines-on-comprehensive-tobacco-control/), Policy and Guidelines on Comprehensive Tobacco Control, June 28, 2016: Sec. V.G.
- [DepEd Order No. 042, s. 2021](https://www.deped.gov.ph/2021/10/04/october-4-2021-do-042-s-2021-guidelines-on-the-utilization-of-program-support-funds-for-special-education-program/), Guidelines on the Utilization of Program Support Funds for Special Education Program, October 4, 2021: items 4, 5.3 to 5.5.
- [DepEd Order No. 013, s. 2026](https://www.deped.gov.ph/2026/06/04/june-4-2026-do-013-s-2026-institutional-guidelines-on-the-implementation-of-the-school-based-feeding-program/), Institutional Guidelines on the Implementation of the School-Based Feeding Program, June 4, 2026: Annex E.
- [DepEd Memorandum No. 048, s. 2026](https://www.deped.gov.ph/2026/08/03/august-3-2026-dm-048-s-2026-allocation-and-release-of-the-school-innovation-and-improvement-fund-to-non-implementing-unit-public-schools-to-strengthen-decentralization-practices-in-the-de/), Allocation and Release of the School Innovation and Improvement Fund to Non-Implementing Unit Public Schools, August 3, 2026: Encl., Sec. III.1.
- [DepEd Order No. 024, s. 2026](https://www.deped.gov.ph/2026/11/26/november-26-2026-do-024-s-2026-guidelines-on-the-implementation-of-the-school-based-mental-health-program/), Guidelines on the Implementation of the School-Based Mental Health Program, November 26, 2026: Sec. V.f.
- [DepEd Order No. 009, s. 2026](https://www.deped.gov.ph/2026/04/16/april-16-2026-do-009-s-2026-guidelines-on-the-implementation-of-the-three-term-school-calendar-in-basic-education/), Guidelines on the Implementation of the Three-Term School Calendar in Basic Education, April 16, 2026: item 4 and Annex B.
- [DepEd Order No. 15, s. 2014](https://www.deped.gov.ph/wp-content/uploads/2014/03/DO_s2014_015.pdf), FY 2014 Guidelines on the Utilization of Financial Assistance to Schools Implementing Special Curricular Programs, March 14, 2014: item 3.1.2 (PDF).
- [DepEd Order No. 38, s. 2015](https://www.deped.gov.ph/2015/08/19/do-38-s-2015-guidelines-on-the-utilization-of-support-funds-for-the-special-education-sped-program/), Guidelines on the Utilization of Support Funds for the Special Education (SPED) Program, August 19, 2015: items 5.1.4 to 5.1.7.
- [DepEd Order No. 45, s. 2015](https://www.deped.gov.ph/2015/09/29/do-45-s-2015-guidelines-on-school-based-management-sbm-grants-for-fiscal-year-fy-2014/), Guidelines on School-Based Management Grants for FY 2014, September 29, 2015: items 1.2, 3.16, 7.1.2.
- [DepEd Order No. 9, s. 2018](https://www.deped.gov.ph/wp-content/uploads/DO_s2018_009.pdf), Implementing Guidelines on the Release and Utilization of MOOE Allocations of Senior High Schools, February 23, 2018: item 26 (PDF).
- DepEd, [Quality Basic Education Development Plan 2025-2035](https://www.deped.gov.ph/wp-content/uploads/Quality-Basic-Education-Development-Plan-QBEDP-2025-to-2035-29-July-2025.pdf), July 29, 2025: Annex 2, pp. 28-29.

**Laws and other agencies' issuances**

- 1987 Constitution of the Philippines, Art. VI, Sec. 15 and Art. VII, Sec. 22 ([Official Gazette](https://www.officialgazette.gov.ph/constitutions/1987-constitution/)).
- [Executive Order No. 359, s. 1989](https://www.gppb.gov.ph/wp-content/uploads/2023/06/Executive-Order-No.-359.pdf), June 2, 1989: Sec. 4(b).
- [DBM Circular Letter No. 2013-14](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2013/Circular%20Letter/CL2013-14.pdf), Reiterating the Submission of APP-CSE, November 29, 2013: item 4.4.1.
- [DBM Circular Letter No. 2022-14](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2022/Circular-Letter/CIRCULAR-LETTER-NO-2022-14-DATED-OCTOBER-28-2022.pdf), Prescribing Guidelines for the Preparation and Submission of the Annual Budget Execution Plans Covering the FY 2023 Budget and Thereafter, October 28, 2022: items 4.1 and 4.5.
- [DBM National Budget Circular No. 599](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Circular/NATIONAL-BUDGET-CIRCULAR-NO-599.pdf), Guidelines on the Release of Funds for FY 2026, January 5, 2026: items 3.3 and 3.9.
- [DBM National Budget Memorandum No. 156](https://www.dbm.gov.ph/wp-content/uploads/Issuances/2026/National-Budget-Memorandum/NATIONAL-BUDGET-MEMORANDUM-NO-156.pdf), National Budget Call for FY 2027, January 5, 2026.
- DBM Corporate Budget Circular No. 27, Guidelines on the Use of Prior Years' Subsidy, April 28, 2025: item 4.4.
- DBM, [Budget of Expenditures and Sources of Financing FY 2027, Glossary of Terms](https://www.dbm.gov.ph/wp-content/uploads/BESF/BESF2027/GLOSSARY.pdf).
- DBM, [National Expenditure Program FY 2027](https://www.dbm.gov.ph/index.php/2027/national-expenditure-program-fy-2027), page dated August 11, 2026.
- [Implementing Rules and Regulations of Republic Act No. 12009](https://www.gppb.gov.ph/ngpa-implementing-rules-and-regulations/), the New Government Procurement Act: Secs. 7.7.1, 7.7.3, 7.7.5, 7.8, 7.9.
- [GPPB Resolution No. 20-2018](https://www.gppb.gov.ph/wp-content/uploads/2023/05/GPPB-Resolution-No.-20-2018.pdf): Annex A, item 5.2.
- DepEd-DBM-DILG-DOF [Joint Circular No. 01, s. 2025](https://www.deped.gov.ph/2026/03/03/deped-dbm-dilg-joint-memorandum-circular-no-01-s-2025-omnibus-guidelines-on-the-use-of-the-special-education-fund-sef/), Omnibus Guidelines on the Use of the Special Education Fund, December 3, 2025: §6.8.
- PS-DBM Advisory No. 2026-22, September 1, 2026.

**Audit reports**

- Commission on Audit, [Department of Education Consolidated Annual Audit Report 2023](https://www.coa.gov.ph/wpfd_file/department-of-education-consolidated-annual-audit-report-2023/): Part II, Obs. 3 (pp. 154-155, 160) and pars. 12.14-12.15 (Table No. 99, pp. 319-321).
- Commission on Audit, [Department of Education Consolidated Annual Audit Report 2025](https://www.coa.gov.ph/wpfd_file/department-of-education-consolidated-annual-audit-report-2025/): Part II, Obs. 20 (Table No. 84, pp. 220-221).

**Schools Division Office memoranda (examples of division practice)**

- SDO Bulacan, Division Memorandum No. 468, s. 2026, October 14, 2026, and its FY 2027 templates.
- SDO Dasmariñas City, Division Memoranda No. 646, s. 2026 (August 25, 2026) and No. 859, s. 2026 (November 4, 2026).
- SDO Kabankalan City, Division Memoranda No. 321, s. 2026 (September 1, 2026) and No. 348, s. 2026 (September 30, 2026).
- SDO Ligao City, Division Memorandum No. 0509, s. 2026, October 22, 2026.
- SDO Nueva Vizcaya, Division Memorandum No. 460, s. 2026, November 12, 2026.
- SDO Tangub City, Division Memorandum No. 363, s. 2026, September 24, 2026.
- SDO Imus City, Division Memorandum No. 768, s. 2025, December 11, 2025, Encl. 3.
- SDO Misamis Oriental, Division Memorandum No. 569, s. 2025, August 18, 2025; Region X Regional Memorandum No. 932, s. 2024, with SDO Misamis Oriental Division Memorandum No. 791, s. 2024.
- SDO Abra, Division Memorandum No. 575, s. 2026; SDO Cebu Province, Division Memorandum No. 614, s. 2026; SDO Tayabas City, Division Memorandum No. 570, s. 2025; SDO Sorsogon, Division Memorandum No. 860, s. 2026, November 3, 2026 (DepEd Computerization Program fund).
- Pasay City South High School, FY 2021 Physical Plan, Financial Obligation and Monthly Disbursement Program, on the school's website.

## The school WFP series

- Work and Financial Plan (WFP) in DepEd: Meaning and Rules (this post)
- [How to Make a School Work and Financial Plan (WFP)](https://nash.com.ph/blog/make-school-work-financial-plan)
- [School Work and Financial Plan Sample: Excel WFP Template](https://nash.com.ph/blog/school-work-financial-plan-sample)
- [WFP Budget Breakdown: How to Cost and Fund School PPAs](https://nash.com.ph/blog/wfp-budget-breakdown)
- [WFP and PPMP, AIP and APP in DepEd Schools: What Must Match](https://nash.com.ph/blog/wfp-aip-ppmp-difference)

*Written by Mark Anthony Llego for NASH Reviewer. Sources: DepEd Orders No. 011, s. 2021, No. 017, s. 2024, No. 008, s. 2019, No. 029, s. 2019, No. 029, s. 2022 and No. 028, s. 2022; the FMOM; DBM Circular Letters No. 2013-14 and No. 2022-14 and National Budget Circular No. 599; COA's audit reports on DepEd for 2023 and 2025.*

---

© 2026 Mark Anthony Llego, NASH Reviewer. You may quote up to 100 words from this article with the author's name, its title and a link. In research and teaching, such as a thesis, action research, a journal article, or a class or LAC session, you may also quote it at the length your point needs, reproduce up to three of its charts or figures unchanged, and analyze its data and publish your results. Cite it as: Llego, M. A. (2026, November 26). *Work and Financial Plan (WFP) in DepEd: Meaning and rules*. NASH Reviewer. https://nash.com.ph/blog/work-financial-plan-deped. Put the reference under each chart you reproduce. Any other reuse, such as reposting the article, its charts or its data files, needs written permission: ask through our [contact form](https://nash.com.ph/contact). Our [Copyright](https://nash.com.ph/copyright) page explains these rules with examples, and the [Terms of Service](https://nash.com.ph/terms#website-content-and-data) set them out.