Most of what a public school buys goes through one of two modes of Republic Act No. 12009, the New Government Procurement Act. Direct Acquisition covers purchases of up to ₱200,000 bought “without need to conduct a canvass or request for quotations”; Small Value Procurement (SVP) covers purchases of up to ₱2,000,000, for which the Bids and Awards Committee (BAC) asks at least three suppliers for quotations, and one quotation is enough to proceed (Implementing Rules and Regulations, Secs. 32.1, 34.1 and 34.3(c)). The IRR took effect on February 25, 2025 (Government Procurement Policy Board [GPPB] Resolution No. 12-2025).
Which mode applies turns on three questions, asked in order: can the Procurement Service of the Department of Budget and Management (PS-DBM) supply the item, what is the whole requirement in the school’s Annual Procurement Plan (APP), and is the purchase goods, infrastructure or a consulting service? The rules below are stated as of November 17, 2026. Planning, delivery, payment and emergency purchases are in the step-by-step guide to school procurement under RA 12009.
Key findings
- Direct Acquisition: up to ₱200,000, no canvass. The purchase must be in the APP, the source “known and reputable”, and the invoice compliant with the rules of the Bureau of Internal Revenue (BIR); no posting on the Philippine Government Electronic Procurement System (PhilGEPS) is required (IRR, Secs. 32.1 to 32.3 and 50.3.2). The GPPB’s Technical Support Office adds, in a non-policy opinion, that market scoping happens at planning and that petty cash payments stay within ₱15,000 a transaction under the Commission on Audit’s (COA) rules (Non-Policy Matter [NPM] No. 004-2026, items 6 and 23).
- Small Value Procurement: up to ₱2,000,000, one quotation is enough. The end-user sends the request to the BAC, the BAC sends requests for quotation to at least three suppliers “of known qualifications”, and above ₱200,000 the request is posted for three calendar days (IRR, Sec. 34.3).
- Common-use supplies come from PS-DBM first. A school buys them elsewhere only when PS-DBM has no stock, its specifications fall short, its stock is short, or the BAC resolves that another source is more efficient, practical or economical, and it keeps the proof each case names, such as a Certificate of Non-Availability of Stocks (IRR, Sec. 40).
- The school head approves; the BAC recommends. The school head approves awards “on behalf of the Secretary, as Head of the Procuring Entity (HoPE)” (DepEd Order No. 017, s. 2024), and “In no case shall the HoPE or the approving authority be a member of the BAC” (IRR, Sec. 41.2.5).
- Splitting is prohibited. A requirement may not be divided “into smaller quantities and amounts” to evade the rules (IRR, Sec. 39.1). The safe measure is the whole requirement in the APP, not one order, unless the purchases are “genuinely separate and distinct in nature, specification, timing, or operational need” (NPM No. 004-2026, item 13).
- The supplier’s documents are a closed list. For SVP: PhilGEPS registration and a mayor’s permit always, an Omnibus Sworn Statement above ₱50,000, and a tax return above ₱500,000; the BAC says in the request for quotation when they are due (GPPB Resolution No. 10-2026, Annex A, items 3.5, 4.2 and 4.7).
The peso lines: which mode fits a school purchase
Four amounts change what a school must do. ₱200,000 is the ceiling of Direct Acquisition (IRR, Sec. 32.1) and the point above which an SVP request for quotation is posted (Sec. 34.3(b)). ₱2,000,000 is the SVP ceiling for national agencies such as DepEd (Sec. 34.1); local governments have their own ceilings by income class (Sec. 34.2), which do not apply to schools. Two more lines, ₱50,000 and ₱500,000, add to the documents an SVP supplier submits (Resolution No. 10-2026, Annex A, item 4.7).
| Amount of the whole requirement | Goods, including repairs of equipment and furniture and other general support services | Infrastructure (including building repairs) or consulting |
|---|---|---|
| Up to ₱200,000 | Direct Acquisition, or Small Value Procurement | Small Value Procurement, without posting |
| Above ₱200,000 up to ₱2,000,000 | Small Value Procurement, with the request posted for three calendar days | The same |
| Above ₱2,000,000 | A mode whose conditions the purchase meets, such as Competitive Bidding | The same |
“Goods” in the IRR include “general support services”, such as “the repair and maintenance of equipment and furniture, as well as trucking, hauling, janitorial, security, and related or analogous services” (Sec. 5(n)), so the repair of a school’s equipment or furniture follows the goods column. The repair of a school building is an Infrastructure Project, which “include the construction, improvement, rehabilitation, demolition, repair, restoration, or maintenance of” works including “school buildings” (Sec. 5(r)); it follows the infrastructure column and never takes Direct Acquisition. Direct Acquisition names goods bought from stores and services from providers such as “furniture repair, automotive service, restoration service, machine and fabrication” (Sec. 32.1); the GPPB’s Procurement Mode Selection Decision Tree, an annex of the IRR since Resolution No. 12-2025 of November 25, 2025, offers it on its goods sheet. The IRR names no default mode above ₱2,000,000: the procuring entity adopts a mode “consistent with the Fit-for-Purpose procurement approach” (Sec. 26.1), and the GPPB’s tree “serves only as a guide” (Resolution No. 12-2025, item 5).
Try a purchase on the ruler: what the school buys, this order, and the whole requirement in the APP.
RA 12009 and its IRR
The peso lines of a school purchase
Describe a purchase. The ruler marks this order and the whole requirement in the APP, and the card names the mode that fits.
The mode that fits
Direct Acquisition
Measured by the whole requirement: ₱150,000. Small Value Procurement is also open.
- The purchase must be in the approved APP. “No government procurement shall be undertaken unless it is in accordance with the approved Indicative APP or final APP of the Procuring Entity” (IRR, Sec. 7.8; for Direct Acquisition, Sec. 32.2)
- No canvass and no request for quotations: the school buys directly from a known and reputable source. “without need to conduct a canvass or request for quotations, may procure directly from any known and reputable sources” (IRR, Sec. 32.1)
- The HoPE may let the end-user buy directly from a PhilGEPS-registered supplier, an e-commerce platform, or off the shelf. (IRR, Sec. 32.3)
- Only from a source that gives a proper invoice. “Procuring Entities shall procure only from sources that issue invoices compliant with the rules of the BIR or other documents evidencing delivery and payment acceptable to the COA.” (IRR, Sec. 32.3)
- No posting on PhilGEPS. “Other modes not enumerated herein shall not be required to comply with the publication of requirements” (IRR, Sec. 50.3.2)
The supplier submits
GPPB Resolution No. 10-2026, Annex A, item 4.7. The list is exclusive (item 3.5).
Sources: IRR of RA 12009, Secs. 5(n), 5(r), 7.8, 26.1, 27.1, 32, 34, 39.1, 40 and 50.3.2; GPPB Resolution No. 10-2026, Annex A.
Common-use supplies: PS-DBM first
“All NGAs, GOCCs, GFIs, SUCs, and LGUs shall procure CSE only from the PS-DBM, subject to its availability” (IRR, Sec. 40.1). Common-use supplies and equipment (CSE) are the items in the PhilGEPS Electronic Catalogue. A school may buy them elsewhere in four cases, each with its own proof (Sec. 40.2):
| Case | What the school keeps |
|---|---|
| PS-DBM has zero stock | “a Certificate of Non-Availability of Stocks by downloading from the PhilGEPS Electronic Catalogue” |
| PS-DBM’s specifications do not meet the need | “a complete list of technical specifications of all CSE items by downloading from the PhilGEPS Electronic Catalogue” |
| PS-DBM’s stock is short of the quantity | “the current Stock Position Report from the PhilGEPS Electronic Catalogue” |
| Another source is more efficient, practical or economical | the end-user’s written recommendation, the BAC’s resolution, and the online form that informs PS-DBM |
PS-DBM calls the first proof the “Certificate of No Available Stocks” (CNAS) and gives the steps to download it (PS-DBM Advisory No. 2025-008). The fourth case names “no internet connectivity or geographical limitations” as instances of impracticality (Sec. 40.2(d)(ii)). PS-DBM also sells common-use supplies through the PhilGEPS Electronic Marketplace (eMarketplace), beside its Virtual Store. The GPPB’s guidelines for it, part of the IRR, have a school list those purchases in its APP for CSE under “Negotiated Procurement – Agency to Agency, as provided under Section 35 (e) of RA No. 12009” (item 7.1), and restate the four cases for the eMarketplace, the first with “an electronic Certificate of Non-Availability of Stocks” (item 6.1.1) (GPPB Resolution No. 10-2025, September 25, 2025; Circular No. 03-2025). Once a case of Section 40.2 applies, the item is bought like any other good: by Direct Acquisition, which covers “CSE not available in the PS-DBM” (Sec. 32.1), or by SVP, which covers “Goods not available in the PS-DBM” (Sec. 34.1).
Direct Acquisition, step by step
Direct Acquisition is “a mode of procurement of CSE not available in the PS-DBM, Non-CSE, and services with ABC not exceeding Two Hundred Thousand Pesos (₱200,000.00), where the Procuring Entity, without need to conduct a canvass or request for quotations, may procure directly from any known and reputable sources” (IRR, Sec. 32.1). In a school it runs this way:
- The plan comes first. The end-user’s market scoping feeds the Project Procurement Management Plan (PPMP) (Sec. 10.1), and “Procurement of goods and services through Direct Acquisition shall be reflected in the APP” (Sec. 32.2). Petty cash purchases that “cannot be itemized” appear in the APP as Miscellaneous Items (Sec. 32.2).
- The purchase request. A designated non-teaching staff member prepares it, the budget or finance staff certifies the allotment, and the school head approves it (DO 017, s. 2024).
- The HoPE’s authority to buy. “The HoPE may authorize the End-User or Implementing Unit to directly purchase” from a PhilGEPS-registered supplier, from an electronic commerce platform that delivers or allows pickup on the school’s date, or off the shelf (Sec. 32.3). The authority runs from the HoPE to the end-user: neither the law, the IRR, the GPPB’s guidelines nor a DepEd order requires the end-user to write to the HoPE asking for a Direct Acquisition. The request is the approved purchase request, and the GPPB’s Technical Support Office (GPPB-TSO) lists the planning documents a Direct Acquisition needs as the “Market Scoping Form”, the “PPMP prepared by the end-user or implementing unit”, the “APP duly approved by the HoPE, indicating Direct Acquisition as the procurement method”, and the “Purchase Request” (NPM No. 004-2026, item 14).
- A proper invoice. “Procuring Entities shall procure only from sources that issue invoices compliant with the rules of the BIR or other documents evidencing delivery and payment acceptable to the COA” (Sec. 32.3).
- No posting. Section 50.3.2 lists the modes whose requests are posted on PhilGEPS, and “Other modes not enumerated herein shall not be required to comply with the publication of requirements.”
- Inspection and acceptance, then payment, as for any purchase.
The GPPB-TSO puts the limit plainly: “the PE must still ensure that the price is reasonable, even if canvass or multiple quotations are not required under Direct Acquisition”, through market scoping that gathers “prevailing prices, historical procurement data, published price lists, or other readily available commercial references” (NPM No. 004-2026, item 22).
What the GPPB’s technical office says about Direct Acquisition
On April 20, 2026 the GPPB-TSO answered 23 questions on Direct Acquisition in a Non-Policy Matter (NPM) opinion, NPM No. 004-2026. The opinion “shall not be construed as a rule, regulation, or policy issuance of the GPPB, nor amending or modifying the provisions of RA No. 12009 and its IRR”, but it is the GPPB’s own office reading Section 32, and several answers address questions schools ask:
| Question | The GPPB-TSO’s answer (item) |
|---|---|
| Is market scoping required? | Yes, at planning: “Market scoping thus applies to planning and price reasonableness validation, not to the execution of Direct Acquisition, where multiple quotations are not required” (6) |
| Can the APP be updated after an emergency purchase? | No: it is updated “before — not after” (10) |
| Is a BAC resolution needed for each purchase? | No: “no separate BAC Resolution is required for each individual Direct Acquisition transaction”; the BAC resolution recommending the APP covers it (11) |
| Is an Omnibus Sworn Statement required? | No (17) |
| Must the supplier be registered with PhilGEPS? | No: “PhilGEPS registration is not mandatory for Direct Acquisition”; it is one of the three bases in Section 32.3 (18) |
| Is a purchase order required? | “A Purchase Order (PO) is not an indispensable requirement in Direct Acquisition” (19) |
| Can every Direct Acquisition be paid from petty cash? | No: petty cash “is subject to a separate per-transaction limit of ₱15,000.00 under applicable COA rules” (23), the limit COA Circular No. 2012-001 sets for petty cash payments |
Direct Acquisition sets how a school buys, up to ₱200,000; petty cash sets how it pays, up to ₱15,000 a transaction. A ₱40,000 purchase may be a Direct Acquisition, but it is paid by check or another authorized means, not from the petty cash fund.
Small Value Procurement, step by step
“Small Value Procurement (SVP) is a mode of procurement whereby the Procuring Entity requests for the submission of at least three (3) price quotations for Goods not available in the PS-DBM, Infrastructure Projects, and Consulting Services. The receipt of one (1) quotation is sufficient to proceed with the evaluation of bidders” (IRR, Sec. 34.1). The procedure is Section 34.3’s:
| Step | What happens | Who acts in a school |
|---|---|---|
| Request | The end-user submits “a request for SVP to the BAC” with the technical specifications or scope of work, the approved budget for the contract (ABC) and the terms (Sec. 34.3(a)) | The end-user, after the school head approves the purchase request |
| Posting | Above ₱200,000, the request for quotation is posted for three calendar days on PhilGEPS, on the school’s website if it has one, and “at any conspicuous place reserved for this purpose” (Sec. 34.3(b)); the BAC posts “through its Secretariat” (Sec. 50.3.2) | BAC secretariat |
| Requests for quotation | “The BAC shall prepare and send the RFQs or RFPs to at least three (3) suppliers, contractors or consultants of known qualifications”; anyone who answered the posting may also quote (Sec. 34.3(c)) | BAC; requests for quotation are signed through its chairperson (DO 017, s. 2024) |
| No quotation | The deadline may be extended “until receipt of at least a single price quotation”, but not beyond the validity of the appropriation (Sec. 34.3(d)) | BAC |
| Pre-bid conference | Optional, “at the discretion of the BAC” (Sec. 34.3(e)) | BAC |
| Abstract | After the deadline, an Abstract of Quotations names everyone who responded and their prices (Sec. 34.3(f)) | BAC |
| Recommendation and award | The BAC recommends the award to the supplier with the lowest calculated responsive bid (LCRB), or the most economically advantageous, most advantageous or highest rated responsive bid (MEARB, MARB or HRRB); “In case of approval, the HoPE shall immediately enter into contract” (Sec. 34.3(g)) | BAC resolution; the school head approves the award (DO 017, s. 2024) and signs the purchase order, keeping any written authority the SDO issues for it (open point) |
Except for the bidding modes, “the BAC may delegate the conduct of procurement activities for the other modes of procurement to the End-User or Implementing Unit, or the Procurement Unit” (Sec. 26.4). Without that delegation, the end-user asks and the BAC sends the requests; with it, the end-user may run the steps, and the award still goes through the BAC’s recommendation and the school head’s approval.
When the supplier’s documents are checked
GPPB Resolution No. 10-2026 (February 3, 2026; Circular No. 06-2026, published June 19, 2026) fixes the documents for SVP: the PhilGEPS Organization ID or PhilGEPS Certificate of Registration (Platinum Membership) and a mayor’s or business permit in every case, a professional license or curriculum vitae for consulting, a Philippine Contractors Accreditation Board (PCAB) license for infrastructure, an income or business tax return “for ABCs above P500k”, and an Omnibus Sworn Statement “for ABCs above P50k” (Annex A, item 4.7). “The eligibility documents enumerated in these Guidelines are exclusive and the PEs shall not require additional eligibility documents” (item 3.5), and documents already on file need not be submitted again (item 4.4).
The resolution does not fix when they are checked. “The Bids and Awards Committee (BAC) shall indicate in the Request for Quotation (RFQ) or Request for Proposal (RFP) the stage of the procurement process when the documentary requirements shall be submitted, i.e., submission of offer/s, evaluation of offer/s, or before issuance of Notice of Award” (item 4.2). A BAC that asks for the documents with the quotation can check them before it reads the prices; one that asks for them before the award checks only the winning supplier’s. Either is allowed, as long as the request for quotation says which. An expired mayor’s permit with the official receipt of its renewal is accepted, “subject to submission of the valid permit after award of contract but before payment” (item 4.3.2(a)).
Opening the quotations, and posting the award
Section 34.3 has no opening ceremony. After the deadline, “an Abstract of Quotations or Ratings shall be prepared setting forth the names of those who responded to the RFQ or RFP, and their corresponding price quotations or ratings” (Sec. 34.3(f)); the rules on public bid opening belong to competitive bidding. The Abstract is the record of what came in. When the BAC meets to take up the quotations, its secretariat keeps the minutes, since the secretariat must “Prepare minutes of meetings and resolutions of the BAC” (Sec. 44.3(c)). A memorandum on the opening of quotations is good practice, not a requirement.
Posting the award is less settled. Section 34 names no posting of an SVP Notice of Award, and the general duty of the BAC secretariat to “Publish or post bidding opportunities, including Bidding Documents, and Notices of Awards” (Sec. 44.3(f)) names no mode, place or period. Two older texts still reach it:
- COA’s checklist asks, for every purchase made without public bidding, for “Proof of posting of Notice of Award in the PhilGEPs [sic] website, the website of the procuring entity concerned, if available, and at any conspicuous place reserved for this purpose in the premises of the procuring entity” (COA Circular No. 2012-001, item 9.2).
- Until the GPPB issues guidelines under RA 12009, procuring entities “shall continue to use the guidelines and forms issued under RA No. 9184” (GPPB Circular No. 01-2025, item 5.2.1), and those guidelines, under Republic Act No. 9184 (the Government Procurement Reform Act that RA 12009 replaced), have the BAC post “the NOA, Contract/PO” within ten days of their issuance, “except for contracts with ABC of Fifty Thousand Pesos (₱50,000.00) and below” (Revised IRR of RA 9184, Annex H, item IV.L.3). The GPPB-TSO kept an RA 9184-era posting rule alive the same way for another alternative mode, community participation, in NPM No. 031-2026 (September 18, 2026), recalling that doubts are “resolved in favor of government procurement” (IRR, Sec. 2).
No rule or opinion settles the point for SVP. The course that satisfies both texts is to post the Notice of Award and the purchase order within ten days of their issuance, in the same three places as the request for quotation, for any SVP above ₱50,000.
Since August 1, 2026, DepEd and the rest of the executive branch post on the eBidding Facility of the modernized PhilGEPS (mPhilGEPS): “Starting 01 August 2026, no new procurement opportunities shall be published on the platform” of the old PhilGEPS 1.5 (PS Advisory No. 2026-19).
Run one
The figure below runs one SVP for a fictional school, step by step.
Try it
Run a Small Value Procurement
Maliwanag Central School, a fictional school, buys ₱350,000 of science laboratory apparatus. Pick a course at each step; the rule answers, and the folder fills.
Step 1 of 7
Who sends the requests for quotation?
The school's ₱350,000 for laboratory apparatus is in the approved APP, and the school head has approved the purchase request. The science department head knows three suppliers and offers to email them the request for quotation herself.
See the answer: Who sends the requests for quotation?
- ANot this. The end-user's part is the request to the BAC. Sending the requests for quotation is the BAC's, unless the BAC has delegated the conduct of this SVP to her (Sec. 26.4).
- BRight. The end-user asks; the BAC prepares and sends the requests for quotation to at least three suppliers of known qualifications. Her three suppliers can be among them.
- CNot this. Direct Acquisition stops at ₱200,000 (Sec. 32.1). At ₱350,000 the school uses Small Value Procurement.
“The End-User or Implementing Unit shall submit a request for SVP to the BAC. The request shall indicate the Technical Specifications, Scope of Work, Terms of Reference, as the case may be, ABC and other terms and conditions.” (IRR, Sec. 34.3(a); see also Sec. 34.3(c) and Sec. 26.4)
Step 2 of 7
Some of the items are common-use supplies.
Before the requests go out, the BAC sees that the purchase request also lists two boxes of a common-use item in the PhilGEPS catalog. PS-DBM's catalog shows zero stock this month.
See the answer: Some of the items are common-use supplies.
- ANot this. The duty is to buy from PS-DBM subject to its availability; zero stock is the first case in which another source is allowed.
- BRight. With zero stock the school may buy elsewhere, keeping the certificate downloaded from the PhilGEPS Electronic Catalogue as its proof.
- CNot this. The exception needs its proof, whatever the amount.
“If the CSE is unavailable due to zero inventory, in which case the Procuring Entity shall secure a Certificate of Non-Availability of Stocks by downloading from the PhilGEPS Electronic Catalogue” (IRR, Secs. 40.1 and 40.2(a))
Step 3 of 7
Does the request for quotation have to be posted?
The BAC has sent the requests to four suppliers. One member says posting is pointless now, since the suppliers already have them.
See the answer: Does the request for quotation have to be posted?
- ANot this. Sending requests does not replace posting. Above ₱200,000, posting is required, and anyone who answers the posting may also quote.
- BNot this. The bulletin board is one of three places. The request also goes on PhilGEPS, and on the school's website if it has one.
- CRight. The ABC is above ₱200,000, so the request is posted in all three places for three calendar days.
“Except for those with ABCs equal to Two Hundred Thousand Pesos (₱200,000.00) and below which shall not require posting, RFQ or Request for Proposal (RFP) shall be posted for a period of three (3) calendar days on the PhilGEPS website, website of the Procuring Entity, if available, and at any conspicuous place reserved for this purpose in the premises of the Procuring Entity.” (IRR, Sec. 34.3(b); Sec. 50.3.2)
Step 4 of 7
Only one quotation came in. Now what?
At the deadline, one supplier has quoted ₱338,500. The other three did not answer.
See the answer: Only one quotation came in. Now what?
- ARight. One quotation is enough to proceed. The BAC evaluates it against the specifications and the ABC.
- BNot this. The deadline is extended only when no quotation at all has come in, and never beyond the validity of the appropriation (Sec. 34.3(d)).
- CNot this. Nothing has failed. The IRR asks for at least three requests, not three quotations.
“Receipt of at least one (1) quotation is sufficient to proceed with the evaluation thereof.” (IRR, Sec. 34.3(c); see Sec. 34.3(d) for no quotation)
Step 5 of 7
The supplier's permit has expired. Accept the quotation?
The supplier sent its PhilGEPS Organization ID and an Omnibus Sworn Statement. Its mayor's permit expired last month, and it attached the official receipt for the renewal.
See the answer: The supplier's permit has expired. Accept the quotation?
- ANot this. The GPPB accepts an expired permit with the receipt for its renewal, if the valid permit comes in after the award and before payment.
- BRight. That is the rule for an expired permit. At ₱350,000 the supplier owes no tax return; that is asked only above ₱500,000.
- CNot this. The list of documents is closed: the school may not ask for more (item 3.5).
“An expired Mayor's permit with official receipt of renewal application shall be accepted, subject to submission of the valid permit after award of contract but before payment.” (GPPB Resolution No. 10-2026, Annex A, item 4.3.2(a); items 3.5 and 4.7)
Step 6 of 7
Who recommends, and who awards?
The quotation is within the ABC and meets the specifications. To save a meeting, a teacher suggests that the school head chair the BAC session and sign everything at once.
See the answer: Who recommends, and who awards?
- ANot this. The school head approves the award on behalf of the Secretary, so the school head cannot sit on the BAC at all, as chair or as member.
- BRight. The BAC recommends the lowest calculated responsive quotation; the school head, as the approving authority, approves it and the purchase order follows.
- CNot this. The award goes to the quotation the BAC finds lowest and responsive, by its resolution, not to a supplier an end-user prefers.
“In no case shall the HoPE or the approving authority be a member of the BAC.” (IRR, Secs. 41.2.5 and 34.3(f) and (g); DO 017, s. 2024 (the school head approves the award on behalf of the Secretary))
Step 7 of 7
One last purchase: split it into three?
Later, the APP lists ₱480,000 of sports equipment for the year, to be delivered to the school at one time, with the whole amount allotted. So the school need not post and gather quotations, the property custodian proposes three Direct Acquisitions of ₱160,000 each.
See the answer: One last purchase: split it into three?
- ANot this. Dividing one requirement to get each piece under a ceiling, in order to avoid posting and quotations, is splitting.
- BNot this. Spacing the pieces apart does not change their purpose. Lots are allowed for reasons such as the budget available, quantity, product availability, delivery sites or market capacity, not to evade a rule.
- CRight. The requirement is ₱480,000, so the school uses SVP. It may divide the SVP into lots for legitimate reasons, such as separate delivery sites.
“Splitting of Government Contracts is not allowed. In using any of the modes of procurement under Article IV of the Act, the Procuring Entity shall ensure that this does not result in splitting of government contracts” (IRR, Sec. 39.1)
Sources: IRR of RA 12009, Secs. 26.4, 32.1, 34.3, 39.1, 40.1 and 40.2, 41.2.5 and 50.3.2; GPPB Resolution No. 10-2026, Annex A; DepEd Order No. 017, s. 2024.
Who may do what: the school head, the BAC and the end-user
Where procurement is decentralized, “the head of each decentralized unit, which is individually considered as a Procuring Entity, shall be considered as the HoPE, subject to the limitations and authority delegated by the head of the department” (IRR, Sec. 41.1.1). DepEd’s delegation is DO 017, s. 2024: the school head, or the school’s officer-in-charge designated by the Schools Division Superintendent (SDS), approves the purchase request and has “full authority to approve and issue the Resolution to Award (RTA) and the Notice to Award (NOA) on behalf of the Secretary, as Head of the Procuring Entity (HoPE)”, “Up to the extent of allotment received”. The step-by-step guide sets out every signatory, including one open point on purchase orders.
Because the school head approves, the school head stays off the BAC: “In no case shall the HoPE or the approving authority be a member of the BAC” (Sec. 41.2.5). That bars chairing it and also sitting on it as a member. DepEd’s own order on additional BACs says the same in so many words: “In no case shall the HOPE and/or the approving authority be the Chairperson or a member of the BAC” (DepEd Order No. 26, s. 2018, item 5). The BAC has five or seven members designated by the HoPE (Sec. 41.2.1), among them a representative of the end-user as a provisional member (Sec. 41.2.2), and the HoPE “may create BACs where the number and complexity of the items to be procured shall so warrant” (Sec. 41.1.2). DepEd’s Financial Management Operations Manual describes a school bids and awards committee, and clustered or district BACs for small schools (2016, p. 130), and DO 26, s. 2018 lets additional BACs be organized by the “geographical location of PMO or end-user units” (item 1). Which BAC acts for a school is the HoPE’s designation, so ask the SDS for it in writing.
Splitting: how to tell
“Splitting of Government Contracts is not allowed”, and it “involves dividing or breaking up of contracts into smaller quantities and amounts, or dividing contract implementation into artificial phases or subcontracts for the purpose of evading or circumventing the requirements of the Act and this IRR” (IRR, Sec. 39.1). The same section allows “procurement per unit, by lot or package … subject to the available budget, required quantity, product availability, delivery sites, geographical location and market capacity.”
The GPPB-TSO’s opinion on Direct Acquisition puts the test this way: “Contract splitting is assessed based on intent, circumstances, and procurement planning under the APP, and not merely on the amount or mode of procurement.” Splitting is present when “a single requirement under the APP is deliberately divided into smaller procurements or transactions to evade or circumvent thresholds or procurement requirements” or when “similar or related items that should have been reasonably aggregated at the planning stage are instead procured separately without valid justification” (NPM No. 004-2026, item 13). RA 12009 lists “Splitting of contracts which exceed procedural purchase limits and competitive bidding” among the acts that make an official administratively liable (Sec. 92(d)).
In a school, three checks follow from those words:
- The requirement. Compare each purchase with the APP line it serves. Three ₱160,000 orders against a ₱480,000 line of sports equipment are one ₱480,000 requirement, which calls for SVP. A line that gathers genuinely separate purchases, such as the Miscellaneous Items for petty-cash purchases that “cannot be itemized” (Sec. 32.2), is not one requirement (NPM No. 004-2026, item 13).
- The reason. A school that receives its allotment in tranches, or needs deliveries at two campuses, has a reason the IRR names; purchases “genuinely separate and distinct in nature, specification, timing, or operational need” are not splitting (NPM No. 004-2026, item 13). A school that divides an order so that it need not post or ask for quotations has the purpose the IRR forbids.
- The mode. One SVP may cover several lots, which leaves no question, and an SVP for each tranche of the allotment is still an SVP. Buying each piece under a lower ceiling is what the GPPB-TSO tests: splitting when one requirement is divided to evade a threshold, not when the purchases are genuinely separate (NPM No. 004-2026, item 13).
The papers to keep
The papers below are what the IRR, the GPPB and DepEd name for each mode, plus two records that no rule names in these words but that answer the first questions an auditor or a losing supplier asks.
| Paper | Direct Acquisition | Small Value Procurement | Where the rule is |
|---|---|---|---|
| The APP entry, and the Market Scoping Form, “a mandatory supporting document” of the PPMP | Yes | Yes | IRR, Secs. 7.8, 10.5 and 32.2; GPPB Resolution No. 03-2025, PPMP form |
| The approved purchase request | Yes | Yes | DO 017, s. 2024 |
| For a common-use item bought outside PS-DBM: the Certificate of Non-Availability of Stocks, the list of specifications, the Stock Position Report, or the BAC resolution | Yes | Yes | IRR, Sec. 40.2 |
| The HoPE’s authority for the end-user to buy directly | When the end-user buys | IRR, Sec. 32.3 | |
| The end-user’s request for SVP to the BAC | Yes | IRR, Sec. 34.3(a) | |
| Proof of posting on PhilGEPS, the school’s website if any, and the school’s conspicuous place | Above ₱200,000 | IRR, Secs. 34.3(b) and 50.3.2 | |
| The requests for quotation, with proof that each supplier received one | Yes; the proof of receipt is a record worth keeping | IRR, Sec. 34.3(c) | |
| Each quotation, marked with when it arrived | Yes; the time of receipt is a record worth keeping | IRR, Sec. 34.3(c) | |
| The supplier’s documents | Yes | GPPB Resolution No. 10-2026, Annex A, item 4.7 | |
| Abstract of Quotations | Yes | IRR, Sec. 34.3(f) | |
| BAC resolution recommending the award | Yes | IRR, Sec. 34.3(g) | |
| Resolution to Award and Notice of Award approved by the school head, and the purchase order | Purchase order not indispensable (NPM No. 004-2026, item 19) | Yes | DO 017, s. 2024 |
| Proof of posting the Notice of Award and the purchase order | Above ₱50,000, as the course that satisfies both texts | COA Circular No. 2012-001, item 9.2; Revised IRR of RA 9184, Annex H, item IV.L.3 | |
| A BIR-compliant invoice or other proof of delivery and payment acceptable to COA | Yes | Yes | IRR, Sec. 32.3 |
| The Inspection and Acceptance Report | Yes | Yes | DO 001, s. 2023, Annex C, Part II.G |
For an SVP, COA asks for much of the same with the payment: the approved procurement plan, the approved purchase request, the purchase order “duly approved by the official concerned and accepted by the supplier”, proof of posting where it is required, the BAC resolution and the HoPE’s approval, the quotations and their abstract, the delivery invoice and the Inspection and Acceptance Report (COA Circular No. 2012-001, items 9.2 and 9.2.5). The circular was written under RA 9184; for a current purchase, read its posting period as the IRR’s three days. For Direct Acquisition, the GPPB-TSO’s reading is that COA rules govern “payment, liquidation, and audit verification, provided that they do not impose additional procurement steps” such as a canvass (NPM No. 004-2026, item 22).
What this means for school heads
Strand 2.2 of the Philippine Professional Standards for School Heads (PPSSH) of DepEd Order No. 024, s. 2020, Financial management, expects a school head to “Manage finances adhering to policies, guidelines and issuances in allocation, procurement, disbursement and liquidation aligned with the school plan” (indicator 2.2.2; see Domain 2). For small purchases that comes down to six habits:
- Measure the APP line, not the order. Before approving a purchase request, look up the APP line it draws on. If the line is one requirement above ₱200,000, buy it by SVP, in lots if needed, whatever the size of this order. The IRR does not say this in those words; it follows from Section 39.1, and the GPPB-TSO judges splitting by “intent, circumstances, and procurement planning under the APP” (NPM No. 004-2026, item 13).
- Check PS-DBM first, and keep the proof the same day. Stock in the PhilGEPS Electronic Catalogue changes; download the Certificate of Non-Availability of Stocks, the specifications or the Stock Position Report when you decide.
- Keep the roles apart. The end-user asks, the BAC canvasses and recommends, the school head approves. Stay off the BAC, and if the BAC delegates an SVP to the end-user under Section 26.4, put the delegation in writing in the folder.
- Check the BAC’s request for quotation before it goes out. It should say when the supplier’s documents are due (Resolution No. 10-2026, item 4.2), ask only for the documents on the GPPB’s list, and go to at least three suppliers.
- Do not wait for three quotations. One quotation received is enough to proceed with the evaluation; the deadline is extended only when none has arrived (IRR, Secs. 34.3(c) and (d)).
- Close the folder before payment. The papers in the table above, complete, are what COA and the BAC will ask for.
Frequently asked questions
Is one quotation enough in Small Value Procurement?
Yes. The BAC must request at least three quotations, but “Receipt of at least one (1) quotation is sufficient to proceed with the evaluation thereof” (IRR, Sec. 34.3(c)). If none arrives, the deadline may be extended until one does, within the validity of the appropriation (Sec. 34.3(d)).
What is the Small Value Procurement threshold for DepEd schools?
₱2,000,000, the ceiling for national agencies, “subject to the periodic review of the threshold amount and adjustments as may be deemed appropriate by the GPPB” (IRR, Sec. 34.1). The request for quotation is posted for three calendar days when the ABC is above ₱200,000 (Sec. 34.3(b)).
Can the school head chair the school’s BAC?
No. The school head approves awards on behalf of the Secretary as HoPE (DO 017, s. 2024), and “In no case shall the HoPE or the approving authority be a member of the BAC” (IRR, Sec. 41.2.5).
Does Direct Acquisition need a canvass or PhilGEPS posting?
Neither is required. The school buys “without need to conduct a canvass or request for quotations” (IRR, Sec. 32.1), and Direct Acquisition is not among the modes Section 50.3.2 requires to be posted. It must still be in the APP and bought from a source that issues a BIR-compliant invoice (Secs. 32.2 and 32.3).
Can a school buy common-use supplies outside PS-DBM?
Only in the four cases of IRR Section 40.2, each with its proof: zero stock (a Certificate of Non-Availability of Stocks), specifications that do not meet the need, stock short of the quantity, or a BAC resolution that another source is more efficient, practical or economical.
Sources
Law and implementing rules
- Republic Act No. 12009, New Government Procurement Act, approved July 20, 2024.
- Implementing Rules and Regulations of RA 12009, approved through GPPB Resolution No. 02-2025, February 4, 2025, in effect since February 25, 2025: Secs. 2, 5(n), 5(r), 7.8, 10.1, 10.5, 26.1, 26.4, 27.1, 32, 34, 39, 40, 41.1, 41.2, 44.3(c), 44.3(f) and 50.3.2.
- RA 12009, Sec. 92(d).
Government Procurement Policy Board
- GPPB Resolution No. 10-2026, Approving the Documentary Requirements and Relevant Guidelines for Specific Modes of Procurement under Republic Act No. 12009 and Its Implementing Rules and Regulations, February 3, 2026 (Circular No. 06-2026, published June 19, 2026): Annex A, items 3.3, 3.5, 4.2, 4.3, 4.4 and 4.7.
- GPPB Resolution No. 03-2025, Approving the Standard Forms for Procurement in Accordance with Republic Act No. 12009 and Its Implementing Rules and Regulations, May 14, 2025: the Mandatory Market Scoping Form and the PPMP form.
- GPPB Circular No. 01-2025 (Resolution No. 05-2025), September 18, 2025: item 5.2.1.
- GPPB Resolution No. 10-2025, Approving the Updated Guidelines for the Implementation of the Philippine Government Electronic Procurement System Electronic Marketplace, September 25, 2025 (Circular No. 03-2025): items 6.1.1 and 7.1.
- GPPB Resolution No. 12-2025, Approving the Procurement Mode Selection Decision Tree under Section 6 of Republic Act No. 12009, November 25, 2025: item 5 and Annex A.
DepEd and COA
- DepEd Order No. 017, s. 2024, Amendment to the Provisions of DepEd Order No. 001, s. 2023 on Signing Authorities for Financial Matters in the Department of Education, December 4, 2024.
- DepEd Order No. 001, s. 2023, Revised Designation of Undersecretaries and Assistant Secretaries to Their Strands and Functional Areas of Responsibilities and Revised Signing Authorities, January 9, 2023: Annex C, Part II.G.
- DepEd Order No. 024, s. 2020, National Adoption and Implementation of the Philippine Professional Standards for School Heads, September 7, 2020: indicator 2.2.2.
- DepEd, Financial Management Operations Manual (2016), p. 130.
- DepEd Order No. 26, s. 2018, Creation of Additional Bids and Awards Committees in the Regional and Schools Division Offices, June 1, 2018: items 1 and 5.
- COA Circular No. 2012-001, Revised Guidelines and Documentary Requirements for Common Government Transactions, June 14, 2012: items 9.2 and 9.2.5, and the petty cash limit.
GPPB Technical Support Office opinions (non-policy matters; not rules of the GPPB)
- NPM No. 004-2026, Interpretation and Application of Direct Acquisition under Section 32 of the Implementing Rules and Regulations of Republic Act No. 12009, April 20, 2026: items 6, 10, 11, 13, 14, 17, 18, 19 and 23.
- NPM No. 031-2026, Request for Clarification on PhilGEPS Posting Requirement for Community Participation, September 18, 2026.
Earlier rules and the Procurement Service
- Revised IRR of RA 9184, as of July 19, 2024: Annex H, item IV.L.3.
- PS-DBM Advisory No. 2025-008, procedure for downloading the Certificate of No Available Stocks.
- PS Advisory No. 2026-19, July 2026: posting on the modernized PhilGEPS from August 1, 2026.
This guide explains RA 12009, its IRR, the GPPB’s issuances and DepEd’s orders on procurement for study and professional awareness. It is not legal advice; for a specific case, consult your Schools Division Office’s legal unit or BAC Secretariat, or write to the GPPB’s Technical Support Office.
Written by Mark Anthony Llego for NASH Reviewer. Sources: RA 12009 and its IRR; GPPB Resolutions No. 03-2025, No. 10-2025, No. 10-2026 and No. 12-2025; GPPB-TSO NPMs No. 004-2026 and No. 031-2026; DepEd Orders No. 26, s. 2018 and No. 017, s. 2024; COA Circular No. 2012-001.