In a DepEd school, the Work and Financial Plan (WFP) and the Annual Implementation Plan (AIP) plan every activity of the year, while the Project Procurement Management Plan (PPMP) and the Annual Procurement Plan (APP) plan the procurement behind them: what is bought or done by administration, how and when. The WFP and the PPMP plan the same money from two ends: the WFP sets out every program, project and activity (PPA) of the fiscal year with its targets and its amounts by month, and the PPMP lists each procurement project’s quantity, mode, schedule and estimated budget (IRR of Republic Act No. 12009, Sec. 7.7.1). For a public school, the AIP does the work of the WFP: no DepEd order in force sets a WFP form for a school’s Maintenance and Other Operating Expenses (MOOE), and DepEd Order No. 008, s. 2019 has school MOOE fund the activities “specifically determined in the Annual Implementation Plan (AIP) which shall follow the calendar year format (Annex 1)” (Sec. V.D.1).

The PPMPs are gathered into the APP, and “No government procurement shall be undertaken unless it is in accordance with the approved Indicative APP or final APP” (IRR, Sec. 7.8). Supplies the school buys from the Procurement Service of the Department of Budget and Management (PS-DBM) are also listed, month by month, in the Annual Procurement Plan for Common-Use Supplies and Equipment (APP-CSE). The cash comes last: the Schools Division Office (SDO) deposits a school’s MOOE on its monthly disbursement program (DepEd Order No. 029, s. 2019, Encl., item 18).

Each of these documents holds part of one plan, so they must agree on five things: the PPA, its amount, its months, the goods and their quantities, and the fund that pays. Many Schools Division Offices ask every school for a WFP on their own template each year, filed with the PPMP and APP; that is division practice, and a school follows its division’s memorandum. The rules below are those in force on November 26, 2026.

Key findings

  • For a school, the AIP does the work of the WFP. DepEd’s orders define the WFP for its offices, and for purchases they read “in the case of the field offices or schools, in accordance with the approved WFP/Annual Implementation Plan and the APP for the current year” (DepEd Order No. 017, s. 2024, Annex A, item B). The Financial Management Operations Manual (FMOM), adopted through DepEd Order No. 60, s. 2016, adds that “The AIP is also referred to as the school operating budget (SOB)” (p. 127).
  • The AIP’s own format is already a WFP’s shape. Annex 1 of DO 008, s. 2019 gives each PPA a target and an amount for every month, totals them by fund (MOOE, Special Education Fund, others), and adds the first quarter of the next year.
  • The WFP covers every PPA; the PPMP only the projects the end-user will procure or undertake by administration. A PPMP states “Whether the implementation of the PAPs will require procurement or undertaken by administration” (IRR, Sec. 7.7.1(a)), and the GPPB’s PPMP form asks for that in its first column. What the PPMP adds to the WFP’s lines is each project’s mode and schedule.
  • The APP is the procuring entity’s whole plan, built from the PPMPs. It is Indicative while the budget is pending and Final after the General Appropriations Act (GAA), posted and sent to the Government Procurement Policy Board (GPPB) “on or before the end of January of the budget year” (IRR, Sec. 7.7.5), and updated whenever PPMPs change (Sec. 7.9).
  • The APP-CSE does not replace the APP. The GPPB’s APP form keeps a row for “Common Use Supplies and Equipment (CSE) to be purchased from PS-DBM”, and the Commission on Audit (COA) faulted schools where “Only the APP-CSE instead of the GPPB prescribed standard APP form was prepared” (2023 audit report on DepEd, Table No. 99).
  • Cash follows the monthly disbursement program. The SDO deposits a school’s MOOE “based on its MDP” (DO 029, s. 2019, Encl., item 18), so the months in that program must be the months the school plans to buy and pay.
  • Mismatches are an audit finding. COA reported schools whose purchases were not in their APP and non-IU schools whose purchases were “not in accordance with their approved Monthly Disbursement Program which was based on their APP” (2023 report, Table No. 99), and in 2025 it again found schools and offices that had not prepared or submitted APPs, used outdated forms or left out specifications (2025 report, Observation 20).

The school plans side by side

A school’s plans run from the three-year School Improvement Plan (SIP) down to the month’s cash. The Basic Education Development Plan 2030 (DepEd Order No. 024, s. 2022) sits above them all, with the Regional and Division Education Development Plans (REDP, DEDP) between it and the school. The table sets out the documents a school head prepares or feeds.

Document Legal basis Period Prepared by Approved by What it holds When it is due
School Improvement Plan (SIP) DepEd Order No. 44, s. 2015 and its SIP Guidebook Three school years The School Planning Team, led by the school head Appraised by the SDO with DepEd’s 2018 SIP Quality Assessment Tool; approved by the Schools Division Superintendent (SDS) The school’s priority improvement areas and the projects that answer them Year 1 of a cycle, with the year’s AIP, by “the second week of May” (DO 44, s. 2015, Encl., Sec. V.A)
Annual Implementation Plan (AIP), also called the school operating budget (SOB) DO 44, s. 2015 (Step 8); DO 008, s. 2019, Sec. V.D.1 and Annex 1 One fiscal year (January to December), plus the next first quarter The School Planning Team Annex 1’s line reads “Approved by: Head of Office/Organization”; in some divisions the SDS approves it Every PPA of the year, its objective, output indicator, fund source, and target and amount by month Each year with the SIP’s documents (DO 44, s. 2015); for the calendar-year AIP, divisions set dates in the last quarter
Work and Financial Plan (WFP), where the division asks for one No national form for school MOOE; division templates One fiscal year The school head As the division sets: the Assistant Schools Division Superintendent (ASDS) or the SDS The year’s PPAs with their amounts by month and, in budget-type templates, the object of expenditure Division calls, September to December
School operating budget (SOB) sheet, where the division asks for one The FMOM’s other name for the AIP (p. 127); division templates One fiscal year The school head As the division sets The school’s MOOE by object of expenditure, each line with its share of the total With the division’s WFP call
Project Procurement Management Plan (PPMP) IRR of RA 12009, Secs. 7.7.1 to 7.7.5 and 10.1; GPPB Resolution No. 03-2025 (form) One fiscal year The end-user, after market scoping Submitted by the head of the end-user; consolidated by the BAC Secretariat Each procurement project, procured or undertaken by administration: description, type, quantity, mode, schedule, fund source, estimated budget Indicative with the budget proposal; revised to the National Expenditure Program (NEP); final after the GAA
Annual Procurement Plan (APP): Indicative, Final, Updated IRR of RA 12009, Secs. 7.7.2 to 7.9; GPPB Resolution No. 03-2025 (form) One fiscal year The BAC Secretariat, from the PPMPs Recommended by the Bids and Awards Committee (BAC); approved by the head of the procuring entity (HoPE) Every procurement project of the procuring entity, with common-use supplies from PS-DBM as one summary row The final APP by the end of January of the budget year
APP-CSE GPPB Resolution No. 20-2018, Annex A; PS-DBM’s yearly form; DepEd Order No. 042, s. 2018, Encl. 3 One fiscal year The property or supply officer Funds certified by the accountant or budget officer; approved by the head of office (a non-IU school’s goes to the SDO for consolidation) Each common-use item from PS-DBM, by month, at PS-DBM’s price “not later than 31 August of the current year”; for 2027, September 15, 2026
Monthly disbursement program (MDP), Budget Execution Document (BED) No. 3 DO 029, s. 2019, Encl., items 5.9 and 18; DBM Circular Letter No. 2022-14, item 4.1 One fiscal year, by month The school, with its budget staff Consolidated by the SDO The school’s cash needs by month, its MOOE as one line With the division’s call; DBM’s own deadline for agencies’ NEP-based BEDs is November 15 or 30 (CL 2022-14, item 4.5.1)

Two calendars run through the table. The SIP and the school year run from June to April; the AIP, the WFP, the PPMP, the APP and the cash run by fiscal year, which is the calendar year. School MOOE is “valid for release and obligation for one fiscal year: that is from January 1 to December 31” (DO 008, s. 2019, Sec. I.3), although the FY 2026 GAA keeps FY 2026 MOOE valid until December 31, 2027 (DBM National Budget Circular No. 599, item 3.3). A fiscal-year plan therefore spans two school years, which is why Annex 1 carries a “Next Quarter (Quarter 1 of Succeeding Year)” column.

A separate guide explains what a WFP is in DepEd, where the term comes from in the government’s budget rules, and who must prepare one.

One project through every school plan

Project Basa-Galing is the series’ sample: reading remediation for struggling readers in Grades 2 to 4 at Liwayway Elementary School, a fictional non-implementing-unit (non-IU) elementary school of about 600 learners. Its budget is five common-use supplies bought from PS-DBM, ₱6,244.56 of school MOOE at the APP-CSE 2027 Form’s prices “as of April 27, 2026”, bought in January, June and September 2027 for three terms of after-class sessions. The school’s FY 2027 MOOE at the NEP level is taken as ₱1,262,000, an example amount: the median FY 2026 MOOE allocation of the 913 non-IU, purely elementary public schools with 550 to 650 learners in School Year (SY) 2025-2026. The sample WFP sets the project’s full row beside the school’s other PPAs.

Pick a field in the figure to see where it sits on each form.

Project Basa-Galing · seven documents · FY 2027

Follow one project through the school's plans

Pick what to follow. Every entry that carries it is marked on each form, and a form that does not carry it says why. The school and its project are the series' sample. Nothing you choose is kept or sent anywhere.

Follow

The project. The project's name runs from the AIP to the WFP and the PPMP. The SOB, the APP, the APP-CSE and the monthly disbursement program name no projects, so the PPMP is what ties the project to the procurement plans.

The amount. ₱6,244.56 is the AIP's full-year amount, the WFP's total, the PPMP's estimated budget, the APP-CSE's total for the five goods, and the project's part of the disbursement program's MOOE line. In the APP it sits inside one summary row for supplies from PS-DBM, and in the SOB it is split between two expense lines.

The months. January, June and September 2027 on every sheet that has months: the AIP's and the WFP's amounts, the PPMP's procurement schedule, the APP-CSE's quantities and the disbursements.

The goods. The five goods and their quantities are written out only in the PPMP and the APP-CSE. The AIP and the WFP carry what they cost, not what they are.

The fund source. School MOOE on every sheet but the APP-CSE: the AIP's fund column, Column 9 of the PPMP and the APP, and the disbursement program's MOOE line. The WFP and the SOB are drawn for the school MOOE as a whole, their totals checked against its NEP-level amount.

The expense class. Two sub-objects of Office Supplies Expenses: 5020301002 for the paper, cartolina, markers and folders (₱4,832.28), and ICT Office Supplies Expenses, 5020301001, for the ink (₱1,412.28). Booking the ink as an ICT supply is the sample's reading: COA's Government Accounting Manual describes the Office Supplies Expenses account as covering “office supplies such as bond paper, ink, and small tangible items” (Vol. III, Ch. 3), and the division's budget officer decides the code. Both codes are on the WFP's budget sheet and the SOB; the plans name the project instead, and the disbursement program carries MOOE as one line.

  1. 1. AIP

    ANNUAL IMPLEMENTATION PLAN FOR FY 2027

    DO 008, s. 2019, Annex 1: every activity, by month and by fund

    The program, project or activity
    Project Basa-Galing: reading remediation for struggling readers in Grades 2 to 4The project
    Its output indicator
    Struggling readers in Grades 2 to 4 given a full term of after-class reading sessions and reassessed (target: 60 learners); sessions held (target: 72)
    Its fund
    School MOOEThe fund source
    Target and Amount, by month
    January: 9 sessions, ₱2,195.41. February: 12 sessions. March: 3 sessions; 30 learners reassessed. June: ₱2,195.41. July: 9 sessions. August: 12 sessions. September: 3 sessions; 30 learners reassessed; ₱1,853.74. October and November: 12 sessions each.The months
    Full Year
    60 learners; 72 sessions; ₱6,244.56The amount

    Not on this form: the goods. The AIP carries what the project costs. The goods are in the budget breakdown behind the row and in the PPMP.

    Not on this form: the expense class. The AIP totals each line by fund (MOOE, SEF, others), not by object of expenditure.

    Prepared by: the school's planning team. Approved by: Head of Office/Organization.

  2. 2. WFP

    WORK AND FINANCIAL PLAN FOR FY 2027

    A division's budget-type template: no national form exists, and columns vary by division

    Program / Output / Activities
    Project Basa-Galing: reading remediation for struggling readers in Grades 2 to 4The project
    Expenses
    Two rows of the sheet: Office Supplies Expenses (UACS 5020301002), ₱4,832.28, for the paper, cartolina, markers and folders; ICT Office Supplies Expenses (5020301001), ₱1,412.28, for the ink cartridgesThe expense class
    Target
    60 learners
    Total Amount
    ₱6,244.56 (the two rows together)The amount
    Quarters 1 to 4, by month
    January ₱2,195.41; June ₱2,195.41; September ₱1,853.74; Quarter 4 noneThe months
    Sheet total checked against
    The school's MOOE at the NEP level, ₱1,262,000.00 for the whole sheetThe fund source

    Not on this form: the goods. A budget-type WFP names the expense class. The goods are in the budget breakdown and the PPMP.

    Prepared by: the school head. Reviewed and approved: as the division sets.

  3. 3. SOB

    SCHOOL MOOE BUDGET FOR FY 2027

    A division's sheet: the school's MOOE by object of expenditure, each line with its share; the FMOM's other name for the AIP (p. 127)

    Annual MOOE Budget
    ₱1,262,000.00, the school's MOOE at the NEP levelThe fund source
    Object of Expenditure: Office Supplies Expenses (UACS 5020301002)
    The school's whole line, ₱4,832.28 of it for the project's paper, cartolina, markers and foldersThe expense class
    Object of Expenditure: ICT Office Supplies Expenses (5020301001)
    The school's whole line, ₱1,412.28 of it for the project's ink cartridgesThe expense class

    Not on this form: the project. The SOB lists expense classes for the whole MOOE, not projects.

    Not on this form: the amount. The project's ₱6,244.56 is split between two expense lines, inside the school's totals.

    Not on this form: the months. The SOB is the year's budget. The months are in the WFP and the disbursement program.

    Not on this form: the goods. The SOB carries amounts only.

    Prepared by: the school head. Reviewed and approved: as the division sets.

  4. 4. PPMP

    PROJECT PROCUREMENT MANAGEMENT PLAN (PPMP) NO. 1 · INDICATIVE

    GPPB standard form (Resolution No. 03-2025): the projects the school will procure or undertake by administration; Fiscal Year 2027; End-User: Liwayway Elementary School

    Column 1. General Description and Objective of the Project to be Procured
    Common-use supplies for Project Basa-Galing (reading remediation, Grades 2 to 4): leveled passages, a reading folder for each learner, charts. Through procurement, not by administration.The project
    Column 2. Type of the Project to be Procured
    Goods
    Column 3. Quantity and Size of the Project to be Procured
    20 reams A4 multipurpose paper; 6 black ink cartridges, Epson T6641; 5 packs cartolina; 30 black permanent markers; 3 packs L-type A4 foldersThe goods
    Column 4. Recommended Mode of Procurement
    None of the modes: common-use supplies are bought from PS-DBM under Section 40, not by Agency-to-Agency (IRR of RA 12009, Secs. 35.5.2(c) and 40.1)
    Columns 6 to 8. Start and End of Procurement Activity; Expected Delivery
    01/2027, 06/2027 and 09/2027The months
    Column 9. Source of Funds
    GAA 2027, current appropriation: school MOOEThe fund source
    Column 10. Estimated Budget / Authorized Budgetary Allocation (PhP)
    ₱6,244.56, an estimated budget until the FY 2027 GAA is enactedThe amount
    Column 11. Attached Supporting Documents
    Market Scoping Checklist; PS-DBM's unit prices as of April 27, 2026

    Not on this form: the expense class. The printed form describes what is procured. The WFP's budget sheet and the SOB carry the expense class.

    Prepared by: the End-User or Implementing Unit. Submitted by: the Head of the End-User or Implementing Unit.

  5. 5. APP

    ANNUAL PROCUREMENT PLAN FOR FY 2027 · INDICATIVE

    GPPB standard form (Resolution No. 03-2025): the procuring entity's plan, consolidated from the PPMPs

    Row
    “Common Use Supplies and Equipment (CSE) to be purchased from PS-DBM (kindly indicate the summary/total amounts only)”
    Column 2. End-User or Implementing Unit
    Liwayway Elementary School
    Column 9. Source of Fund
    GAA 2027, current appropriation: school MOOEThe fund source
    Column 10. Estimated Budget / Approved Budget for the Contract (PhP)
    The school's total for common-use supplies; Project Basa-Galing's ₱6,244.56 is part of itThe amount

    Not on this form: the project. The supplies row carries a total only. The PPMP ties this total to the project.

    Not on this form: the months. The supplies row is a summary. When each good is bought is in the APP-CSE.

    Not on this form: the goods. The supplies row is a total. The APP-CSE lists the goods.

    Not on this form: the expense class. The printed form has no column for it.

    Prepared by: the BAC Secretariat. Recommended by: the BAC Chairperson. Approved by: the Head of the Procuring Entity.

  6. 6. APP-CSE

    APP-CSE 2027 FORM

    PS-DBM's form, Part I: the goods the school will buy from PS-DBM, by month, uploaded on mPhilGEPS

    PAPER, MULTIPURPOSE A4 (ream)
    January 7, June 7, September 6: 20 at ₱139.80 = ₱2,796.00The goodsThe months
    INK CARTRIDGE, EPSON C13T664100 (T6641), Black (cart)
    January 2, June 2, September 2: 6 at ₱235.38 = ₱1,412.28The goodsThe months
    CARTOLINA, assorted colors (pack)
    January 2, June 2, September 1: 5 at ₱201.87 = ₱1,009.35The goodsThe months
    MARKER, Permanent, Black (piece)
    January 10, June 10, September 10: 30 at ₱15.84 = ₱475.20The goodsThe months
    FOLDER, L-type, A4 (pack)
    January 1, June 1, September 1: 3 at ₱183.91 = ₱551.73The goodsThe months
    A. TOTAL (these five lines)
    ₱6,244.56The amount
    B. ADDITIONAL PROVISION FOR PRICE CHANGES (10% of TOTAL)
    Computed on the school's whole plan, at the foot of the form, not per project

    Not on this form: the project. The form lists goods. The school adds up every project's need for each good.

    Not on this form: the fund source. The form has no fund column; the head of office approves the plan's budget in figures and words (line E).

    Not on this form: the expense class. The goods carry PS-DBM's product codes instead.

    Prepared by: Property/Supply Officer. Certified funds available: Accountant / Budget Officer. Approved by: Head of Office/Agency.

  7. 7. Disbursement program

    MONTHLY DISBURSEMENT PROGRAM (BED No. 3) FOR FY 2027

    DBM's BED No. 3: the school's cash needs by month, its MOOE as one line; the SDO deposits MOOE cash on it (DO 029, s. 2019, item 18)

    Particulars
    MOOE: the school's whole allocation, under the new GAA's comprehensive releaseThe fund source
    January, June, September
    ₱2,195.41, ₱2,195.41 and ₱1,853.74 of the MOOE line in those monthsThe months
    Total Program (the project's part of the MOOE line)
    ₱6,244.56The amount

    Not on this form: the project. The program carries the school's MOOE as one line, so the project's ₱6,244.56 sits inside it.

    Not on this form: the goods. The program carries amounts only.

    Not on this form: the expense class. DBM's BED No. 3 carries MOOE as one line; some divisions' monthly sheets split it by object of expenditure.

    Prepared by the school with its budget staff; consolidated by the SDO.

Each form shows its column names in its own order, with the project's entry; columns the entry leaves blank are left out, and the AIP's first columns are named by what they hold. The WFP's and the SOB's columns are one division template's; another division's may differ. That template lists only Office Supplies Expenses: the split into ICT and other office supplies is the sample's. The disbursement program follows DBM's BED No. 3, with the school's MOOE as one line. Sources: DO 008, s. 2019, Annex 1; the FMOM, p. 127; GPPB Resolution No. 03-2025 (PPMP and APP forms); PS-DBM's APP-CSE 2027 Form; DBM Circular Letter No. 2022-14, item 4.1; DO 029, s. 2019, item 18; the Unified Accounts Code Structure. Prices are PS-DBM's as of April 27, 2026.

Each form takes something different from the project.

  • The AIP carries the project by name, its output indicator (60 learners, 72 sessions), its fund source (School MOOE), and a target and an amount for each month: ₱2,195.41 in January and June, ₱1,853.74 in September, and sessions in February, March, July, August, October and November.
  • The WFP a division asks for carries the same row in its own columns, and its total is checked against the school’s NEP-level MOOE. A budget-type template adds the object of expenditure, here two rows: Office Supplies Expenses (Unified Accounts Code Structure, UACS, 5020301002), ₱4,832.28, for the paper, cartolina, markers and folders, and ICT Office Supplies Expenses (5020301001), ₱1,412.28, for the ink cartridges. Booking the ink as an ICT supply is the sample’s reading: COA’s Government Accounting Manual describes the Office Supplies Expenses account as covering “office supplies such as bond paper, ink, and small tangible items” (Vol. III, Ch. 3), and the division’s budget officer decides the code.
  • The SOB, where the division asks for one, names no project: it carries the school’s MOOE by object of expenditure, with the project’s ₱4,832.28 and ₱1,412.28 inside its two office supplies lines.
  • The PPMP carries the procurement: the five goods and their quantities, marked as procured, the months of procurement and delivery, the fund source and ₱6,244.56 as the estimated budget. Its fourth column, the recommended mode, names none of the modes of Section 26 of the IRR: common-use supplies are bought “only from the PS-DBM, subject to its availability” (Sec. 40.1), and the IRR keeps “Procurement of Goods from the PS-DBM” out of Agency-to-Agency procurement (Sec. 35.5.2(c)).
  • The APP carries the project only inside its row for common-use supplies from PS-DBM, which the form asks for as “summary/total amounts only”.
  • The APP-CSE carries the goods by month at PS-DBM’s prices, with no project name: the school adds up every project’s need for each good.
  • The monthly disbursement program carries the money by month, with no project name: Basa-Galing’s ₱6,244.56 sits inside the school’s MOOE line for January, June and September, since DBM’s BED No. 3 carries MOOE as one line.

WFP vs AIP: the same year in two forms

A school’s AIP and a WFP describe the same year, and DepEd’s own texts treat them as one for a school. The WFP is “an annual operational plan that details the office’s planned programs, outputs, and activities including the timelines and budgetary requirements”, which “guides budget execution by outlining the monthly physical, obligation, and disbursement plans” (DO 017, s. 2024, Annex A, item A). In the Program Management Information System (PMIS), it “consists of the Physical Plan, Monthly Obligation Program, and Monthly Disbursement Program as prescribed by the Department of Budget and Management (DBM)” (DepEd Order No. 011, s. 2021, Part III, item r). The PMIS is used “at the Central Office, Regional Offices, and Schools Division Offices only”, and the separate policy for schools that the order promises (Part VIII.1) had not been issued as of November 26, 2026.

Set Annex 1 of DO 008, s. 2019 beside that definition. Its “Target” columns are a physical plan by month, and its “Amount” columns are the money each month needs, totaled by fund. The disbursement program is the one part a school keeps apart, as its MDP. The FMOM reads the same way: “The AIP is also referred to as the school operating budget (SOB)” (p. 127), and the first MOOE cash advance of the year is supported by the “Annual Improvement [sic] Plan culled out of School Improvement Plan” and a “Monthly Disbursement Program” (p. 95).

The AIP and a division’s WFP still differ in three ways.

AIP (DO 008, s. 2019, Annex 1) Division WFP (budget-type template)
Funds Every fund: “TOTAL MOOE”, “TOTAL SEF” and “TOTAL OTHERS”, which covers “PTA funds, Canteen Funds, Donations (in cash and/or in kind), etc.” Usually the school MOOE alone, its total checked against the NEP-level allocation
How a line is described By PPA, objective and output indicator By PPA and object of expenditure (in some templates with its UACS code), in some with tax withheld and the amount net of tax
Physical targets A target for every month Varies: some templates ask only for the number of participants or beneficiaries

What may not differ is the substance. MOOE funds activities “identified in the approved School Improvement Plan (SIP) for implementation in the current year and as specifically determined in the Annual Implementation Plan” (DO 008, s. 2019, Sec. V.D.1), and a school’s purchases must follow its approved WFP or AIP and the APP (DO 017, s. 2024, Annex A, item B). A PPA in the WFP that is not in the AIP has no approved plan behind its purchases, and a WFP whose amounts differ from the AIP’s leaves the school with two versions of one plan. Imus City’s evaluation tool checks that the WFP’s activities are in the AIP (DM 768, s. 2025, Encl. 3, item 2), and Dasmariñas City calls the document “Annual Implementation Plan / Work and Financial Plan” (DM 859, s. 2026).

DO 44, s. 2015 has its own AIP template (the SIP Guidebook’s Annex 10), headed by school year. For MOOE, the calendar-year format of DO 008, s. 2019 governs. The sample SIP and AIP sets one project on Annex 1’s fifteen months.

WFP vs PPMP: every PPA against what is procured

The WFP covers every PPA of the year; the PPMP covers the PAPs, or the parts of them, that the school will procure or undertake by administration, and adds what the WFP leaves out: each project’s mode and schedule. The IRR has each end-user prepare PPMPs “covering their programs, activities, and projects (PAPs)” with seven pieces of information (Sec. 7.7.1):

  1. “Whether the implementation of the PAPs will require procurement or undertaken by administration”;
  2. the type and objective of the project to be procured;
  3. its quantity and size;
  4. the procurement modes to be adopted;
  5. the schedule of each procurement activity;
  6. “The estimated budget for the contract”; and
  7. the technical specifications, scope of work or terms of reference.

The GPPB’s standard PPMP form (approved by Resolution No. 03-2025) has twelve columns: the general description and objective, the type, the quantity and size, the recommended mode, whether a pre-procurement conference is held, the start and end of the procurement activity, the expected delivery, the source of funds, the estimated budget or authorized budgetary allocation, the attached supporting documents, and remarks. Its guide asks the end-user to “Indicate whether the project will be implemented through procurement or by administration” in the first column, and it makes “The duly accomplished Market Scoping Checklist for each procurement project” a mandatory supporting document. Market scoping comes first: the end-user conducts it “as a preliminary undertaking in preparing its PPMP” (IRR, Sec. 10.1).

How does a WFP row become PPMP lines? A PPA that buys goods, services or works becomes one or more PPMP lines, marked as procured. A repair the school undertakes by administration stays on the PPMP, marked so, with its materials. A PPA with nothing to buy and no works to carry out, such as a learning action cell session run by the school’s own teachers, becomes none. Some costs in a WFP are not procurement at all, such as a teacher’s travel expenses to a division training, which are reimbursed, not bought.

The PPMP’s amount for a PPA is therefore at most its WFP amount. “All procurement should be within the approved budget of the Procuring Entity” (IRR, Sec. 7.7), and a school’s purchases must follow its approved AIP or WFP and APP (DO 017, s. 2024, Annex A, item B). For Project Basa-Galing every peso is a purchase, so the PPMP’s ₱6,244.56 equals the WFP’s.

A school can mark each PPA that buys something or is undertaken by administration, so that every marked PPA is checked against its PPMP lines before the plans go to the division. It is a working aid; no national form requires it.

The PPMP also moves with the budget. Indicative PPMPs support the budget proposal; “Upon submission of the National Expenditure Program (NEP)” the end-user revises them “to reflect the budgetary allocation” (Sec. 7.7.3); once the GAA is final, the end-user finalizes them for the final APP (Sec. 7.7.5). As of November 26, 2026, the FY 2027 GAA had not been enacted, so FY 2027 PPMPs and WFPs are at the NEP level. The guide to school procurement under RA 12009 covers the PPMP’s role in each purchase.

PPMP vs APP: one end-user’s purchases, then the whole plan

The PPMP is one end-user’s list; the APP is the procuring entity’s whole plan, made from the PPMPs. GPPB Resolution No. 03-2025, in approving the forms, describes the PPMP as “a document prepared by the End-User or Implementing Unit that identifies the specific procurement requirements necessary for the implementation of their programs, activities, and projects”, and the APP as “a consolidated document listing all procurement requirements of a government entity for a given fiscal year”, which “is derived from the Project Procurement Management Plans submitted by End-User or Implementing Unit”.

PPMP APP
Whose The end-user or implementing unit The procuring entity
Prepared by The end-user, after market scoping The BAC Secretariat, from the approved PPMPs
Signed “Prepared by” the end-user; “Submitted by” its head Prepared by the BAC Secretariat; recommended by the BAC Chairperson; approved by the HoPE
What it holds Each procurement project with its description, quantity and size, mode, schedule, fund source, estimated budget and supporting documents Each procurement project with its end-user, mode, early procurement, bid evaluation criteria, schedule, fund source, estimated budget or approved budget for the contract (ABC), strategy and remarks
Versions Numbered; Indicative, then Final Indicative, Final, then Updated versions (Version 1, Version 2 and so on)
Rule Changes “may be undertaken as often as necessary” (Sec. 7.9) “No government procurement shall be undertaken unless it is in accordance with the approved Indicative APP or final APP” (Sec. 7.8)

The APP form has three groups of rows: the general requirements, “Miscellaneous Items (for Direct Acquisition only) Sec 32.2 of RA No. 12009”, and the common-use supplies from PS-DBM as a summary. Its foot gives three totals: early procurement projects, common-use supplies from PS-DBM, and the whole estimated budget. An Updated APP lists every project of the year, changed or not, with the new or revised rows highlighted and the changes in bold.

DepEd’s signing order still speaks of a “Supplemental WFP and a Supplemental APP” (DO 017, s. 2024, Annex A, item B), and COA’s recommendations use “supplemental APPs and PPMPs”. Under the new forms, a change after the final APP is an Updated APP.

Which APP holds a school’s purchases depends on how the division is set up. The FMOM has each school constitute “a school bids and awards committee (SBAC)”, lets small schools “be clustered to form a cluster BAC”, and notes that “Some divisions have formed district level BAC and SIC for clustered schools” (p. 130). The SDS’s designation order shows which BAC acts for a school, and the guide to small value procurement and direct acquisition explains the modes a school’s APP names most often.

The APP-CSE and the APP

The APP-CSE is the part of the procurement plan that PS-DBM sees: each common-use item, by month, at PS-DBM’s price. DO 042, s. 2018 has every DepEd office and school prepare one and send it to its supply office “for consolidation”; a school that is not an implementing unit sends it to the SDO’s Property and Supply Unit (Encl. 3, item 1.a). The plan for the next budget year is uploaded on the Modernized Philippine Government Electronic Procurement System (mPhilGEPS) “not later than 31 August of the current year” (GPPB Resolution No. 20-2018, Annex A, item 5.2). For 2027, PS-DBM moved that date to September 15, 2026 (Advisory No. 2026-22).

The APP-CSE sets two limits. “Only agencies that have uploaded their APP-CSE to the VS via mPhilGEPS will be able to purchase CSE items from PS-DBM” (PS-DBM Virtual Store FAQs, item 9), and “all CSE requirements in excess of the quantities indicated in the original APP-CSE form will not be served if not covered by a supplemental APP-CSE” (APP-CSE 2027 Form, Reminder 7). If Liwayway’s plan asked PS-DBM for only four ink cartridges for the year, PS-DBM would not serve the two more its sessions need unless a supplemental APP-CSE covered them.

Does the APP-CSE replace the APP? No. DO 042, s. 2018 puts “all inventory items (common and non-common use supplies, materials and equipment) that will be procured for the current year” in the APP (Policy Statement), and the GPPB’s APP form keeps a row for “Common Use Supplies and Equipment (CSE) to be purchased from PS-DBM”. COA’s 2023 report on DepEd faulted the implementing schools of one division where “Only the APP-CSE instead of the GPPB prescribed standard APP form was prepared as the basis of procurement” (Table No. 99).

Compare the APP-CSE with the WFP line by line, not by grand total. The form adds “B. ADDITIONAL PROVISION FOR PRICE CHANGES (10% of TOTAL)” and any freight to the whole plan, so its grand total is larger than the sum of the supply lines in the WFP. The series’ sample WFP sets that provision aside once, as a line of its own, rather than inside each project. What the head of office signs is that the total “has been included in or is within our approved budget for the year”. The APP-CSE guide covers the form, the deadline and ordering from PS-DBM.

The school operating budget and the monthly disbursement program

The school operating budget (SOB) is the FMOM’s other name for the AIP (p. 127), and the FMOM’s glossary calls it an “annual budget that contains estimates of the total value of resources … required for the performance of the operation” (p. 202). Some divisions ask for the SOB as a sheet of its own: the school’s MOOE by object of expenditure, with each line’s share of the total. Where they do, its lines add up to the same MOOE total as the WFP. In Liwayway’s SOB, the project’s ₱4,832.28 of paper, cartolina, markers and folders sits in the Office Supplies Expenses line and its ₱1,412.28 of ink in the ICT Office Supplies Expenses line.

The monthly disbursement program is “the estimated monthly disbursement requirements of the operating units (OUs) of DepEd” (DO 029, s. 2019, Encl., item 5.9). For a non-IU school it decides the cash: “The cash requirement to be deposited for MOOE of the schools will be determined by the expenditures needed based on its MDP. It shall be released by the SDO within the first week of every month or quarter, subject to availability of cash allocation released by the DBM” (item 18). Above the school, DBM includes in the comprehensive Notice of Cash Allocation “the requirements of DepEd’s non-IUs corresponding to the amounts indicated in the approved Monthly Disbursement Program” (COA-DBM-DepEd Joint Circular No. 2019-1, item 6.2.1, enclosed in DO 029).

At the national level the MDP is BED No. 3, the “Basis for the initial and subsequent issuance of disbursement authorities” (DBM Circular Letter No. 2022-14, item 4.1), and DBM reminds agencies “to ensure the consistency of the information reflected in the BEDs with the procurement schedules/specifications” sent to the GPPB and PS-DBM (item 4.3). BED No. 3 is laid out by type of disbursement authority and allotment class, so the school’s program carries its MOOE as one line (item 4.1 and Annex C); the object of expenditure lives in the WFP’s budget sheet and the SOB. Some divisions’ monthly cash sheets also split each month by object of expenditure.

For a school, the months in the MDP follow the months in the AIP, the WFP and the APP-CSE. Basa-Galing’s part of the MOOE line is ₱2,195.41 in January, ₱2,195.41 in June and ₱1,853.74 in September; a program that put all ₱6,244.56 in January would send the cash months before June’s and September’s purchases.

What must match across the WFP, AIP, PPMP and APP

Five fields carry the same project through the plans, and a sixth ties the plans to the budget sheets.

Field Where it appears What must agree The rule behind it
The PPA SIP project; AIP; WFP; PPMP Column 1 The same name and purpose, traceable to the SIP MOOE funds the activities set in the approved SIP and the AIP (DO 008, s. 2019, Sec. V.D.1); purchases follow the approved WFP or AIP and the APP (DO 017, s. 2024, Annex A, item B)
The amount AIP full year; WFP total; PPMP Column 10; APP Column 10 (within the supplies row for PS-DBM goods); APP-CSE lines; MDP (inside the MOOE line) The PPMP’s estimate for a PPA is no more than its AIP and WFP amount; the APP’s total is the sum of its PPMPs Procurement within the approved budget (IRR, Sec. 7.7); purchases in accordance with the approved AIP or WFP and APP (DO 017, s. 2024, Annex A, item B)
The months AIP and WFP monthly amounts; PPMP Columns 6 to 8; APP Columns 7 and 8; APP-CSE monthly quantities; MDP A purchase is planned, ordered, delivered and paid in the same months on every sheet Cash is deposited on the MDP (DO 029, s. 2019, Encl., item 18); BEDs consistent with procurement schedules (CL 2022-14, item 4.3)
The goods and quantities Budget breakdown behind the WFP row; PPMP Column 3; APP-CSE lines The same items and the same yearly quantities PS-DBM does not serve quantities beyond the plan (APP-CSE 2027 Form, Reminder 7)
The fund source AIP fund column; PPMP Column 9; APP Column 9; the MDP’s MOOE line; the WFP and SOB by the fund they are drawn for The same fund on every sheet Each fund has its own rules: SEF items must be in the SEF budget, among Annex C’s items and in the approved SIP and DEDP (DepEd-DBM-DILG-DOF Joint Circular No. 01, s. 2025, §6.3.1)
The object of expenditure WFP (budget-type); SOB; some divisions’ monthly cash sheets The same class and UACS code on the budget sheets The SOB and budget-type WFPs are drawn by object of expenditure; DBM’s BED No. 3 carries MOOE as one line (CL 2022-14, item 4.1)

The totals of the whole plan agree as well. Division templates check that the WFP total equals the school’s NEP-level MOOE, and where an SOB is asked for, that the SOB equals both. The PPMPs add up to the school’s part of the APP. The WFP and the PPMPs agree PPA by PPA, but their grand totals need not: the WFP also carries costs that are not procurement. Imus City’s evaluation tool does check that “The same total amount were [sic] reflected in the PPMP, APP, and WFP” (Encl. 3, item 13), so a school follows its own division’s instruction on where such costs go.

Three other differences are expected and are not errors: the APP-CSE’s 10% provision for price changes, the APP’s single row for PS-DBM supplies, and the move from the NEP level to the GAA once the budget is enacted.

Each amount in these plans comes from costing each PPA and checking which fund may pay for it. The figure below is a draft of Basa-Galing’s documents with five errors in it.

Practice · a draft packet · 10 entries

Find what does not match

Each entry comes from a draft of Project Basa-Galing's documents. Judge it against the approved row, and the answer appears under it with the rule. 5 entries do not match. Nothing you choose is kept or sent anywhere.

The approved row

  • Project Basa-Galing, paid from the school MOOE
  • Office Supplies Expenses (UACS 5020301002), ₱4,832.28, and ICT Office Supplies Expenses (5020301001), ₱1,412.28
  • ₱6,244.56: ₱2,195.41 in January, ₱2,195.41 in June, ₱1,853.74 in September 2027
  • 20 reams A4 paper, 6 ink cartridges (2 in each of the three months), 5 packs cartolina, 30 markers, 3 packs folders
  1. 1. AIP, Full Year: ₱6,244.56

    Right.Not quite. This entry agrees.

    The AIP's full year is the WFP row's total. DO 008, s. 2019 has MOOE fund the activities the AIP sets out (Sec. V.D.1), and the WFP row restates the AIP's, so the two should be the same amount.

  2. 2. WFP, Expenses: Office Supplies Expenses (5020301002) for the paper, cartolina, markers and folders; ICT Office Supplies Expenses (5020301001) for the ink

    Right.Not quite. This entry agrees.

    These are the two sub-objects of Office Supplies Expenses in the Unified Accounts Code Structure. Booking the ink as an ICT office supply is the sample's reading: COA's Government Accounting Manual describes the Office Supplies Expenses account as covering “office supplies such as bond paper, ink, and small tangible items” (Vol. III, Ch. 3), and the division's budget officer decides the code.

  3. 3. PPMP, Column 3: Quantity and Size: 20 reams A4 paper; 6 ink cartridges; 5 packs cartolina; 30 markers; 3 packs folders

    Right.Not quite. This entry agrees.

    The same goods and quantities as the budget breakdown behind the WFP row, and the same yearly totals as the APP-CSE.

  4. 4. PPMP, Column 10: Estimated Budget: ₱6,500.00

    Right.Not quite. This entry does not match.

    ₱255.44 more than the project's budget. “All procurement should be within the approved budget of the Procuring Entity” (IRR of RA 12009, Sec. 7.7), and a school's purchases follow its approved AIP or WFP and APP (DO 017, s. 2024, Annex A, item B): a PPMP above the AIP and WFP line plans a purchase the plan does not pay for.

    Fix: ₱6,244.56, or raise the AIP and WFP line first if the market scoping found higher prices.

  5. 5. PPMP, Column 9: Source of Funds: Special Education Fund

    Right.Not quite. This entry does not match.

    The AIP pays the project from the school MOOE. An SEF item must be in the local school board's SEF budget, among the items of the joint circular's Annex C and in the approved SIP and DEDP (Joint Circular No. 01, s. 2025, §6.3.1).

    Fix: GAA 2027, current appropriation: school MOOE.

  6. 6. APP, common-use supplies row: Left out: the school's supplies from PS-DBM are only in its APP-CSE

    Right.Not quite. This entry does not match.

    The APP form keeps a row for “Common Use Supplies and Equipment (CSE) to be purchased from PS-DBM”, and DO 042, s. 2018 puts every inventory item in the APP. Auditors faulted implementing schools that prepared only the APP-CSE as the basis of procurement (COA, 2023 annual audit report on DepEd, Table No. 99).

    Fix: Enter the school's total for common-use supplies in the APP's supplies row, Basa-Galing's ₱6,244.56 within it.

  7. 7. APP-CSE, PAPER, MULTIPURPOSE A4: January 7, June 7, September 6: 20 reams at ₱139.80 = ₱2,796.00

    Right.Not quite. This entry agrees.

    The quantities match the PPMP and the months match the AIP; the price is PS-DBM's as of April 27, 2026.

  8. 8. APP-CSE, INK CARTRIDGE, EPSON T6641, Black: January 2, June 0, September 2: 4 cartridges at ₱235.38 = ₱941.52

    Right.Not quite. This entry does not match.

    The plan asks PS-DBM for 4 cartridges, 2 fewer than the project's 6, and none in June, when the supplies for Term 1 of the next school year are bought. Requirements beyond the plan “will not be served if not covered by a supplemental APP-CSE” (APP-CSE 2027 Form, Reminder 7).

    Fix: January 2, June 2, September 2: 6 cartridges, ₱1,412.28.

  9. 9. SOB, Office Supplies Expenses (5020301002): The school's line includes ₱4,832.28 for the project's paper, cartolina, markers and folders

    Right.Not quite. This entry agrees.

    ₱2,796.00 + ₱1,009.35 + ₱475.20 + ₱551.73 = ₱4,832.28, the WFP's first expense row. The ink's ₱1,412.28 sits in the ICT Office Supplies Expenses line.

  10. 10. Disbursement program, the MOOE line, the project's part: January ₱6,244.56; June and September nothing

    Right.Not quite. This entry does not match.

    The SDO deposits a school's MOOE cash on its disbursement program (DO 029, s. 2019, item 18), and the plans buy in January, June and September. Auditors faulted purchases of schools that were “not in accordance with their approved Monthly Disbursement Program” (COA, 2023 annual audit report on DepEd, Table No. 99).

    Fix: ₱2,195.41 in January, ₱2,195.41 in June, ₱1,853.74 in September.

The five errors are invented for practice; each is a kind of mismatch that COA's audit reports on DepEd describe. Sources: DO 008, s. 2019, Sec. V.D.1; IRR of RA 12009, Sec. 7.7; DO 017, s. 2024, Annex A, item B; Joint Circular No. 01, s. 2025, §6.3.1; DO 042, s. 2018; GPPB Resolution No. 03-2025 (APP form); APP-CSE 2027 Form, Reminder 7; DO 029, s. 2019, item 18; COA's Government Accounting Manual, Vol. III, Ch. 3; COA, 2023 annual audit report on DepEd, Table No. 99.

What auditors flag when the plans do not match

COA’s annual audit reports on DepEd describe the mismatches by school and by division. In its 2023 report, under “Deficiencies in the preparation of APP and PPMP” (Table No. 99, pp. 319 to 321), it reported, among others:

  • 32 implementing units in one division that prepared no APP or PPMP;
  • school purchases of ₱976,336.54 and ₱609,984.47 that were “not included in the APP”;
  • PPMPs for supplies, equipment, semi-expendable property and training expenses that “were not prepared and integrated in the approved APP”, which led to frequent purchases;
  • implementing schools that prepared only the APP-CSE as the basis of procurement;
  • APP-CSE quantities smaller than what schools actually bought, and repair materials left out of the APP for items other than common-use supplies;
  • “Procurements of Non-IUs are not in accordance with their approved Monthly Disbursement Program which was based on their APP”.

Its recommendation to the school heads of that last division was to “ensure that school’s procurements are included in their approved Monthly Disbursement Program and hence are aligned with their approved APP, and whenever there are changes thereto, to seek approval of revised or supplementary APP, as the case maybe, before proceeding with any procurement” (par. 12.15(b), p. 321). The same report recorded a school head who explained that he “did not prepare the Annual Implementation Plan (AIP), School Operating Budget (SOB), and APP of the school” after moving to it in February 2023 (par. 12.35, p. 335). It also found non-IU schools in one province that “encountered difficulties in executing their Work and Financial Plan (WFP) according to their schedule”: ₱111,717.25 of their funds reverted to the National Treasury and ₱1,133,179.59 stayed unreleased at year-end (pp. 154 and 155).

The 2025 report (Observation 20, Table No. 84, pp. 220 and 221) found schools and offices under ten regional offices that had not prepared or submitted APPs, had used outdated or incomplete forms, or had left out technical specifications. Management agreed “to instruct the concerned schools and offices to prepare and approve consolidated APP and PPMP” and “to adopt supplemental APPs and PPMPs for newly identified projects and align APPs with approved budgets”. In one region, ₱47,298,000 of procurement in October to December 2025 was processed “without using the required New Standard Forms such as APP, PPMP, and the Mandatory Market Scoping Form”.

When one plan changes, which others change

A change runs down the chain before any purchase: the AIP and the WFP first, then the PPMP and the APP, then the APP-CSE if the change touches PS-DBM supplies, then the disbursement program. The IRR allows “additional PPMPs or changes to the PPMPs … as often as necessary”, with the BAC Secretariat folding the approved PPMPs into the APP for the HoPE’s approval (Sec. 7.9). PS-DBM lets an agency edit its uploaded APP-CSE on mPhilGEPS if “a signed and approved copy of the supplemental APP-CSE form is available” (APP-CSE 2027 Form, Reminder 7).

The school head reviews the plans each quarter. DepEd Order No. 029, s. 2022 has the school head “Conduct quarterly Program Implementation Review (PIR) in the school to track physical and financial accomplishments” (Sec. VIII, item f). Offices that use the PMIS have ten working days after a PIR to revise their WFP (DO 011, s. 2021, Part III, item m); no national text sets a deadline for a school’s revision. The guide to making a school WFP takes a plan through the PIR and its adjustment.

The budget itself changes once a year. Divisions have schools plan on the NEP-level MOOE and adjust after the GAA; the IRR has PPMPs revised at the NEP (Sec. 7.7.3) and finalized after the GAA (Sec. 7.7.5). When Congress changes an agency’s NEP, DBM wants its revised BEDs “within fifteen (15) working days after approval of the GAA” (CL 2022-14, item 4.5.3.2).

What this means for school heads

  1. Write the AIP first, and the rest from it. Every PPA in a WFP, a PPMP or an APP should trace to a project in the SIP and a row in the AIP, in Annex 1’s calendar-year format, with each line’s fund.
  2. Mark the PPAs that buy something or are undertaken by administration. For each, prepare PPMP lines after market scoping, with the Market Scoping Checklist attached, and keep each PPA’s PPMP estimate within its AIP and WFP amount.
  3. Put PS-DBM supplies in two places. Add up every PPA’s need for each common-use item into the APP-CSE by month, and make sure the APP that covers the school carries their total in its supplies row.
  4. Spread the money by the months you will buy. The monthly amounts in the AIP and WFP, the PPMP’s schedule, the APP-CSE’s quantities and the disbursement program should name the same months.
  5. Check the totals before submitting. The WFP total against the NEP-level MOOE the division sent, the SOB against the WFP where one is asked for, and the PPMPs against the APP. The sample WFP and template carry formula checks for these totals.
  6. Change the plans before you buy. A new purchase, a larger quantity or a different month goes into the AIP or WFP, the PPMP, the Updated APP and, for PS-DBM goods, a supplemental APP-CSE, in that order.
  7. Keep the signed versions together. Keep the approved AIP, WFP, PPMPs, APP (each version), APP-CSE and disbursement program for the year in one file. Auditors compare them, and COA has asked the bookkeepers of three regions to attach to each voucher “a copy of the page of the approved APP and supplemental APP where the items to be procured are found” (2023 report, par. 12.15(c)).

These tasks fall under Domain 2 of the Philippine Professional Standards for School Heads (PPSSH), Managing School Operations and Resources, which the guide to PPSSH Domain 2 sets out with its finance and procurement strands.

Frequently asked questions

What is the difference between a WFP and a PPMP?

A WFP lists every program, project and activity of the fiscal year with its targets and amounts by month. A PPMP lists the projects the end-user will procure or undertake by administration, with each one’s quantity, mode, schedule and estimated budget, and states whether each PAP “will require procurement or undertaken by administration” (IRR of RA 12009, Sec. 7.7.1). A PPA with nothing to buy and no works to carry out has a WFP line and no PPMP line.

Is the WFP the same as the AIP?

For a school, the AIP does the work of the WFP. DO 017, s. 2024 refers schools to “the approved WFP/Annual Implementation Plan and the APP” (Annex A, item B), and the AIP’s format in DO 008, s. 2019, Annex 1, already has a target and an amount for every month. Where a division asks for a WFP on its own template, its PPAs and amounts should be the AIP’s.

What is the difference between the PPMP and the APP?

The PPMP is one end-user’s list of procurement projects; the APP is the procuring entity’s consolidated plan, made by the BAC Secretariat from the approved PPMPs, recommended by the BAC and approved by the head of the procuring entity (IRR of RA 12009, Secs. 7.7.2 and 7.7.5). No procurement may be undertaken unless it is in the approved Indicative or final APP (Sec. 7.8).

Does the APP-CSE replace the APP?

No. The APP-CSE lists the common-use supplies bought from PS-DBM, by month; the APP lists every procurement project and carries those supplies as one summary row. DO 042, s. 2018 puts all inventory items in the APP, and COA faulted schools that prepared only the APP-CSE (2023 audit report on DepEd, Table No. 99).

Must the WFP total equal the PPMP total?

Not under the procurement rules. The PPMP covers procurement, while the WFP also carries costs that are not procurement, such as travel expenses, so the WFP’s total can be larger. For each PPA, the PPMP’s estimate for its purchases should not exceed the PPA’s amount in the AIP and WFP (IRR of RA 12009, Sec. 7.7; DO 017, s. 2024, Annex A, item B). One division’s evaluation tool checks the two totals against each other: follow the division’s memorandum. Division templates also check that the WFP’s total equals the MOOE the division sent at the NEP level.

Sources

DepEd issuances

  • DepEd Order No. 008, s. 2019, Revised Implementing Guidelines on the Direct Release, Use, Monitoring and Reporting of Maintenance and Other Operating Expenses Allocation of Schools, Including Other Funds Managed by Schools, May 2, 2019: Secs. I.3, V.D and V.D.1; Annex 1.
  • DepEd Order No. 017, s. 2024, Amendment to the Provisions of DepEd Order No. 001, s. 2023 on Signing Authorities for Financial Matters in the Department of Education, December 4, 2024: Annex A, items A and B.
  • DepEd Order No. 011, s. 2021, Guidelines on the Operationalization of the Program Management Information System, February 24, 2021: Part III, items m and r; Part VIII.1.
  • DepEd Order No. 44, s. 2015, Guidelines on the Enhanced School Improvement Planning (SIP) Process and the School Report Card (SRC), September 29, 2015: Encl., Sec. V.A; SIP Guidebook, Activity 1.2, Step 8 and Annex 10.
  • DepEd Order No. 029, s. 2019, Procedural Guidelines on the Management of Cash Advances for School Maintenance and Other Operating Expenses and Program Funds of Non-Implementing Units Pursuant to COA, DBM and DepEd Joint Circular No. 2019-1, October 17, 2019: Encl., items 5.9 and 18; Joint Circular No. 2019-1, item 6.2.1.
  • DepEd Order No. 029, s. 2022, Adoption of the Basic Education Monitoring and Evaluation Framework, June 22, 2022: Sec. VIII, item f.
  • DepEd Order No. 024, s. 2022, Adoption of the Basic Education Development Plan 2030, May 30, 2022.
  • DepEd Order No. 042, s. 2018, Updated Guidelines on Delivery, Inspection, Acceptance and Recording of DepEd Procured Assets, September 21, 2018: Policy Statement; Encl. 3, item 1.a.
  • DepEd Order No. 60, s. 2016, Implementation of the Financial Management Operations Manual and Orientation of DepEd Financial Management Staff at the Regional, Division, and School Levels, September 2, 2016: FMOM, pp. 95, 127, 130 and 202.

Procurement law and forms

Budget issuances

Division memoranda (examples of practice)

Accounting

  • Commission on Audit, Government Accounting Manual, Volume III, Chapter 3, Description of Accounts: Office Supplies Expenses (50203010).
  • Unified Accounts Code Structure, Object Code, Sub-Object, under Office Supplies Expenses: 5020301001, ICT Office Supplies Expenses; 5020301002, Office Supplies Expenses (read November 26, 2026).

Audit reports

The school WFP series

Written by Mark Anthony Llego for NASH Reviewer. Sources: DO 008, s. 2019; DO 017, s. 2024; DO 011, s. 2021; DO 029, s. 2019; DO 042, s. 2018; the FMOM; the IRR of RA 12009 and the GPPB’s standard forms; PS-DBM’s APP-CSE 2027 Form; DBM Circular Letter No. 2022-14; COA’s 2023 and 2025 audit reports on DepEd.